Construction Planning and Scheduling

Chapter 7
Probabilistic Scheduling and Schedule Risk Analysis

Bachelors Program in Construction Technology
Construction Planning and Scheduling   •   Bachelor

Probabilistic Scheduling and Schedule Risk Analysis

Introduction

Construction schedules are forecasts made under uncertainty. Weather, productivity, design development, material availability, labour performance, plant breakdowns, inspections, and unforeseen site conditions can all cause actual durations to differ from planned durations. A deterministic schedule assigns one duration to each activity and produces one completion date. This is useful for coordination, but it can create false confidence when uncertainty is significant.

Probabilistic scheduling represents activity durations as ranges or probability distributions. It therefore answers questions such as:

  • What is the expected project duration?
  • What is the probability of completing by a contractual date?
  • Which activities contribute most to completion-date risk?
  • How much time contingency is justified?
  • Which mitigation actions provide the greatest reduction in risk?

The principal techniques covered in this chapter are three-point estimating, the Program Evaluation and Review Technique (PERT), risk registers, sensitivity analysis, Monte Carlo simulation, contingency determination, and confidence-based forecasting. These tools do not eliminate uncertainty; they make uncertainty visible and support more defensible decisions.

Learning Objectives

By the end of this chapter, a student should be able to:

  1. Distinguish deterministic and probabilistic schedules.
  2. Develop optimistic, most-likely, and pessimistic activity estimates.
  3. Calculate PERT expected durations and approximate variances.
  4. Explain the assumptions and limitations of PERT.
  5. Construct and use a schedule risk register.
  6. Apply sensitivity analysis to identify schedule drivers.
  7. Explain the logic of Monte Carlo simulation and interpret confidence levels.
  8. Distinguish activity contingency, project time contingency, and management reserve.
  9. Communicate completion forecasts using probability rather than a single unsupported date.
  10. Evaluate professional, ethical, and governance implications of schedule risk reporting.

1. Deterministic and Probabilistic Scheduling

A deterministic schedule uses a single duration, such as 15 days, for each activity. Its critical path and completion date are calculated from these fixed values. The method is transparent and easy to update, but it treats an uncertain estimate as if it were a fact.

A probabilistic schedule assigns an uncertain duration to an activity. The duration may be represented by a range, a discrete set of outcomes, or a continuous probability distribution. Repeated analysis produces a distribution of possible project completion dates rather than one date.

The distinction is important:

FeatureDeterministic scheduleProbabilistic schedule
Activity durationOne valueDistribution or range
OutputOne principal finish dateRange and probability distribution
Main useBaseline coordinationRisk-informed forecasting
CriticalityUsually one critical pathCriticality may vary across simulations
UncertaintyOften implicitExplicitly modelled

Probabilistic scheduling is especially valuable during early design, procurement planning, major infrastructure work, complex interfaces, and projects with contractual completion exposure.

2. Three-Point Estimating

Three-point estimating uses three duration estimates for an activity:

  • Optimistic duration, a: the duration under favourable conditions, normally assuming few disruptions.
  • Most-likely duration, m: the duration judged most plausible under expected conditions.
  • Pessimistic duration, b: the duration under adverse but credible conditions.

These values are not necessarily minimum, typical, and absolute maximum durations. They should represent a realistic range supported by construction knowledge, historical data, productivity records, supplier information, and explicit assumptions.

2.1 Triangular estimating

The simplest approach assumes a triangular distribution. Its mean is:

μ = (a + m + b) ÷ 3

where μ is the estimated mean duration and a, m, and b are expressed in the same time units. This formula is appropriate when the three points are treated as the lower limit, mode, and upper limit of a triangular distribution.

The approximate variance of a triangular distribution is:

σ² = (a² + m² + b² − am − ab − mb) ÷ 18

where σ² is in squared time units. The standard deviation is σ = √σ².

2.2 PERT beta approximation

PERT uses a weighted average that gives greater emphasis to the most-likely estimate:

te = (a + 4m + b) ÷ 6

Here, te is the PERT expected duration. A commonly used approximation for the standard deviation is:

σ = (b − a) ÷ 6

and therefore:

σ² = ((b − a) ÷ 6)²

The PERT formulas are approximations based on a beta-shaped distribution bounded by a and b. They are useful when expert estimates are available but detailed historical data are limited. They should not be interpreted as proof that the real duration distribution is beta-shaped.

