Construction Equipment and Methods

Chapter 13
Operations Planning, Fleet Management, and Reliability

Bachelors Program in Construction Technology
Construction Equipment and Methods   •   Bachelor

Operations Planning, Fleet Management, and Reliability

Introduction and Context

Construction equipment creates value only when it is available, correctly matched to the work, economically operated, and coordinated with labour, materials, drawings, traffic routes, and safety controls. A machine may have high rated capacity yet contribute little if it waits for trucks, travels excessive distances, lacks fuel, or fails during a critical activity. Operations planning therefore connects productivity estimates with the project schedule and converts individual equipment decisions into a managed production system.

Fleet management is the systematic planning, acquisition, allocation, operation, maintenance, replacement, and disposal of construction equipment. Reliability management extends this responsibility by reducing failures, controlling downtime, and learning from operating data. Together, these disciplines support cost, time, quality, safety, environmental, and contractual objectives.

The central managerial question is not simply “How many machines are available?” It is: “Can the required work be produced at the required rate, with acceptable risk and life-cycle cost?”

Learning Objectives

After studying this chapter, students should be able to:

  1. Integrate equipment productivity with activity schedules and resource-loaded programmes.
  2. Develop practical fleet plans using capacity, cycle time, utilization, and balancing principles.
  3. Design site logistics and dispatching arrangements that reduce waiting and interference.
  4. Distinguish corrective, preventive, predictive, and reliability-centred maintenance.
  5. Calculate and interpret availability, utilization, mean time between failures, and mean time to repair.
  6. Plan spare parts, fuel, data collection, and telematics systems.
  7. Select meaningful key performance indicators and use continuous-improvement methods.
  8. Evaluate the technical, financial, ethical, and safety implications of equipment decisions.

1. From Productivity Estimate to Operating Plan

A productivity estimate describes potential output under specified conditions. An operating plan states how that potential will be achieved in a particular project. The estimate must therefore be adjusted for material characteristics, operator skill, weather, traffic, haul distance, job layout, interruptions, maintenance, and safety constraints.

For a repetitive operation, basic production can be estimated as:

Q = q × n × η × 60 / C

where:

  • Q = production rate, usually m³/h, tonnes/h, or units/h;
  • q = quantity produced per cycle by one machine;
  • n = number of similar machines;
  • η = operating efficiency, expressed as a decimal;
  • C = average cycle time in minutes.

The equation assumes that cycle conditions are reasonably stable and that η captures delays not already included in cycle time. Double-counting delays must be avoided. If the cycle time already includes observed waiting, a separate delay factor should not be applied again.

For a loader filling trucks, for example, the effective truck capacity may be limited by both volume and mass:

q = min(V, W / ρ)

where V is legal or geometric volume, W is allowable payload mass, and ρ is material density. The result must be expressed in consistent units. A truck advertised as having a large body volume cannot legally carry more mass than its permitted payload.

Capacity matching and bottlenecks

A fleet is balanced when the capacities of linked operations are sufficiently compatible. If excavation produces 120 m³/h but hauling can remove only 90 m³/h, the excavation unit will eventually wait or stockpile material. If hauling capacity is 150 m³/h, trucks may wait for loading. The practical system output is governed by the bottleneck:

Qsystem = min(Q1, Q2, …, Qk)

This simplified relationship applies to serial operations where every unit of output must pass through each stage. Buffers, parallel work fronts, and different material streams may modify the analysis, so the project team should examine the actual process rather than rely mechanically on the minimum value.

A useful balancing measure is the ratio of available downstream capacity to upstream capacity:

R = Qdownstream / Qupstream

A ratio below 1 indicates a downstream constraint; a ratio substantially above 1 may indicate excess capacity or poor allocation. Perfect equality is not always desirable because uncertainty, breakdowns, and variable cycle times require some resilience.

Worked example: matching trucks to a loader

A loader fills a 10 m³ truck in 4 minutes. A truck requires 6 minutes to travel loaded, 5 minutes to unload and return, and 1 minute for positioning. Thus, the truck cycle is 16 minutes, including the 4-minute loading period. Assume an operating efficiency of 0.90 and no additional restrictions.

