Construction Law and Contracts

Chapter 10
Risk Allocation, Insurance and Exceptional Events

Bachelors Program in Construction Technology
Construction Law and Contracts   •   Bachelor

Risk Allocation, Insurance and Exceptional Events

Introduction and Context

Construction projects operate in an environment of uncertainty. Ground conditions may differ from surveys, designs may contain errors, materials may become unavailable, extreme weather may interrupt work, and third parties may suffer loss. Construction contracts therefore do more than describe the works and price: they allocate risks among the employer, contractor, consultants, suppliers, insurers and sometimes public authorities.

Risk allocation is the contractual process of deciding who bears the consequences of an uncertain event. A sound allocation normally places a risk with the party best able to control it, insure it, estimate it, or absorb its consequences. Poor allocation can produce inflated prices, disputes, uninsured losses and project failure.

This chapter examines contractual risk matrices, insurance, indemnities, force majeure, frustration and change-in-law provisions. The discussion uses general common-law and international construction principles. Because construction law varies by jurisdiction, the governing law, legislation, standard form and judicial interpretation must always be checked before professional reliance.

Learning Objectives

By the end of this chapter, a student should be able to:

  1. Explain the relationship between risk identification, allocation and pricing.
  2. Evaluate contractual treatment of site conditions, design, materials, damage and third-party risks.
  3. Distinguish insurance, indemnity, limitation of liability and guarantee mechanisms.
  4. Interpret force majeure, exceptional-event, frustration and change-in-law provisions.
  5. Prepare and review a practical project risk matrix.
  6. Analyse a disputed event and recommend appropriate contractual and governance responses.

1. The Logic of Contractual Risk Allocation

A construction contract converts uncertainty into obligations, procedures and financial consequences. Risk allocation is not simply a list of adverse events. It answers five questions:

  • What event has occurred or may occur?
  • Which party controls or influences it?
  • Who bears the cost, delay and performance consequences?
  • What notice, evidence and mitigation are required?
  • Is the risk transferred through price, insurance, indemnity or a contractual relief mechanism?

A risk can be allocated expressly or implicitly. Express allocation appears in clauses concerning site information, weather, design responsibility, title, care of the works, compensation events, force majeure or changes in law. Implicit allocation may arise from the general scope of work, the standard of care, conditions precedent, payment provisions or the common-law rules governing breach and causation.

Risk allocation principles

The following principles are useful, although none overrides the contract or mandatory law:

PrinciplePractical implication
ControlAllocate a risk to the party able to prevent or manage it.
KnowledgeAllocate concealed information risks to the party with superior information or investigation access.
InsurabilityAllocate fortuitous physical risks to the party able to obtain suitable insurance.
PricingA party accepting a risk should be able to price it rationally.
ProximityThe party closest to the event or affected activity may be best placed to respond.
CausationLiability should reflect the party’s act, omission or contractual responsibility.
ProportionalityExposure should not be unlimited or disproportionate to the risk.
EvidenceThe contract should specify records and notice needed to establish entitlement.

A risk allocation is commercially credible only when it is aligned with the contract price, programme, resources and available insurance. Transferring every conceivable risk to a contractor does not eliminate the risk; it may merely cause a contingency premium, defensive conduct, insolvency or later dispute.

2. The Contractual Risk Matrix

A risk matrix is a structured register connecting an event with responsibility, consequence and response. It should be prepared during procurement and updated during construction. A useful matrix includes:

Risk eventLikely causePrimary risk bearerCost consequenceTime consequenceInsurance or reliefRequired evidence
Differing ground conditionUnforeseen soil or groundwaterDepends on contractInvestigation, redesign, additional workPossible extensionSpecific differing-site-condition clause; sometimes insuranceSite records, photographs, test results
Design errorDefective employer or contractor designDesign-responsible partyRework and lossDelay and disruptionProfessional indemnity insuranceDesign documents, review records
Material price escalationMarket volatilityUsually contractor unless adjustedIncreased procurement costPossible delayPrice-adjustment clause, rarely insuranceQuotations, indices, supplier notices
Damage to worksFire, flood, theft or accidental damageParty having care of works, subject to contractRepair or replacementReconstruction delayContractors’ all-risks insuranceIncident report, policy notice
Injury to third partySite operationsResponsible party or shared by contractCompensation and defence costsSuspension and reputational effectsPublic liability insurance and indemnityStatements, site records, medical evidence
Exceptional eventWar, epidemic, government restrictionContract-definedUnallocated or sharedExtension, suspension or terminationUsually not ordinary property insuranceOfficial notices and programme analysis

The matrix must distinguish between the risk owner and the party responsible for administering the response. For example, an employer may retain the financial risk of an unforeseen archaeological discovery, while the contractor must notify it, protect the discovery and maintain records.

