Demand Forecasting and Capacity RequirementsIntroductionCapacity planning begins with a deceptively difficult question: how much productive capability will an operation require, when will it be required, and with what degree of certainty? The answer cannot be obtained from a forecast alone. Managers must translate expected demand into workloads, workloads into resource requirements, and resource requirements into decisions about people, equipment, space, technology, suppliers, and time. This translation is complicated by product variety, different processing routes, setup times, yield losses, absenteeism, maintenance, seasonality, demand uncertainty, and service-level commitments. A firm may have sufficient average capacity but still fail during peaks. Conversely, excessive capacity may create high fixed costs and low utilization. Capacity planning therefore connects demand management, operations strategy, workforce planning, scheduling, inventory, and financial decision-making. The central logic is: Demand forecast or orders → product mix → resource workload → effective capacity → capacity gap → managerial action. Forecasts are not promises; they are structured estimates subject to error. Capacity decisions should consequently be based not only on a most-likely forecast but also on uncertainty, response time, flexibility, and the cost of being short or long. Learning ObjectivesBy the end of this chapter, the reader should be able to: - Distinguish forecasts, orders, demand, and capacity requirements.
- Select forecasting approaches appropriate to the time horizon and information available.
- Convert product demand and bills of resources into labor, machine, and space requirements.
- Calculate available, effective, required, and protective capacity.
- Analyze capacity gaps under variability and service-level requirements.
- Link short-, medium-, and long-term capacity decisions.
- Critically evaluate forecast error, bottlenecks, assumptions, and ethical risks in capacity planning.
1. Demand, Forecasts, and Planning Horizons1.1 Demand is not always the same as salesObserved sales may understate true demand when products are out of stock, orders are rejected, lead times are excessive, or customers substitute another product. Conversely, orders may overstate sustainable demand when customers place speculative orders, cancel them, or buy in anticipation of shortages. A useful planning process separates: - Market demand: what customers would purchase under stated conditions.
- Orders: transactions or commitments received by the operation.
- Shipments: quantities actually delivered.
- Forecast demand: an estimate of future demand.
- Dependent demand: demand calculated from another item’s planned production, such as components in a bill of materials.
- Independent demand: demand determined primarily by external customers or markets.
The appropriate input depends on the decision. A make-to-order operation may use a firm order backlog for near-term scheduling, while a capital-investment decision may require a market forecast and alternative scenarios. 1.2 Planning horizonsCapacity decisions are often classified by response time: | Horizon | Typical decisions | Main information |
|---|
| Short term: days to weeks | Overtime, sequencing, temporary labor, subcontracting, preventive-maintenance timing | Orders, backlog, near-term forecast, current availability | | Medium term: months to roughly two years | Workforce size, shifts, inventory, aggregate production, contracts, cross-training | Aggregate forecast, seasonality, labor and supplier constraints | | Long term: multiple years | Facilities, major equipment, technology, network design, automation | Strategic scenarios, market growth, technology, capital economics |
The boundaries are not universal. They depend on the lead time for acquiring capacity. A temporary worker may be available within days, whereas a new facility may require years. Thus, the planning horizon should be defined by the organization’s capacity-adjustment lead times rather than by arbitrary calendar labels. 2. Forecasting for Capacity Decisions2.1 Qualitative and quantitative approachesQualitative methods include executive judgment, sales-force estimates, customer surveys, market research, and the Delphi method. They are useful when historical data are limited, products are new, or structural change makes the past unreliable. Quantitative methods include time-series models and causal models. Time-series methods infer future values from historical patterns such as level, trend, seasonality, and cycles. Causal models relate demand to explanatory variables such as price, income, advertising, weather, or economic indicators. No method is universally best. Forecast selection should consider data quality, forecast horizon, aggregation level, stability of relationships, cost of error, and the decision’s reversibility. 