Worked Example 1: PERT activity estimate

Suppose formwork for a floor is estimated as follows:

  • a = 8 days
  • m = 12 days
  • b = 20 days

The expected duration is:

te = (8 + 4(12) + 20) ÷ 6 = 76 ÷ 6 = 12.67 days

The standard deviation is:

σ = (20 − 8) ÷ 6 = 2 days

The variance is 4 days². The result does not mean that the activity will take exactly 12.67 days. It is an expected value used for risk analysis.

Good estimating practice

Three-point estimates should be accompanied by assumptions. For example, “optimistic” may assume two crews and uninterrupted material delivery, while “pessimistic” may include one week of rain and a delayed inspection. If assumptions are not recorded, later users may mistake a risk-conditioned estimate for an unconditional duration.

Estimates should also be calibrated. A team that consistently gives optimistic estimates should review completed-project data and adjust its estimating process. Estimates must not be manipulated to produce a desired completion probability.

3. Network Logic and Expected Project Duration

A project network represents precedence relationships. If Activity B cannot start until Activity A finishes, A precedes B. For a simple serial path, expected durations are added:

E[Tpath] = ∑ tei

where tei is the expected duration of activity i on the path.

If activity durations on the path are treated as independent, path variance is:

Var(Tpath) = ∑ σ²i

and path standard deviation is:

σpath = √(∑ σ²i)

The units are consistent: durations are measured in days, variances in days², and standard deviation in days.

For a simple serial path, an approximate completion probability can be calculated using a normal approximation:

Z = (D − μpath) ÷ σpath

where D is the target duration, μ_path is the expected path duration, σ_path is its standard deviation, and Z is a standardised value. The probability is then obtained from the cumulative standard normal distribution, written as Φ(Z):

P(Tpath ≤ D) ≈ Φ(Z)

This approximation is most defensible when the path contains several activities, no dominant correlation exists, and the resulting distribution is reasonably close to normal. It is not generally reliable for a complete project network with parallel paths, changing critical paths, or strongly skewed activity distributions.

Worked Example 2: Serial path probability

A procurement path contains three independent activities with the following PERT estimates:

Activityte (days)σ (days)
Shop drawings101.5
Review and approval82.0
Fabrication203.0

Thus:

μpath = 10 + 8 + 20 = 38 days
σpath = √(1.5² + 2.0² + 3.0²) = √15.25 ≈ 3.91 days

For a 42-day target:

Z = (42 − 38) ÷ 3.91 ≈ 1.02

A standard normal table gives Φ(1.02) ≈ 0.846. Under the stated assumptions, the approximate probability of completing this serial path within 42 days is therefore 84.6%.

4. Limits of the Critical Path and PERT

In a deterministic schedule, the critical path is the longest path through the network based on fixed durations. In a probabilistic schedule, the path that is critical in one simulation may not be critical in another. A near-critical path may become critical when one of its activities experiences delay.

PERT has several important limitations:

  1. Distributional approximation: The beta assumption may not represent actual construction durations.
  2. Independence assumption: Adding variances assumes activity durations are independent. Shared weather, labour shortages, or common suppliers can create correlation.
  3. Path approximation: Calculating the probability of one path does not automatically calculate the probability of completing the entire network.
  4. Estimate quality: Mathematical precision cannot compensate for poor a, m, and b estimates.
  5. Network quality: Missing logic, incorrect constraints, and excessive use of lags distort the analysis.
  6. Risk omission: A duration range may not adequately represent discrete events such as a major permit failure or utility conflict.

Consequently, PERT is best used as a transparent approximation and screening method. For significant projects, simulation and expert review should supplement it.

5. Schedule Risk Registers

A schedule risk register is a controlled record of uncertain events and conditions that may affect planned dates. It should be integrated with the project risk-management process rather than maintained as an isolated spreadsheet.

A useful schedule risk register contains:

FieldPurpose
Risk IDUnique reference
DescriptionCause, event, and effect stated clearly
Affected activitiesLinks risk to the schedule network
ProbabilityLikelihood of occurrence
ImpactExpected effect on duration or dates
TriggerObservable early-warning condition
OwnerPerson accountable for response
ResponseAvoid, mitigate, transfer, accept, or exploit
Residual riskRisk remaining after response
Status and review dateGovernance and monitoring

A strong description follows a cause–event–effect structure: “Because the long-lead switchgear supplier has limited production capacity, delivery may be delayed, causing energisation and commissioning to move later.” This is more useful than “supplier risk.”