A risk matrix should also identify residual risk. Even when an insurer responds, deductibles, exclusions, policy limits and uninsured losses remain. Similarly, an indemnity may provide a contractual recovery route but does not guarantee that the indemnifying party is solvent.

Risk scoring

Organisations sometimes score risks according to probability and impact. A simple qualitative scale—low, medium and high—can support discussion, but it should not be mistaken for a legal allocation. A high-scoring risk is not automatically the employer’s or contractor’s responsibility. Scoring assists management; contractual wording determines entitlement.

3. Site Conditions and Existing Information

Site risk is a frequent source of construction disputes. Relevant conditions include geology, groundwater, contamination, utilities, access, adjacent structures, archaeological remains, weather exposure and existing defects.

Site information and reliance

The contract should state:

  • what information the employer provides;
  • whether the contractor may rely on it;
  • whether the contractor must independently investigate;
  • which conditions remain employer risks;
  • the notice procedure for unexpected conditions; and
  • the available remedy, such as additional cost, time, redesign or termination.

A contractor’s general duty to inspect the site does not necessarily mean that it assumes every concealed condition. The legal result depends on the wording, tender documents, express representations, disclaimers and governing law. A clause stating that the contractor has examined all conditions may be powerful, but it may not protect deliberate misrepresentation or override statutory duties.

Differing site conditions

A well-drafted clause normally requires prompt notice, preservation of the condition, access for investigation, mitigation and substantiation of cost and delay. The contractor should avoid disturbing evidence before inspection unless necessary for safety. The employer should respond promptly and avoid directing work informally where a formal instruction is required.

A site condition may be:

  1. Physical and unforeseeable: materially different from information reasonably available at tender.
  2. Known but underestimated: a risk that the contractor accepted through the pricing documents.
  3. Caused by another party: such as inaccurate utility information or late site access.
  4. A contractor means-and-methods issue: ordinarily within the contractor’s control.

The distinction is factual and contractual. Cost records should separate additional labour, plant, materials, subcontractor charges, prolongation and disruption.

4. Design Responsibility and Professional Liability

Design risk must be allocated with precision. The employer may provide a complete design, the contractor may design temporary works or specialist elements, or the project may use a design-and-build model in which the contractor bears broad design responsibility.

Standards of design obligation

A design obligation may require:

  • compliance with drawings and specifications;
  • compliance with performance requirements;
  • compliance with laws, codes and approvals;
  • reasonable skill and care; or
  • achievement of a particular fitness-for-purpose result.

These standards are not equivalent. A reasonable-skill-and-care obligation is generally evaluated by professional practice applicable to the circumstances. A fitness-for-purpose obligation focuses on the promised result and may be more demanding, even where the designer acted carefully. The governing law and express wording are decisive.

The contract should identify responsibility for design coordination, design reviews, constructability, temporary works, interfaces and approval processes. Employer review or approval should not unintentionally transfer design responsibility unless the contract says so, and contractor review should not automatically make the contractor responsible for defects outside its allocated scope.

Professional indemnity insurance

Design consultants and design-responsible contractors commonly maintain professional indemnity insurance. It normally responds to civil liability arising from professional negligence, subject to policy terms, exclusions, limits, deductibles and notification requirements. It is not a substitute for technical competence, and it may not cover intentional wrongdoing, contractual guarantees, pollution or known circumstances.

5. Materials, Procurement and Supply-Chain Risk

Materials risk includes defective products, late delivery, insolvency of suppliers, scarcity, price escalation, transport interruption and substitution. The contract should address approved suppliers, testing, warranties, title, storage, substitution and responsibility for procurement decisions.

The contractor commonly bears ordinary procurement risk because it selects suppliers and coordinates delivery. However, employer-nominated suppliers, employer-provided materials and changes in specifications may shift responsibility. A contractor should not be liable for a defect in employer-provided materials that it could not reasonably detect, although it may still have a duty to inspect and warn.