One truck’s effective rate is:

Qt = 10 × 0.90 × 60 / 16 = 33.75 m³/h

The loader’s potential rate when continuously loading is:

Ql = 10 × 0.90 × 60 / 4 = 135 m³/h

Four trucks provide 4 × 33.75 = 135 m³/h. Therefore, four trucks approximately match the loader. In practice, a fifth truck might be justified if traffic variability causes loader starvation, but it could also create queues and higher cost. The decision should be tested using field observations, simulation, or telematics data rather than relying only on nominal cycle times.

2. Schedule Integration and Resource Loading

The construction programme identifies activities, precedence relationships, durations, and milestones. Equipment planning adds the resources needed to perform each activity. A resource-loaded schedule assigns equipment, operators, crews, and sometimes fuel or temporary facilities to time periods.

The process normally follows these steps:

  1. Break the work into measurable activities using the work breakdown structure.
  2. Determine quantities, production rates, and expected working hours.
  3. Calculate resource demand for each activity.
  4. Place demand against the calendar and identify peaks.
  5. Resolve conflicts by changing sequence, shift pattern, fleet size, subcontracting, or methods.
  6. Check access, permits, maintenance windows, environmental restrictions, and operator availability.
  7. Establish a baseline and update it using actual progress and equipment data.

If an activity requires quantity V and has effective production Q, its production duration is:

T = V / Q

where T is time in hours if quantity and production use compatible units. This is a production duration, not necessarily the calendar duration. Calendar duration must also consider shifts, working days, weather allowances, planned interruptions, and resource constraints.

A resource histogram displays demand by time. Peaks can reveal a need to stagger activities, rent equipment, use alternate methods, or negotiate access. However, resource smoothing should not compromise the critical path without an approved schedule change. Resource leveling may extend the project when limited equipment is shared among activities; smoothing attempts to reduce fluctuations while preserving the completion date.

Schedule logic and equipment mobility

Equipment movement is itself a schedule activity. A crane cannot be assumed to be simultaneously available at two work fronts, and a paver or batching plant may require setup, calibration, and cleaning time. Mobilization, demobilization, attachment changes, inspection, and traffic-control installation should be represented explicitly. Omitting these tasks produces an unrealistic plan and encourages unsafe informal movement.

3. Site Logistics and Dispatching

Site logistics is the design and control of physical flows: equipment, people, materials, waste, fuel, information, and emergency access. A logistics plan should show haul roads, turning radii, loading and unloading areas, pedestrian segregation, laydown zones, refuelling points, workshops, washout areas, stockpiles, gates, and one-way routes where appropriate.

Good logistics reduces nonproductive time and risk. Important design principles include:

  • Separate pedestrians and mobile plant using distance, barriers, and controlled crossings.
  • Provide adequate road width, bearing capacity, drainage, visibility, signage, and lighting.
  • Locate loading areas to reduce reversing; where reversing is unavoidable, use a trained banksman and a controlled exclusion zone.
  • Keep emergency routes and fire access unobstructed.
  • Control dust, mud tracking, noise, and contaminated runoff.
  • Place fuel and maintenance facilities according to environmental and fire requirements.
  • Use time windows or appointment systems where several trades share a constrained access point.

Dispatching assigns machines and operators to tasks in response to the plan and current conditions. A dispatch system may be manual, radio-based, or digital. It should identify the machine, operator, location, task, priority, expected duration, and exceptional conditions. A sound dispatching rule is transparent: urgent safety or quality needs take priority over convenience, while repeated ad hoc reassignment should trigger a planning review.

A simple queuing perspective is useful. When arrival demand approaches service capacity, waiting time can increase sharply. Thus, operating a loading point at nominal 100% capacity leaves no allowance for variability. Planned spare capacity may cost less than queues, idle crews, and missed milestones.

4. Fleet Management Decisions

Fleet management covers the entire equipment life cycle:

StageMain decisions
PlanningRequired capacity, duty cycle, terrain, attachments, emissions, and schedule
AcquisitionBuy, lease, rent, subcontract, or share equipment
DeploymentAllocation, transport, commissioning, operator assignment, and controls
OperationDispatch, fuel, production, inspections, and utilization
MaintenanceService intervals, repairs, parts, condition monitoring, and records
ReplacementEconomic life, obsolescence, reliability, and residual value
DisposalSale, transfer, recycling, environmental closure, and documentation

The buy–rent–lease decision should consider total cost, not merely the daily hire rate. Relevant costs include transport, setup, operator training, insurance, financing, maintenance, fuel, downtime, residual value, and contractual flexibility. Ownership may be attractive for sustained utilization and specialized equipment; rental may be superior for short-duration, uncertain, or peak demand.