2.2 Basic time-series modelsFor a simple moving average over the previous k periods: Ft+1 = (Dt + Dt-1 + ⋯ + Dt-k+1)/k where Fₜ₊₁ is the forecast for period t + 1, Dₜ is actual demand in period t, and k is the number of periods. This method assumes that recent observations are representative and gives equal weight to them. It is less responsive when k is large. A weighted moving average is: Ft+1 = ∑i=0k-1 wi Dt-i, with ∑wi = 1 where wᵢ are nonnegative weights. The weights must sum to one, preserving the unit of demand. Exponential smoothing is commonly expressed as: Ft+1 = αDt + (1 − α)Ft where 0 < α ≤ 1 is the smoothing constant. A high α responds rapidly to recent changes; a low α produces a smoother forecast. This basic form assumes no explicit trend or seasonal component. For a forecast with trend, one may use a trend-adjusted method such as Holt’s method. Seasonal demand requires a seasonal model or seasonal indices. Applying an unadjusted average to strongly seasonal demand can systematically understate peaks and overstate troughs. 2.3 Forecast accuracyForecast error for period t is commonly defined as: et = Dt − Ft A positive error means actual demand exceeded the forecast. Mean absolute deviation is: MAD = (1/n)∑|et| Root mean squared error is: RMSE = √[(1/n)∑et²] Mean absolute percentage error is: MAPE = (100/n)∑|et/Dt| where n is the number of evaluated periods. MAPE is undefined when actual demand is zero and can be distorted by very small denominators. Forecast metrics should be calculated using a holdout period or rolling-origin evaluation rather than evaluating a model only on the data used to fit it. For capacity planning, the distribution of error matters. Two forecasts may have the same MAD but different bias or different extreme errors. A capacity manager should examine bias, variability, peak errors, and errors at the level at which capacity is constrained. 3. Translating Demand into Resource Requirements3.1 Product mix and bills of resourcesAggregate units conceal important differences. Ten thousand units of a simple product may require less capacity than two thousand units of a complex product. Product mix must therefore be represented explicitly. A bill of resources (BOR) states the resources and standard quantities required per unit of product. It may include labor hours, machine minutes, inspection time, material-handling time, tooling, energy, or specialized skills. A bill of materials identifies components; a bill of resources identifies capacity-consuming activities and resources. For resource r, required workload is: Wr = ∑p=1P Qp apr + Sr where Qₚ is the planned quantity of product p, aₚᵣ is the standard amount of resource r per unit of product p, and Sᵣ is setup, changeover, or other batch-related workload. Workload and resource standards must use consistent units, such as machine-hours or labor-hours. If yield is less than 100 percent, planned starts must be increased. If q good units are required and yield is y, where 0 < y ≤ 1, the required starts are: Qstart = q/y This relationship assumes that yield is adequately represented by a stable average and that rework is either included in the standard or separately modeled. 3.2 Worked example: product mix and machine requirementsA plant plans to produce 1,200 units of Product A and 800 units of Product B in one month. Each A requires 0.40 machine-hours on Resource M and each B requires 0.75 machine-hours. There are 60 batches of A and 40 batches of B; each changeover takes 0.50 hours. Run time is: - A: 1,200 × 0.40 = 480 machine-hours.
- B: 800 × 0.75 = 600 machine-hours.
- Run-time total = 1,080 machine-hours.
Setup time is: - (60 + 40) × 0.50 = 50 machine-hours.
Therefore: - Required workload = 1,080 + 50 = 1,130 machine-hours.
Ignoring setups would understate the requirement by 50 hours, or approximately 4.4 percent of total workload. This illustrates why capacity analysis based solely on unit counts can be misleading. 4. Available, Effective, and Required Capacity4.1 Capacity terminology- Design capacity: theoretical maximum output under ideal conditions.
- Demonstrated capacity: output historically achieved under specified conditions.
- Available capacity: scheduled time potentially available for production.
- Effective capacity: realistic capacity after planned losses such as breaks, maintenance, changeovers, meetings, and expected quality losses.
- Required capacity: workload needed to satisfy the plan.
- Protective or reserve capacity: intentionally uncommitted capacity retained for variability, emergencies, growth, or service protection.