Price escalation clauses may use a published index, a defined reference date, specified materials and a calculation method. They should state whether adjustment is upward only or symmetrical, whether subcontractor evidence is required and how delay affects entitlement. Without a contractual mechanism, ordinary market inflation is often allocated according to the fixed-price bargain, subject to applicable law and exceptional-event provisions.

6. Damage to the Works, Property and Third Parties

Care of the works

Contracts commonly allocate care of the works until completion, takeover or another defined milestone. The responsible party may have to repair physical loss or damage, except for listed employer risks or events covered through project insurance.

The clause should address:

  • the works and temporary works;
  • materials on and off site;
  • existing structures;
  • contractor’s plant and equipment;
  • adjacent property;
  • damage caused by design defects;
  • damage caused by employer use or occupation; and
  • the effect of partial possession or sectional completion.

Care-of-works provisions must be read with insurance clauses. A party may be contractually responsible even where insurance is unavailable, unless the contract makes insurance the exclusive remedy or otherwise limits responsibility.

Third-party claims

Third parties may include neighbours, road users, utility owners, visitors, employees of other contractors and members of the public. Liability may arise through negligence, nuisance, trespass, statutory breach or contractual obligations owed to the employer.

The contractor should control site access, traffic, lifting operations, excavation, noise, dust, vibration and public protection. The employer should provide accurate information about land rights and known constraints. Indemnities should identify whose acts trigger liability and should not blindly convert every third-party claim into an unlimited contractor obligation.

7. Insurance as a Risk-Transfer Mechanism

Insurance transfers specified financial consequences to an insurer in exchange for a premium. It does not change the physical event and does not automatically determine contractual responsibility.

Common construction policies include:

InsuranceTypical subject
Contractors’ all-risks or builders’ riskPhysical loss or damage to works, subject to exclusions
Public liabilityThird-party bodily injury or property damage
Employers’ liability or workers’ compensationEmployee injury, according to local law
Professional indemnityDesign and professional negligence liability
Contractor’s plant and equipmentLoss or damage to owned or hired equipment
Marine cargo or transit coverMaterials during transportation
Delay in start-up or advance loss of profitCertain financial consequences of insured physical damage
Pollution liabilityEnvironmental risks where specifically insured

Reviewing an insurance clause

A contract reviewer should check:

  1. Who must procure the policy?
  2. Who is insured, jointly insured or named as an additional insured?
  3. What are the limits, deductibles and territorial boundaries?
  4. Are design, defects, testing, terrorism, flood, pollution and existing property covered or excluded?
  5. When must evidence of insurance be supplied?
  6. Who pays the deductible?
  7. Is waiver of subrogation required?
  8. What happens if the insurer denies or delays payment?
  9. Are policy cancellation and renewal requirements addressed?
  10. Does the contract require prompt notification of circumstances and claims?

Insurance obligations should be coordinated with indemnities and limitation clauses. A requirement to obtain insurance for a risk is not always an agreement to cap liability at the policy limit. Conversely, a policy limit is not necessarily the amount recoverable under the contract.

8. Indemnities, Guarantees and Limitations of Liability

An indemnity is a contractual promise to protect another party against a specified loss, claim, damage, cost or liability. Its interpretation depends heavily on wording and applicable law. Important drafting issues include causation, third-party claims, defence control, settlement consent, contributory fault, notice and mitigation.

A guarantee generally concerns performance by another person or entity and may be subject to formal requirements. A parent-company guarantee can provide financial support if a project company fails, but its scope, duration and enforceability must be examined.

Limitations of liability may include:

  • an aggregate financial cap;
  • exclusions of consequential or indirect loss;
  • exclusions for lost profit or revenue;
  • a separate cap for specified risks; and
  • carve-outs for fraud, wilful misconduct, death, personal injury or unpaid sums.

The effectiveness of such clauses is jurisdiction-dependent. Mandatory law may invalidate or restrict exclusions, particularly for personal injury, consumer protection, corruption or deliberate wrongdoing.

9. Force Majeure and Exceptional Events

Force majeure is a contractual doctrine, not a universal legal rule. A force majeure clause defines events and consequences. Typical events include war, terrorism, riot, natural disaster, epidemic, government action, embargo and sometimes extreme weather or industrial action.

A well-structured clause addresses four elements:

  1. Event: the event falls within the stated definition.
  2. Causation: the event prevents, hinders or delays performance as required by the clause.
  3. Control and foreseeability: the event is beyond reasonable control and was not reasonably avoidable, if those conditions apply.
  4. Procedure and consequence: notice, mitigation, continuing updates and relief are specified.