A basic ownership cost per productive hour can be expressed as:

Ch = (C0 − S + Cm + Ci + Ct) / Hp + Cf

where C0 is acquisition cost, S is residual value at disposal, Cm is maintenance and repair cost over the analysis period, Ci is insurance and registration cost, Ct is taxes and fixed charges, Hp is expected productive hours, and Cf is fuel and variable operating cost per productive hour. This is a simplified average-cost model. Financial analysis should discount future cash flows when comparing alternatives over different lives.

Equipment selection must also account for compatibility. A carrier’s hydraulic flow and pressure must suit an attachment; lifting equipment must satisfy capacity at the required radius and configuration; transport dimensions must comply with route restrictions; and emissions or noise limits may exclude otherwise capable machines.

5. Reliability, Availability, and Maintenance

Reliability is the probability that equipment performs its required function for a specified time under stated conditions. It differs from durability, which concerns resistance to deterioration, and maintainability, which concerns the ease and speed of restoring function.

Maintenance strategies include:

  • Corrective maintenance: repair after failure. It may be reasonable for noncritical, inexpensive, or redundant items, but is risky for safety-critical or schedule-critical assets.
  • Preventive maintenance: service at time, calendar, mileage, engine hours, or cycles. It reduces some failures but can cause unnecessary component replacement if intervals are poorly selected.
  • Predictive or condition-based maintenance: intervene when measurements indicate degradation. Oil analysis, vibration, thermal imaging, pressure trends, fault codes, and battery data are examples.
  • Reliability-centred maintenance (RCM): select tasks according to function, failure consequences, failure mechanisms, and technically feasible controls.
  • Proactive maintenance: remove root causes such as contamination, misalignment, overload, poor lubrication, or operator misuse.

Availability has several definitions. A commonly used inherent availability excludes logistics and administrative delays:

Ai = MTBF / (MTBF + MTTR)

where MTBF is mean time between failures and MTTR is mean time to repair. This assumes alternating operating and repair periods and consistent definitions. Operational availability may include preventive maintenance, waiting for parts, operators, transport, and other delays:

Ao = uptime / (uptime + downtime)

The denominator must define the observation window clearly. Availability is not utilization. A machine may be available but not utilized because no work, operator, fuel, or access is available.

For example, if a dozer operates between failures for an average of 180 hours and requires 12 hours of repair, then:

Ai = 180 / (180 + 12) = 0.9375, or 93.75%.

If parts delays add 8 hours, operational availability over the same failure-repair cycle becomes 180 / (180 + 12 + 8) = 0.90, or 90%. The difference identifies logistics as a potential improvement target.

Mean time between failures is meaningful only when “failure” is defined consistently. A sensor fault, a production-limiting hydraulic leak, and a catastrophic engine failure should not be combined without classification. Failure data should record asset identity, operating hours, component, symptom, cause, corrective action, downtime categories, and parts used.

6. Spare-Parts and Support Management

Parts management balances readiness against inventory cost and obsolescence. Criticality analysis classifies parts by consequence of stockout, lead time, failure frequency, and availability of alternatives. A low-cost seal with a long import lead time may be more operationally critical than an expensive but locally available filter.

Common controls include approved part numbers, interchangeable-part records, minimum and maximum stock levels, reorder points, cycle counting, secure storage, shelf-life control, and warranty tracking. A reorder point can be represented as:

ROP = d × L + SS

where d is average demand per time unit, L is replenishment lead time in the same time unit, and SS is safety stock. This deterministic form assumes stable average demand. More advanced policies estimate demand and lead-time variability statistically.

Parts should be issued against a work order so that maintenance cost and failure history remain visible. Cannibalizing one machine to repair another may restore short-term production but creates hidden risk and must be authorized, documented, and followed by a recovery plan.

7. Telematics, Data, and Digital Dispatch

Telematics combines location, machine sensors, operating-hour data, fuel information, fault codes, and communication networks. It can support geofencing, utilization measurement, idle-time reduction, service reminders, route analysis, theft detection, and production verification.

A productive telematics programme requires more than installing devices. The organization must define data ownership, access rights, retention, cybersecurity, privacy, calibration, and response procedures. Poorly configured systems may record engine-on time as productive time, misclassify low-load operation, or generate alarms that staff ignore.