A common measure is utilization: Utilization = Actual ext{ output or load} / Design ext{ capacity} Efficiency is often expressed as: Efficiency = Actual ext{ output} / Effective ext{ capacity} The numerator and denominator must refer to comparable units and time periods. Utilization near 100 percent may be undesirable in a variable system because queues, delays, and recovery time can increase sharply as capacity approaches its limit. For a resource with N identical units, H scheduled hours per unit, and an effective-capacity factor e, effective capacity is: Ceff = NHe where 0 < e ≤ 1. If the factor already includes planned downtime and expected losses, those losses must not be subtracted again. 4.2 Worked example: capacity gapA department has four identical machines. Each is scheduled for 160 hours per month. Planned maintenance, breaks, and normal losses imply an effective-capacity factor of 0.85. The required workload from the production plan is 590 machine-hours. Effective capacity is: - Cₑff = 4 × 160 × 0.85 = 544 machine-hours.
The capacity gap is: - Required − effective = 590 − 544 = 46 machine-hours short.
The department can respond through overtime, improved yield, reduced setup time, subcontracting, rescheduling, an additional machine, or a change in product mix. The correct response depends on cost, lead time, quality, and customer commitments. 5. Variability, Service Levels, and Protective Capacity5.1 Why averages are insufficientIf demand and processing times were certain, capacity could be matched directly to average workload. Real systems experience random arrivals, variable task times, absenteeism, failures, rework, urgent orders, and forecast error. The result is that average capacity may be adequate while service performance is unacceptable. In a queueing system, high utilization generally causes waiting time and congestion to rise nonlinearly. The exact relationship depends on the arrival process, service-time distribution, number of servers, scheduling discipline, and buffer policy. Consequently, a single utilization threshold should not be treated as a universal law. 5.2 Service-level capacityA service level may be defined as the probability of meeting demand within a promised time, the percentage of orders shipped on time, or the probability of avoiding a stockout. The definition must be explicit. If forecast error over a planning period has mean μₑ and standard deviation σₑ, a simple protection quantity for a one-sided service target is: P = μe + zσe where z is the standard-normal quantile corresponding to the desired probability, assuming errors are approximately normal, independent as modeled, and measured in the same units as capacity. If the forecast is unbiased, μₑ is approximately zero. This formula is a planning approximation, not a universal safety-capacity rule. For multiple independent periods, the standard deviation of the sum is: σsum = √(σ1² + σ2² + ⋯ + σn²) If errors are correlated, covariance terms are required; simply adding standard deviations is generally incorrect. Correlation is especially important when demand shocks affect several products or resources simultaneously. Protection may be held as spare labor, cross-trained employees, flexible equipment, inventory, supplier options, or time buffers. The choice should reflect the location of uncertainty and the cost of each response. 5.3 Capacity cushionA capacity cushion is capacity deliberately maintained above expected demand. A basic definition is: Capacity ext{ cushion} = (Available ext{ capacity} − Expected ext{ load}) / Available ext{ capacity} The measure is meaningful only when “available capacity” and “expected load” are defined consistently. A larger cushion may be justified by volatile demand, severe penalties for lateness, long expansion lead times, or safety-critical consequences. A smaller cushion may be acceptable where demand is stable and capacity is easily added. 6. Capacity Planning Across Horizons6.1 Short-term capacity planningShort-term actions include overtime, temporary labor, cross-training, dispatching rules, maintenance timing, order prioritization, subcontracting, and controlled use of inventory. These actions are fast but may be expensive or disruptive. Overtime can protect service but may increase fatigue, defects, and safety risk. Short-term planning should use a finite-capacity view where possible. A plan that assumes unlimited capacity merely postpones the problem to the schedule. Managers should identify bottleneck resources, verify labor and skill availability, and protect critical operations from excessive variability. 6.2 Medium-term planningAggregate planning balances demand, workforce, production rate, inventory, backlog, and outsourcing over several months. A level strategy maintains a relatively stable production rate and uses inventory or backlog to absorb variation. A chase strategy changes production or workforce to follow demand. Hybrid strategies combine stable core capacity with flexible labor, overtime, inventory, or external supply. A useful aggregate-planning formulation minimizes total relevant cost: Minimize ∑t=1T(ctp Pt + cth It + ctb Bt + cto Ot + cts St) subject to the flow balance: It-1 + Pt + Ot − Dt = It − Bt Here Pₜ is regular production, Oₜ overtime or external production, Dₜ demand, Iₜ ending inventory, Bₜ backlog, and Sₜ a workforce or capacity-adjustment variable. The c terms are unit costs. Constraints may limit production, workforce changes, inventory, backlog, overtime, and supplier capacity. This is a simplified linear-planning representation; real models may require integer variables, nonlinear costs, or multiple resources. 