Consequences may include an extension of time, suspension, cost compensation, renegotiation or termination after a prolonged period. Some clauses provide time but no money; others distinguish between employer-risk events and neutral exceptional events.

The affected party usually must mitigate. This may involve resequencing work, obtaining alternative suppliers, protecting materials, using available labour or applying for permits. A party cannot normally rely on force majeure for an event caused by its own breach, poor planning or failure to comply with a contractual prerequisite.

Force majeure versus frustration

Frustration is a legal doctrine arising independently of a contractual force majeure clause in some common-law systems. It may discharge a contract when an unforeseen event, without the fault of either party, makes performance impossible, illegal or radically different from what was agreed. Mere increased expense, reduced profitability or ordinary delay is usually insufficient.

The consequences of frustration are determined by applicable law and may be severe: the contract may end rather than continue with an extension of time. Force majeure, by contrast, operates according to its wording and may preserve the contract through suspension or adjustment. A contract should not assume that a force majeure clause and frustration produce the same result.

10. Change in Law and Government Action

Change-in-law clauses allocate the effect of new or amended legislation, regulations, taxes, permits and binding official requirements after the contractual reference date. They should define:

  • the relevant baseline date;
  • whether changes must be unforeseeable;
  • whether discriminatory or project-specific measures receive special treatment;
  • qualifying cost and delay;
  • notice and substantiation;
  • mitigation and alternatives; and
  • termination rights if compliance becomes impossible or uneconomic.

A contractor may be entitled to time and money where a change directly affects performance. However, ordinary compliance with laws existing at tender is generally part of the contractor’s baseline responsibility unless the contract states otherwise. A change-in-law clause should also distinguish a change in law from a change in interpretation or enforcement.

11. Notices, Records and Claims Administration

Risk allocation fails when entitlement cannot be demonstrated. Contracts commonly require notice within a stated period. The effect of late notice varies: it may be a condition precedent, an evidential requirement or merely an administrative obligation. The wording must be read carefully.

A robust claim file normally includes:

  • event chronology;
  • contract provisions relied upon;
  • contemporaneous correspondence;
  • photographs and site diaries;
  • labour, plant and material records;
  • updated programmes and critical-path analysis;
  • mitigation measures;
  • invoices and subcontractor evidence; and
  • separation of direct cost, prolongation and disruption.

The party administering the contract should respond fairly and promptly. Silence, informal directions and inconsistent records increase dispute risk. Digital field systems, time-stamped photographs, BIM issue logs and electronic procurement records can improve traceability, but records must be accurate, secure and accessible.

12. Applied Case: The Riverside Medical Centre

The following is an illustrative case, not a report of an actual court decision.

Background

An employer engaged a contractor under a design-and-build contract to construct a medical centre. The contract price was fixed, the contractor accepted responsibility for detailed design and procurement, and the employer provided a geotechnical report. The contract contained a differing-site-condition clause, a force majeure clause providing time but generally no cost, a change-in-law clause, contractors’ all-risks insurance and public liability insurance.

Problem

During excavation, the contractor encountered contaminated soil not identified in the report. The contractor notified the employer after four days, isolated the area and requested instructions. At the same time, a specialist façade supplier became insolvent, and a new fire-safety regulation increased the required façade testing. Six weeks later, exceptionally heavy flooding affected the access road. The contractor claimed additional excavation cost, replacement-supplier costs, testing costs and delay damages.

Analysis

The contaminated soil is potentially a differing physical condition. The key questions are whether it was materially different from information reasonably available, whether the contractor’s investigation obligation covers it, and whether notice was timely. The contractor’s isolation and records support mitigation.

The façade supplier’s insolvency is more likely to be a contractor procurement risk because the contractor selected the supplier. The result could differ if the supplier was nominated by the employer or if the insolvency resulted from an employer instruction.

The new fire-safety regulation falls within the change-in-law clause if it occurred after the reference date and directly affected the works. The contractor must show incremental testing cost and delay, while avoiding recovery for compliance that was already required.

The flood may qualify as force majeure if it falls within the clause and prevented or delayed performance. The contractor must show causation, mitigation and critical-path effect. If the flood merely increased cost but did not prevent performance, the clause may provide no monetary relief.