Useful data architecture links:

  1. Asset identification and sensor data;
  2. time-stamped work orders and maintenance records;
  3. schedule activities and quantities;
  4. operator and location information; and
  5. dashboards with exception-based alerts.

Artificial intelligence can assist with anomaly detection, remaining-useful-life estimates, route optimization, and image-based inspection. Its outputs should support—not replace—engineering judgment. Models require representative data, periodic validation, explainable thresholds where safety is involved, and human authorization for consequential decisions. A false negative may permit a dangerous failure, while a false positive may cause unnecessary downtime.

8. Performance Measurement and Continuous Improvement

A KPI is useful only when it has a defined numerator, denominator, data source, frequency, owner, target, and decision rule. Common equipment KPIs include:

KPIInterpretation
Physical availabilityFraction of scheduled time equipment is capable of working
UtilizationFraction of available or scheduled time actually assigned and working; definition must be stated
MTBFAverage operating time between defined failures
MTTRAverage active repair time, or broader restoration time if stated
Fuel per unit outputEnergy efficiency of production
Idle percentageEngine-on time without productive work
Cost per productive hourEconomic burden of ownership and operation
Schedule adherenceActual completion compared with planned work
First-time fix rateRepairs resolved without repeat intervention
Near misses and incidentsSafety performance and learning signals

Avoid optimizing one KPI in isolation. Reducing idle time by rushing operators may increase incidents or component wear. Maximizing utilization may eliminate necessary preventive maintenance. A balanced scorecard should include production, cost, reliability, safety, quality, environmental, and workforce measures.

The Plan–Do–Check–Act cycle provides a practical improvement framework. Plan a specific change and prediction; do it under controlled conditions; check results against a baseline; and act by standardizing, revising, or abandoning the change. Root-cause tools include the five whys, fault-tree analysis, Pareto analysis, process mapping, and failure mode and effects analysis (FMEA). Corrective actions should address causes rather than merely replace failed parts.

9. Illustrative Case: Earthworks Fleet on a Constrained Urban Site

Background

A contractor must excavate and remove 48,000 m³ of soil in 12 weeks. Work is limited to 10 hours per day, 6 days per week, giving 720 scheduled hours. An urban site has one narrow gate, strict truck appointment windows, and limited room for stockpiling.

Problem

The initial plan allocated one excavator and eight trucks. Field observation showed that trucks queued at the gate while the excavator occasionally waited for empty vehicles. Residents also reported excessive idling and noise. A major road closure was scheduled in week six, creating a risk of access disruption.

Analysis

The required average production is:

48,000 / 720 = 66.7 m³/h.

The team measured a truck cycle of 36 minutes, including loading, travel, unloading, and return. Each truck carried 12 m³. With an efficiency factor of 0.85, one truck’s effective rate was:

12 × 0.85 × 60 / 36 = 17.0 m³/h.

Four trucks would theoretically provide 68 m³/h, close to demand. Eight trucks therefore created excessive queue potential unless the haul route changed. Telematics confirmed that engine-on idle time averaged 24% of shift hours.

Approach and solution

The contractor adopted four primary trucks and retained two flexible backup trucks for peak windows or breakdowns. A fifth truck was scheduled during the morning access window, then reassigned to another nearby project. The dispatch plan used appointment slots, a one-way internal route, a gate marshal, and a no-idling rule except during safe loading or traffic control. Preventive inspections were moved to the end of the shift, while the excavator received a planned midweek condition check.

The road-closure risk was addressed by excavating an additional 4,000 m³ before week six, subject to approved traffic and environmental controls. A stockpile was placed only after confirming bearing capacity, drainage, and property boundaries.

Outcome

After two weeks, average production rose from 58 to 70 m³/h, idle time fell from 24% to 11%, and gate queues were reduced. The contractor did not simply add equipment; it improved matching, sequencing, dispatching, and information flow. The final result depended on measurement and safe logistics, not on the nominal capacity of any single machine.

Learning points

  1. Fleet size should be based on system capacity and variability, not on isolated machine ratings.
  2. Telematics is valuable when linked to a defined operational response.
  3. Access constraints can be more influential than equipment horsepower.
  4. Backup capacity should be targeted at critical risks rather than maintained indiscriminately.
  5. Schedule risk, community impact, and environmental controls belong in equipment planning.