6.3 Long-term capacity planningLong-term decisions include facility location, process technology, automation, equipment scale, network structure, and make-or-buy arrangements. They must consider demand scenarios rather than a single forecast. Relevant criteria include total cost, flexibility, resilience, carbon impact, labor availability, regulatory requirements, and strategic control. A capacity investment is often partly irreversible. Therefore, managerial flexibility has economic value. Staged expansion, modular equipment, leasing, option contracts, and partnerships can reduce exposure to forecast error. A technically efficient facility may be strategically poor if it cannot accommodate product variety or future process changes. 7. From Capacity Requirements to Line BalancingCapacity requirements describe how much resource time is needed; line balancing allocates tasks across workstations. For a paced line, cycle time is the available production time divided by required output: C = Available ext{ production time}/Required ext{ units} If total task time is ∑tᵢ and there are m workstations, line efficiency is: E = (∑ti)/(mC) The balance delay is 1 − E. These formulas assume a defined cycle time, compatible task precedence, and comparable task-time units. A high theoretical efficiency does not guarantee good performance if tasks are variable, material supply is unreliable, or the line is starved and blocked. The link to forecasting is essential: forecast volume determines required output, required output determines cycle time, and the product mix determines task content. When demand mix changes, a previously balanced line may become constrained at a different workstation. 8. Illustrative Case: Northstar Medical DevicesBackgroundNorthstar Medical Devices assembles two disposable diagnostic kits. Kit A has stable demand, while Kit B has seasonal demand and a higher inspection requirement. The plant operates one eight-hour shift for 20 working days per month. Management promises 95 percent on-time shipment and is considering a new contract. ProblemThe sales forecast for next month is 6,000 A kits and 3,000 B kits. Resource standards are: | Resource | Kit A | Kit B |
|---|
| Assembly labor | 0.10 h | 0.16 h | | Inspection labor | 0.03 h | 0.08 h | | Sealing machine | 0.04 h | 0.06 h |
Each product requires 100 batches per month, and each batch causes 0.15 machine-hours of sealing setup. Effective availability is 90 percent for labor and 85 percent for the sealing machine. Four assembly employees and two inspection employees are scheduled; one sealing machine is available. AnalysisAssembly workload is: - 6,000(0.10) + 3,000(0.16) = 1,080 labor-hours.
Inspection workload is: - 6,000(0.03) + 3,000(0.08) = 420 labor-hours.
Sealing run time is: - 6,000(0.04) + 3,000(0.06) = 420 machine-hours.
Sealing setup time is: - (100 + 100)(0.15) = 30 machine-hours.
Total sealing requirement is therefore 450 machine-hours. Scheduled labor hours per employee are 160 per month. Effective assembly capacity is: - 4 × 160 × 0.90 = 576 hours.
Effective inspection capacity is: - 2 × 160 × 0.90 = 288 hours.
Sealing capacity is: - 1 × (20 × 8) × 0.85 = 136 hours.
The calculated requirements exceed capacity in all three resources, especially sealing. However, the data reveal a likely modeling issue: the sealing standard may be expressed in minutes rather than hours, or the forecast may refer to multiple shifts. Before authorizing overtime or capital expenditure, the team must validate units and standards. This is a critical professional discipline: a mathematically correct calculation based on incorrect units produces an operationally wrong decision. Suppose validation confirms that sealing times are 0.004 and 0.006 hours per kit, not 0.04 and 0.06. Sealing run time becomes 42 hours, and total requirement is 72 hours, below the 136-hour effective capacity. Assembly and inspection remain constrained. Northstar could add temporary assembly labor, cross-train inspection staff, use approved overtime, or outsource a portion of Kit B. Because inspection has the smaller absolute capacity margin, it should be treated as a service-protection bottleneck. Approach and outcomeNorthstar adopts a hybrid plan: two cross-trained assembly employees are qualified for inspection, a modest overtime allowance is reserved for demand surges, and the contract is phased in over three months rather than accepted at full volume immediately. Forecasts are reviewed weekly, but capacity decisions use a rolling three-month scenario analysis. A quality gate prevents unqualified temporary labor from performing regulated inspection tasks. The outcome is not simply “more capacity.” It is a coordinated solution involving validated standards, flexible skills, phased demand, and governance of quality-critical work. Learning points- Product mix changes resource requirements even when total units are unchanged.