Probability-impact scoring can prioritise attention, but a risk score is not itself a probability distribution. For example, multiplying a five-point probability score by a five-point impact score creates a ranking index, not a statistically valid expected delay unless the scales have been explicitly calibrated.

Threats, opportunities, and discrete risks

Most schedule discussions focus on threats, but opportunities also matter. An alternative construction method, early release of design information, or additional prefabrication capacity may shorten the schedule. Discrete risks should be modelled separately from ordinary activity variability when appropriate. For example, ordinary concrete-placement productivity may be represented by a duration distribution, while a low-probability permit suspension may be represented as an event that adds 10 to 20 days if it occurs.

6. Sensitivity Analysis

Sensitivity analysis examines how changes in assumptions affect the forecast. It helps identify where management effort is likely to have the greatest value.

Common methods include:

  • One-at-a-time analysis: Change one duration or risk assumption while holding others constant.
  • Tornado analysis: Rank inputs by their effect on completion date or a selected percentile.
  • Scenario analysis: Compare coherent cases such as normal, accelerated, and disrupted delivery.
  • Correlation testing: Examine whether common causes affect several activities together.
  • Criticality analysis: Record the percentage of simulations in which an activity lies on the critical path.
  • Schedule sensitivity index: Relate variation in an activity to variation in project completion, commonly using correlation or regression measures.

Sensitivity is not the same as criticality. An activity can be critical in many simulations but have little duration variation; it may be consistently important but not a major source of uncertainty. Conversely, a highly variable activity may have low criticality if it has substantial float.

7. Monte Carlo Simulation Principles

Monte Carlo simulation estimates the distribution of project outcomes by repeatedly sampling uncertain inputs and recalculating the schedule network.

A typical procedure is:

  1. Define a logically sound baseline schedule.
  2. Assign distributions to uncertain activity durations and discrete risks.
  3. Define correlations where common causes create dependence.
  4. Sample one duration for each uncertain activity.
  5. Calculate early and late dates using the sampled values.
  6. Record the project completion date and other outputs.
  7. Repeat the process many times.
  8. Summarise the resulting distribution using percentiles, probabilities, and sensitivity measures.

The simulation does not “predict” one inevitable date. It produces conditional results based on the network, distributions, correlations, calendars, constraints, and risk events supplied by the analyst.

Probability distributions

A distribution should reflect the type and quality of evidence available. A triangular distribution is simple and transparent. A beta-PERT distribution can represent a bounded range with a most-likely value. Empirical distributions based on historical data may be preferable when sufficient reliable observations exist. Lognormal or other skewed distributions may be appropriate for activities where delay is bounded on the early side but can become substantially longer than the central estimate.

The selected distribution should not be chosen merely because it gives a desirable completion date. It should be justified by data, physical constraints, expert judgement, and sensitivity testing.

Correlation

If several activities are affected by the same rainfall period, labour shortage, or design-review bottleneck, treating them as independent can understate risk. Correlation measures the tendency of variables to vary together. Perfect positive correlation means they move together in a fixed standardised relationship; zero correlation means no linear association, although other dependence may still exist.

Correlation should be used carefully. Inventing high correlations without evidence can overstate risk, while ignoring common causes can understate it. Workshops with experienced planners, analysis of historical data, and explicit common-cause risk factors are useful approaches.

Interpreting simulation output

Important outputs include:

  • P10: A date or duration that approximately 10% of simulated outcomes meet or beat.
  • P50: The median; approximately half of outcomes meet or beat it.
  • P80 or P90: More conservative dates with approximately 80% or 90% probability of meeting the target, subject to model quality.
  • Probability of meeting a fixed date: The proportion of simulations finishing on or before that date.
  • P-value of an activity: The percentage of simulations in which the activity is critical, where the software defines criticality consistently.

Percentiles are not guarantees. An “80% confidence date” means that, under the model and assumptions, approximately 80% of simulated outcomes finish on or before that date. It does not mean an 80% contractual guarantee.

8. Contingency and Confidence-Based Forecasting

Time contingency is additional time provided for identified uncertainty. It should be distinguished from hidden padding, arbitrary management reserve, and float already present in the logic.

Common forms include:

  • Activity contingency: Allowance associated with a particular uncertain activity.
  • Path or phase contingency: Allowance for uncertainty in a connected work package.
  • Project time contingency: Additional time between the expected completion and an approved target or commitment.
  • Management reserve: Time or budget controlled by authorised management for unknown-unknowns or changes in scope, where the governance system permits it.