10. Governance, Safety, and Professional Responsibility

Equipment decisions have legal and ethical consequences. Employers must provide competent operators, inspections, training, guarding, traffic controls, lifting procedures, and records required by applicable legislation and standards. Site managers must not disable alarms, extend service intervals, overload machines, or pressure operators to bypass controls in pursuit of production targets.

Data governance is also important. Worker location and performance data may be personal information. Collection should have a legitimate purpose, limited access, transparent policies, secure storage, and proportionate retention. Automated scoring must not unfairly penalize operators for conditions outside their control, such as dispatch delays or weather.

Environmental responsibilities include fuel spill prevention, emissions control, noise management, soil and water protection, waste handling, and energy-efficient operation. Life-cycle decisions should consider embodied carbon, remanufacturing, battery safety, charging infrastructure, and end-of-life recycling where relevant.

Challenges and Limitations

Productivity and reliability estimates are uncertain. Weather, material variability, traffic, operator learning, supply interruptions, and unforeseen ground conditions can invalidate assumptions. Historical data may contain inconsistent failure definitions or survivorship bias: failed machines may be removed from the fleet, making the remaining average look artificially reliable.

Digital systems can create false precision. A dashboard may display percentages to two decimal places even though the underlying production quantity, location, or downtime coding is unreliable. Managers should combine data with field observation and worker knowledge. Models should be recalibrated when methods, attachments, duty cycles, or site conditions change.

Finally, the cheapest hourly machine is not necessarily the lowest-cost solution. A decision that increases breakdown risk, noise, emissions, or unsafe interaction may transfer costs to workers, communities, the environment, or later project stages.

Best-Practice Checklist

Before mobilization, confirm that:

  • production assumptions and units are documented;
  • fleet capacity is matched to bottlenecks and variability;
  • equipment movements and setup are in the schedule;
  • routes, exclusion zones, gates, fuel, maintenance, and emergency access are designed;
  • inspection and maintenance responsibilities are assigned;
  • critical parts and suppliers are identified;
  • telematics definitions and data governance are approved;
  • KPIs have owners, targets, and action thresholds; and
  • the plan includes review points for learning and adjustment.

Chapter Summary

Operations planning converts productivity estimates into a coordinated production system. It links quantities, cycle times, efficiency, schedule logic, resource loading, equipment mobility, site logistics, and dispatching. Fleet management considers the whole life cycle, including acquisition strategy, compatibility, cost, utilization, maintenance, replacement, and disposal.

Reliability and availability must be defined carefully. Ai = MTBF/(MTBF + MTTR) is useful for a simplified inherent-availability analysis, while operational availability includes broader delays. Preventive, predictive, corrective, proactive, and reliability-centred maintenance are different strategies and should be selected according to failure consequences and evidence.

Spare-parts controls, telematics, AI-assisted analysis, and balanced KPIs can improve readiness, but only when data definitions, governance, human judgment, and safety controls are sound. Continuous improvement uses measurement, root-cause analysis, controlled changes, and standardization. The professional objective is not maximum equipment activity at any cost; it is safe, reliable, economical, and environmentally responsible delivery of the required work.

Key Terms

Availability: Proportion of a defined period during which equipment is capable of performing its required function.

Bottleneck: The process stage that limits the output of a linked production system.

Corrective maintenance: Maintenance performed after a failure or detected fault.

Dispatching: Assigning equipment and operators to tasks as conditions change.

Fleet management: Coordinated life-cycle management of construction equipment.

FMEA: Failure mode and effects analysis used to identify and prioritize potential failures.

Inherent availability: Availability based mainly on operating time and active repair time.

MTBF: Mean time between defined failures.

MTTR: Mean time to repair or restore equipment, according to the stated definition.

Operating efficiency: Fraction of scheduled time or nominal capacity converted into effective production.

Predictive maintenance: Maintenance triggered by evidence of developing condition or degradation.

Preventive maintenance: Planned maintenance performed at specified time, usage, or cycle intervals.

Resource loading: Assigning labour, equipment, and other resources to scheduled activities.

Reliability: Probability of performing a required function for a specified time under stated conditions.

Resource leveling: Adjusting activity timing to resolve resource limits, potentially changing project duration.

Spare-parts criticality: Importance of a part based on failure consequence, lead time, alternatives, and operational impact.

Telematics: Integrated collection and communication of equipment location, sensor, operating, and fault data.