Insurance may respond to physical damage caused by flooding, but it does not necessarily cover contamination remediation, supplier insolvency or regulatory compliance. Policy exclusions and deductibles must be checked.

Approach and solution

The parties should establish a joint event chronology, preserve contaminated-soil evidence, obtain independent environmental testing, and agree a safe excavation instruction. They should separately evaluate the supplier insolvency, regulatory change and flood rather than combine them into one global claim. The programme should identify the effect of each event on critical activities. Costs should be segregated by event and supported by records.

A negotiated agreement might provide an instructed variation for contaminated soil, time and demonstrable testing cost for the change in law, no entitlement for ordinary supplier insolvency, and an extension of time for the flood if the contractual threshold is met. Insurance claims should be notified without admitting liability.

Learning points

The case demonstrates that a single period of delay may contain several legally distinct risks. Causation, notice, mitigation, insurance response and contractual wording must be analysed event by event. A risk matrix prepared at tender would not replace this analysis, but it would reveal which evidence and procedures were required.

13. Governance, Ethics and Contemporary Practice

Risk allocation has ethical as well as commercial consequences. Excessive transfer to a small contractor may undermine fair competition and encourage concealment of problems. Employers and contractors should disclose material site information, avoid misleading tender assumptions and administer claims consistently.

Modern projects increasingly use digital contract-management platforms, BIM coordination, sensor data, satellite weather records and automated document analysis. AI can help classify notices, identify missing records and compare contract obligations, but it cannot reliably determine legal entitlement without contextual interpretation. Human review remains essential, particularly where privileged advice, confidential information or personal data is involved.

Contemporary contracts also address climate-related risks, cyber incidents, supply-chain disruption and sustainability obligations. Extreme weather should not automatically be treated as force majeure; parties must examine historical foreseeability, design resilience and the precise contractual threshold. Cyber insurance and digital-security obligations should be coordinated with physical works insurance and data-protection requirements.

14. Best-Practice Review Framework

Before signing, a project team should:

  1. Identify physical, design, commercial, legal, environmental and third-party risks.
  2. Assign each risk to a named contractual party.
  3. Test whether that party can control, price or insure it.
  4. Confirm the remedy: money, time, variation, suspension or termination.
  5. Align the risk with insurance limits, exclusions and deductibles.
  6. Define notices, records, mitigation and valuation procedures.
  7. Check interfaces between employer, contractor, designer and suppliers.
  8. Review caps, indemnities and carve-outs together rather than separately.
  9. Revisit the matrix at mobilisation, design changes and major events.
  10. Obtain jurisdiction-specific legal and insurance advice for high-value risks.

Chapter Summary

Construction contracts allocate uncertainty through express obligations, insurance, indemnities, limitations and exceptional-event procedures. A risk matrix should identify the event, responsible party, cost and time consequences, available insurance or relief, and required evidence. Site conditions, design, materials, damage and third-party claims require separate analysis because control and information differ across risks.

Insurance transfers specified financial exposure but does not automatically determine contractual responsibility. Indemnities, guarantees and liability caps must be interpreted together and subject to mandatory law. Force majeure is contractual and depends on defined events, causation, control, notice and mitigation. Frustration is a narrower legal doctrine that may discharge a contract. Change-in-law clauses allocate the consequences of new legal requirements according to a defined reference date and procedure. Effective administration depends on timely notices, reliable records, programme analysis and ethical disclosure.

Key Terms

Risk allocation: Assignment of the consequences of uncertainty among contracting parties.

Risk matrix: A structured register identifying risks, owners, consequences and responses.

Differing site condition: A physical condition materially different from that reasonably indicated or expected under the contract.

Design responsibility: Contractual responsibility for producing compliant and adequate design.

Fitness for purpose: An obligation to achieve a specified functional result.

Professional indemnity insurance: Insurance for specified professional negligence liabilities.

Care of the works: Responsibility for physical loss or damage to the works before the contractual transfer milestone.

Indemnity: A promise to compensate or protect another party against specified losses or claims.

Guarantee: A promise concerning performance or payment, often involving a third party.

Limitation of liability: A contractual restriction on the amount or categories of recoverable loss.

Deductible: The portion of an insured loss retained by the insured.

Waiver of subrogation: An agreement restricting an insurer’s recovery rights against specified parties.

Force majeure: A contract-defined event beyond a party’s control that triggers stated relief.

Frustration: A legal doctrine that may discharge a contract when performance becomes radically different or impossible.