Contingency can be derived from a selected percentile. If the expected or median completion is μ and a chosen percentile is Q_p, then the percentile-based time allowance is conceptually:

Cp = Qp − μ

where C_p is the allowance above the selected central forecast. The subtraction is meaningful only when both values use the same calendar, logic, scope, and status date. A P80 contingency is not automatically equal to 0.84 standard deviations; that shortcut applies only to a normal distribution and does not generally apply to a simulated project network.

A practical governance process should state:

  1. the confidence level selected;
  2. whether the date is a working forecast or contractual commitment;
  3. which risks are included;
  4. whether mitigation actions are assumed complete;
  5. who owns the contingency; and
  6. the conditions for releasing or consuming it.

Using all contingency early without investigating the causes of variance is poor control. Conversely, concealing contingency to make a bid appear shorter undermines trust and can create unsafe acceleration pressure.

9. Illustrative Case: Regional Health Centre Construction

The following is a fictional illustrative case.

Background

A contractor is planning a 24-month regional health centre containing a reinforced-concrete frame, mechanical and electrical systems, medical-gas installation, specialist equipment, testing, and authority inspections. The contractual completion date is 30 June. The deterministic baseline shows completion on 15 June, apparently providing 15 calendar days of float.

Problem

The project director is concerned that the baseline does not reflect uncertainty in switchgear procurement, façade access, design approvals, and integrated commissioning. The client wants to know whether 30 June represents a high-confidence commitment or merely an optimistic target.

Analysis

The team validates the logic and identifies three major paths:

  1. structure and enclosure;
  2. medical systems and specialist equipment; and
  3. electrical energisation and integrated commissioning.

Three-point estimates are obtained from package managers and checked against historical productivity. A risk register records potential design-review delays, a switchgear delivery event, wet-weather effects on façade work, and late authority inspection. The team identifies common exposure to design approvals and models it as a correlated risk factor rather than four independent delays.

A 10,000-iteration Monte Carlo simulation is run using the approved calendars and current mitigation assumptions. The resulting completion distribution is summarised as follows:

OutputForecast
P50 completion22 June
P80 completion12 July
P90 completion24 July
Probability of completing by 30 June63%

The electrical path is critical in 48% of iterations, the medical-systems path in 31%, and the enclosure path in 17%. The remaining iterations have another path or tie condition as critical. Sensitivity analysis shows that switchgear delivery, integrated commissioning productivity, and authority inspection timing are the strongest contributors to completion-date variance.

Approach and solution

The team does not simply add the difference between 15 June and 12 July to the baseline. Instead, it adopts the P80 date as the internal control forecast, subject to client approval, and develops responses:

  • release switchgear technical data earlier;
  • obtain a supplier manufacturing-progress report every two weeks;
  • create a factory acceptance-test hold point;
  • sequence partial energisation where safe and permitted;
  • conduct progressive commissioning by system;
  • engage the authority early regarding inspection documentation; and
  • update the simulation monthly using actual progress and revised estimates.

The risk register identifies owners and triggers. For example, failure to achieve 60% switchgear manufacture by a specified date triggers a recovery review rather than waiting for the delivery failure itself.

Outcome

The first simulation establishes that the contractual date is possible but not highly reliable. After mitigation, the updated model increases the probability of completing by 30 June to 76%, while the P80 date moves to 6 July. The project team communicates both dates: 30 June remains the contractual objective, while 6 July is the risk-informed internal planning date until further evidence is obtained.

Learning points

The case demonstrates that:

  • a deterministic 15-day float was not equivalent to 15 days of risk protection;
  • criticality can shift between paths;
  • a risk register must connect events to activities and responses;
  • mitigation should change the model only when it changes an assumption or distribution;
  • confidence dates are more informative than an unsupported single forecast; and
  • simulation outputs require professional judgement and transparent governance.

10. Technology, Data, and AI

Modern scheduling systems can import activity histories, calculate distributions, run simulations, and display probability curves. Digital twins and integrated project-control platforms may connect schedule risk with quantities, procurement status, cost, and field production data.

AI can assist with extracting delay signals from daily reports, identifying recurring causes, comparing current productivity with historical patterns, and proposing candidate risks. However, AI-generated estimates require validation. Construction data are often incomplete, inconsistently coded, and affected by project-specific conditions. An algorithm may reproduce historical bias, confuse correlation with causation, or provide unjustified confidence. Human planners remain responsible for model assumptions, approvals, and communication.