- Bills of resources must be validated with operations personnel.
- Service-level commitments require protection at the bottleneck, not merely average capacity.
- Flexibility can be more valuable than nominal capacity.
- In regulated operations, capacity expansion cannot compromise competence, traceability, or quality.
9. Technology, Data, and GovernanceEnterprise resource planning, advanced planning and scheduling systems, manufacturing execution systems, and workforce-management tools can connect forecasts, orders, routings, labor standards, and available capacity. Digital twins and simulation can test alternative product mixes, shift patterns, failures, and expansion options before implementation. Artificial intelligence can support demand sensing, anomaly detection, probabilistic forecasting, and scenario generation. It should not be treated as an automatic replacement for operational judgment. Managers must assess data drift, biased historical decisions, explainability, cybersecurity, privacy, and accountability. A model trained on periods of shortage may learn suppressed demand rather than true market demand. Human review is essential when forecasts affect employment, safety, medical supply, or customer access. Good governance includes version-controlled standards, documented assumptions, forecast overrides with reasons, separation of data and judgment, audit trails, and periodic back-testing. Forecast accuracy should not be the only performance measure: service, cost, resilience, quality, employee well-being, and environmental impact also matter. 10. Challenges and LimitationsCapacity calculations are often limited by: - Forecast uncertainty: future demand can change abruptly.
- Aggregation error: average demand hides peaks, mix, and geography.
- Standard-time error: engineered times may not reflect actual conditions.
- Resource substitution: nominally interchangeable workers may differ in skills.
- Correlated disruptions: one event may affect many resources simultaneously.
- Bottleneck migration: improving one resource can move the constraint elsewhere.
- Behavioral responses: customers may change orders when lead times change.
- Double counting: downtime, yield loss, and setup time may be included twice.
- False precision: detailed decimals can disguise weak assumptions.
Capacity planning is therefore a decision process under uncertainty, not a single calculation. Sensitivity analysis, scenario planning, rolling updates, and post-implementation learning are necessary complements to formal models. Best-Practice FrameworkA robust capacity study should: - Define the decision, horizon, service promise, and unit of analysis.
- Reconcile forecasts, orders, backlog, lost sales, and dependent demand.
- Segment products by process route, variability, margin, and strategic importance.
- Build and validate bills of resources, including setups, yield, and rework.
- Calculate effective capacity by resource and time period.
- Identify bottlenecks and test peak, base, and adverse scenarios.
- Compare flexible and irreversible responses using total relevant cost.
- Document assumptions, uncertainty, and governance controls.
- Implement a monitoring cycle with leading indicators and trigger points.
- Review forecast and capacity performance after the period ends.