Utilization: Degree to which available or scheduled equipment time is actively assigned and productive, as specifically defined.

Review Questions

Short Answer Questions

  1. Why can a machine with high rated capacity still have low project productivity?
  2. Distinguish availability from utilization.
  3. What information should be recorded in a reliable equipment failure report?
  4. State two advantages and one limitation of telematics.
  5. Why should mobilization and attachment changes be included in the schedule?

Long Answer Questions

  1. Explain how a resource-loaded schedule is developed from quantities and productivity estimates.
  2. Compare corrective, preventive, predictive, proactive, and reliability-centred maintenance.
  3. Discuss the factors that should be considered in a buy–rent–lease equipment decision.
  4. Explain how site logistics and dispatching influence productivity, safety, and community impacts.
  5. Describe a balanced KPI system for a construction equipment fleet and explain why single-KPI optimization is dangerous.

Analytical / Application Questions

  1. A loader fills 8 m³ trucks in 3 minutes. Each truck has a total cycle of 15 minutes, including loading. If operating efficiency is 0.80, calculate the effective production of one truck and estimate the number of trucks required to support continuous loading. State practical factors that might change your answer.
  2. A crane has an MTBF of 240 operating hours and an MTTR of 16 hours. Calculate its inherent availability. If waiting for parts adds 8 hours per failure cycle, calculate the corresponding broader availability and interpret the difference.
  3. A project shows high equipment utilization but repeated safety incidents, excessive fuel consumption, and missed preventive-maintenance tasks. Propose a continuous-improvement investigation, including data to collect, root-cause methods, corrective actions, and KPIs.

Multiple Choice Questions with Answers

Question 1

Which factor most directly identifies the limiting output of a serial equipment operation?

A. The newest machine in the fleet

B. The stage with the lowest effective production capacity

C. The machine with the highest purchase price

D. The number of operators on the project

Correct Answer: B. The stage with the lowest effective production capacity

Question 2

A truck carries 12 m³, has a 36-minute cycle, and operates at an efficiency of 0.85. What is its effective production rate?

A. 12.0 m³/h

B. 17.0 m³/h

C. 20.4 m³/h

D. 24.0 m³/h

Correct Answer: B. 17.0 m³/h

Question 3

Which activity should be explicitly represented in a realistic equipment schedule?

A. Only productive machine movement

B. Only the equipment purchase date

C. Mobilization, setup, and attachment changes

D. Operator preferences without time allowances

Correct Answer: C. Mobilization, setup, and attachment changes

Question 4

Which maintenance strategy uses oil analysis or vibration trends to determine intervention timing?

A. Corrective maintenance

B. Predictive maintenance

C. Run-to-failure disposal

D. Unplanned replacement

Correct Answer: B. Predictive maintenance

Question 5

A machine has an MTBF of 180 hours and an MTTR of 12 hours. What is its inherent availability?

A. 90.0%

B. 93.75%

C. 96.0%

D. 98.5%

Correct Answer: B. 93.75%

Question 6

Which statement correctly distinguishes availability from utilization?

A. They are always identical measures

B. Availability concerns capability; utilization concerns actual assignment or use

C. Utilization measures only repair duration

D. Availability measures only fuel consumption

Correct Answer: B. Availability concerns capability; utilization concerns actual assignment or use

Question 7

In the simplified reorder-point equation ROP = d × L + SS, what does SS represent?

A. Scheduled shift

B. Service speed

C. Safety stock

D. Standard size

Correct Answer: C. Safety stock

Question 8

Which practice best supports reliable spare-parts cost and failure analysis?

A. Issuing all parts without work orders

B. Recording parts against the relevant maintenance work order

C. Removing part numbers after installation

D. Keeping parts records only in operator memory

Correct Answer: B. Recording parts against the relevant maintenance work order

Question 9

What is a principal risk of optimizing equipment utilization alone?

A. It always reduces production

B. It may encourage deferred maintenance or unsafe operation

C. It eliminates the need for scheduling

D. It guarantees lower fuel consumption

Correct Answer: B. It may encourage deferred maintenance or unsafe operation

Question 10

Which characteristic is essential for a useful equipment KPI?

A. A complex name with no defined data source

B. A defined numerator, denominator, owner, and decision rule

C. A target that changes after every result

D. Measurement of only purchase cost

Correct Answer: B. A defined numerator, denominator, owner, and decision rule