Good data governance includes version control, traceable source data, documented calendars, consistent activity coding, access controls, and an audit trail for changes to distributions and correlations.

11. Professional, Ethical, and Governance Considerations

Schedule risk analysis affects tender commitments, payment, claims, workforce planning, safety, and public confidence. Professionals should therefore:

  • report uncertainty honestly rather than selecting assumptions to meet a promised date;
  • distinguish fact, estimate, assumption, and judgement;
  • avoid double-counting risks already included in activity distributions;
  • document exclusions and model limitations;
  • protect commercially sensitive and personal data;
  • avoid using acceleration assumptions that create unsafe working conditions;
  • ensure that contractual reporting definitions match the analytical calendar; and
  • obtain appropriate review before using probabilistic results for major decisions.

A forecast is credible when another competent analyst can understand how it was produced and challenge its assumptions.

12. Best-Practice Workflow

A robust schedule risk analysis can follow this sequence:

  1. Confirm scope, work breakdown structure, calendars, status date, and schedule logic.
  2. Remove open-ended activities, invalid constraints, and unexplained excessive lags.
  3. Review historical performance and identify uncertainty sources.
  4. Obtain documented three-point estimates from responsible specialists.
  5. Separate ordinary variability from discrete risk events.
  6. Record risks, triggers, owners, responses, and residual exposure.
  7. Define correlations and common-cause risks explicitly.
  8. Run a preliminary simulation and check the output for plausibility.
  9. Perform sensitivity and scenario analysis.
  10. Select a confidence level appropriate to the decision and risk appetite.
  11. Approve contingency through governance rather than hiding it in activities.
  12. Update the model as actual progress and risk conditions change.

Challenges and Limitations

Probabilistic scheduling is not a substitute for sound planning. Its results may be misleading when the baseline logic is incomplete, estimates are politically influenced, risks are omitted, distributions are unsupported, or correlations are ignored. Simulation can also create an illusion of sophistication: a graph with thousands of iterations is not necessarily more credible than a carefully reasoned expert estimate.

The method is also sensitive to scope change. When design development changes the work, old distributions and risk registers may no longer apply. The model should be treated as a decision-support instrument that evolves with the project, not as a permanent truth.

Chapter Summary

Probabilistic scheduling represents uncertain activity durations and risk events explicitly, producing completion probabilities rather than a single deterministic date. Three-point estimates use optimistic, most-likely, and pessimistic values. PERT calculates an approximate expected duration using te = (a + 4m + b) ÷ 6 and commonly estimates standard deviation as σ = (b − a) ÷ 6. For a simple independent serial path, expected durations are added and variances may be summed, but full project networks require caution because paths can change and activities may be correlated.

A schedule risk register links causes, events, effects, activities, probabilities, impacts, triggers, owners, and responses. Sensitivity analysis identifies the assumptions and activities that most influence completion. Monte Carlo simulation repeatedly samples uncertain inputs and recalculates the network, producing P50, P80, P90, and date-probability outputs. Confidence-based contingency should be governed transparently and must not be confused with hidden padding or guaranteed performance.

The quality of a risk forecast depends primarily on schedule logic, estimate quality, risk identification, correlation assumptions, data governance, and professional judgement. Probabilistic results are most valuable when they support timely mitigation and honest communication.

Key Terms

Three-point estimate: An estimate expressed as optimistic, most-likely, and pessimistic durations.

Optimistic duration: Duration under favourable but credible conditions.

Most-likely duration: Duration judged most plausible under expected conditions.

Pessimistic duration: Duration under adverse but credible conditions.

PERT: A probabilistic estimating technique using a weighted three-point average.

Expected duration: The probability-weighted central duration used in analysis.

Variance: A measure of dispersion expressed in squared time units.

Standard deviation: The square root of variance, expressed in time units.

Probability distribution: A model describing possible values and their likelihoods.

Risk register: A controlled record of risks, impacts, responses, owners, and status.

Discrete risk: An uncertain event that occurs or does not occur and may add a specific delay.

Correlation: A measure of association between uncertain variables.

Monte Carlo simulation: Repeated random sampling and schedule recalculation.

Sensitivity analysis: Analysis of how output changes when inputs or assumptions change.

Criticality: The frequency with which an activity or path is critical in simulations.

Percentile: A value below which a specified proportion of outcomes falls.