Change in law: A new, amended or differently applicable legal requirement affecting performance.

Mitigation: Reasonable action to prevent or reduce loss or delay.

Condition precedent: A contractual requirement that must be satisfied before a right arises.

Critical path: The sequence of activities controlling the earliest completion date.

Residual risk: Exposure remaining after contractual allocation or insurance.

Review Questions

5 Short Answer Questions

  1. What is the purpose of a construction risk matrix?
  2. Why does insurance not automatically determine contractual liability?
  3. State two matters that should be addressed in a force majeure clause.
  4. How does frustration differ from force majeure?
  5. Why are contemporaneous records important in an exceptional-event claim?

5 Long Answer Questions

  1. Explain the principles used to allocate site-condition risk and discuss how notice and investigation obligations affect entitlement.
  2. Compare reasonable skill and care with fitness-for-purpose design obligations.
  3. Discuss the relationship between contractors’ all-risks insurance, care-of-the-works provisions and indemnities.
  4. Analyse the essential elements and possible consequences of a change-in-law clause.
  5. Explain how liability caps, exclusions, indemnities and insurance should be reviewed as an integrated system.

3 Analytical / Application Questions

  1. A contractor encounters undocumented utilities after receiving an employer-prepared site report. Prepare an issue analysis identifying possible risk allocation, evidence, notices and remedies.
  2. A government restriction delays a project, but the contractor had already failed to order critical materials. Analyse whether force majeure relief should be available for the whole delay.
  3. Using the Riverside Medical Centre case, separate the claims into site condition, procurement, change-in-law, flood and insurance issues, and recommend a fair contractual resolution for each.

Multiple Choice Questions with Answers

Question 1

Which principle generally supports allocating a risk to the party best able to prevent or manage it?

A. Control

B. Severability

C. Privity

D. Liquidation

Correct Answer: A. Control

Question 2

What is the primary purpose of a differing-site-condition clause?

A. To guarantee contractor profit

B. To address physical conditions materially different from those reasonably indicated or expected

C. To eliminate all site investigation duties

D. To replace public liability insurance

Correct Answer: B. To address physical conditions materially different from those reasonably indicated or expected

Question 3

Professional indemnity insurance most directly concerns liability arising from:

A. Ordinary material price inflation

B. Professional negligence in design or advice

C. Every flood affecting a site

D. Supplier insolvency in all circumstances

Correct Answer: B. Professional negligence in design or advice

Question 4

Which statement best describes force majeure?

A. It is always an implied rule requiring payment of all losses

B. It is a contractual mechanism whose effect depends on its wording

C. It automatically terminates every construction contract

D. It applies only to design errors

Correct Answer: B. It is a contractual mechanism whose effect depends on its wording

Question 5

What is a common consequence of frustration in common-law systems?

A. Automatic entitlement to unlimited damages

B. Discharge of the contract when performance becomes radically different or impossible

C. Mandatory price escalation

D. Transfer of all risks to the insurer

Correct Answer: B. Discharge of the contract when performance becomes radically different or impossible

Question 6

Which item is especially important when reviewing an insurance obligation?

A. The contractor’s preferred project logo

B. Policy limits, exclusions and deductibles

C. The colour of site fencing

D. The employer’s annual leave policy

Correct Answer: B. Policy limits, exclusions and deductibles

Question 7

A change-in-law clause should normally identify:

A. A contractual reference date

B. Only the contractor’s preferred suppliers

C. The colour of approved materials

D. The personal views of the project manager

Correct Answer: A. A contractual reference date

Question 8

Why should claims arising from several events be analysed separately?

A. Different events may have different contractual rules, causes and remedies

B. Combined claims are always illegal

C. Insurance never applies to separate events

D. Separate analysis removes the need for evidence

Correct Answer: A. Different events may have different contractual rules, causes and remedies

Question 9

Which action is an example of mitigation?

A. Ignoring an available alternative supplier

B. Preserving evidence and resequencing work where reasonably possible

C. Destroying site records after an incident

D. Waiting until completion before giving any notice

Correct Answer: B. Preserving evidence and resequencing work where reasonably possible

Question 10

What does a deductible represent?

A. The insurer’s maximum possible profit

B. The portion of an insured loss retained by the insured

C. A guaranteed contractor bonus

D. A statutory tax on construction materials

Correct Answer: B. The portion of an insured loss retained by the insured

Construction Law and Contracts
Chapter 10 of 15