Contingency: Time allowance for identified uncertainty.

Management reserve: Controlled allowance for authorised uncertainty outside the normal baseline.

Confidence-based forecast: A completion date associated with a stated probability of achievement.

Review Questions

Short Answer Questions

  1. What is the principal difference between a deterministic and a probabilistic schedule?
  2. Define optimistic, most-likely, and pessimistic activity durations.
  3. State the PERT expected-duration formula and identify its variables.
  4. Why can the critical path change during a Monte Carlo simulation?
  5. What does a P80 completion date mean?

Long Answer Questions

  1. Explain the assumptions and limitations of using PERT for construction activity durations.
  2. Describe the essential fields of a schedule risk register and explain how they support control.
  3. Explain how correlation between activities can affect a project completion forecast.
  4. Compare activity contingency, project time contingency, and management reserve.
  5. Describe a complete workflow for conducting a schedule risk analysis on a major construction project.

Analytical / Application Questions

  1. An activity has a = 6 days, m = 10 days, and b = 18 days. Calculate its PERT expected duration, standard deviation, and variance. State the units and assumptions.
  2. A project has a contractual completion date with a simulated probability of 58%. Recommend what additional information, mitigation, or governance actions should be considered before accepting the date.
  3. A simulation identifies a procurement activity as critical in 35% of iterations and commissioning as critical in 55%, but procurement has the greater duration variance. Explain why these findings are not contradictory and recommend how the team should respond.

Multiple Choice Questions with Answers

Question 1

Which formula is the standard PERT approximation for expected activity duration?

A. te = (a + m + b) ÷ 3

B. te = (a + 4m + b) ÷ 6

C. te = (a + 2m + b) ÷ 4

D. te = (a + b) ÷ 2

Correct Answer: B. te = (a + 4m + b) ÷ 6

Question 2

An activity has optimistic duration 5 days and pessimistic duration 17 days. Using the common PERT approximation, what is its standard deviation?

A. 1 day

B. 2 days

C. 3 days

D. 6 days

Correct Answer: B. 2 days

Question 3

What does a P80 completion date indicate?

A. The project will certainly finish on that date.

B. The project will finish exactly 80 days after start.

C. Approximately 80% of modelled outcomes finish on or before that date.

D. The date has an 80% cost overrun probability.

Correct Answer: C. Approximately 80% of modelled outcomes finish on or before that date.

Question 4

Why is correlation important in schedule risk analysis?

A. It removes all uncertainty from activity estimates.

B. It represents common causes that may affect activities together.

C. It guarantees that the critical path remains unchanged.

D. It converts durations from days to weeks.

Correct Answer: B. It represents common causes that may affect activities together.

Question 5

For independent activities on a simple serial path, which quantity is normally summed to obtain path variance?

A. Standard deviations

B. Expected durations

C. Individual variances

D. Completion probabilities

Correct Answer: C. Individual variances

Question 6

Which item is most appropriate for a schedule risk register?

A. A risk owner and an observable trigger

B. Only the project budget code

C. The contractor’s office address

D. A fixed guarantee that the risk cannot occur

Correct Answer: A. A risk owner and an observable trigger

Question 7

What is the main purpose of sensitivity analysis?

A. To identify inputs that strongly influence the forecast.

B. To eliminate the need for a logical schedule.

C. To replace all expert judgement with random numbers.

D. To ensure every activity becomes critical.

Correct Answer: A. To identify inputs that strongly influence the forecast.

Question 8

Which statement best describes Monte Carlo simulation?

A. It calculates one duration using only the most-likely estimate.

B. It repeatedly samples uncertain inputs and recalculates the schedule.

C. It removes discrete risks from the model.

D. It assumes every activity is perfectly correlated.

Correct Answer: B. It repeatedly samples uncertain inputs and recalculates the schedule.

Question 9

A path has expected duration 38 days and standard deviation 3.91 days. What is its approximate Z value for a 42-day target?

A. 0.51

B. 1.02

C. 3.91

D. 42.00

Correct Answer: B. 1.02

Question 10

Which practice is most ethically appropriate when presenting a probabilistic forecast?

A. Report only the most favourable percentile.

B. Hide contingency inside unexplained activity durations.

C. State assumptions, inclusions, limitations, and the selected confidence level.

D. Describe a P80 date as a guaranteed completion date.

Correct Answer: C. State assumptions, inclusions, limitations, and the selected confidence level.