Chapter SummaryDemand forecasting and capacity planning are connected but distinct activities. Forecasts estimate future requirements; capacity planning determines the resources and actions needed to meet those requirements at an acceptable cost and service level. Effective analysis distinguishes market demand, orders, shipments, and dependent demand; respects planning horizons; and accounts for product mix, bills of resources, setups, yield, downtime, and variability. Moving averages, exponential smoothing, and causal models can support forecasting, but model choice must reflect data and decision context. Forecast accuracy should be assessed using appropriate metrics and by examining bias and extreme errors. Resource workload is obtained by multiplying product quantities by resource standards and adding batch-related work. Available capacity must be converted into effective capacity after planned losses. Short-term capacity uses overtime, sequencing, cross-training, and subcontracting. Medium-term planning balances workforce, inventory, backlog, and production. Long-term planning addresses facilities, technology, network design, and strategic flexibility. Service-level requirements justify protective capacity, but protection must be calculated with explicit assumptions about forecast-error distributions and correlation. Finally, capacity analysis must be governed by validated data, clear units, ethical safeguards, and continuing review. Key TermsForecast: A structured estimate of future demand. Capacity: The maximum feasible output or workload a resource can provide under specified conditions. Effective capacity: Realistic capacity after normal planned losses. Design capacity: Theoretical maximum capacity under ideal conditions. Product mix: The proportions of different products or services in total demand. Bill of resources: A specification of resource quantities required by a product or service. Dependent demand: Demand calculated from the need for another item or output. Independent demand: Demand generated primarily by external customers or markets. Forecast error: The difference between actual demand and forecast demand. MAD: Mean absolute deviation, an average absolute forecast error measure. RMSE: Root mean squared error, which gives greater weight to large errors. Capacity cushion: Capacity intentionally held above expected workload. Protective capacity: Reserved capacity used to absorb uncertainty or protect service. Utilization: Actual load or output relative to a stated capacity base. Efficiency: Actual output relative to effective capacity. Bottleneck: A resource that limits system throughput or service performance. Aggregate planning: Medium-term coordination of demand, production, workforce, inventory, and backlog. Cycle time: Time available per unit required on a paced process or line. Line efficiency: Total task time divided by total available workstation time. Service level: A defined probability or percentage describing fulfillment performance. Review QuestionsShort Answer Questions- How do orders differ from market demand and forecast demand?
- What is the purpose of a bill of resources?
- Why must setup time be included in capacity calculations?
- Distinguish design capacity from effective capacity.
- Why can high utilization increase waiting and service problems?
Long Answer Questions- Compare qualitative, time-series, and causal forecasting methods for a new product and a mature seasonal product.
- Explain how product mix, yield, rework, and batch size affect resource requirements.
- Discuss the differences among short-, medium-, and long-term capacity decisions.
- Explain why forecast accuracy alone is insufficient for evaluating a capacity-planning process.
- Evaluate the advantages and risks of using AI-based demand forecasting in capacity planning.
Analytical / Application Questions- A department has three machines, each scheduled for 150 hours per month, with an effective-capacity factor of 0.80. Required workload is 390 machine-hours. Calculate effective capacity and the capacity gap, then recommend two possible responses.
- A firm forecasts 2,000 units of Product X and 1,000 units of Product Y. X requires 0.20 labor-hours and Y requires 0.50 labor-hours. There are 15 batches, each requiring 2 labor-hours of setup. Calculate total labor workload and explain how a 10 percent yield loss would alter the plan.
- Design a capacity-response plan for a seasonal operation whose forecast has high error, whose service penalty is severe, and whose permanent expansion requires two years. Justify the balance among inventory, flexible labor, subcontracting, and reserve capacity.
Multiple Choice Questions with AnswersQuestion 1Which input most directly represents the resource time required per unit of a product? A. Bill of resources B. Sales invoice C. Capacity cushion D. Forecast error Correct Answer: A. Bill of resources Question 2A four-machine department schedules 160 hours per machine and has an effective-capacity factor of 0.85. What is effective capacity? A. 544 machine-hours B. 640 machine-hours C. 188 machine-hours D. 756 machine-hours Correct Answer: A. 544 machine-hours Question 3In the expression Ft+1 = αDt + (1 − α)Ft, increasing α generally makes the forecast: A. More responsive to recent demand B. Independent of recent demand C. More affected by old observations D. Automatically seasonal Correct Answer: A. More responsive to recent demand Question 4Which item is normally added to unit processing workload when products are made in batches? A. Setup or changeover time B. Forecast percentage error only C. Design capacity D. Selling price Correct Answer: A. Setup or changeover time Question 5If required workload exceeds effective capacity, the operation has: A. A capacity shortfall B. A capacity cushion C. Zero utilization D. A demand surplus only Correct Answer: A. A capacity shortfall Question 6Which planning decision is most characteristically long term? A. Selecting a site for a new facility B. Changing tomorrow’s dispatch sequence C. Authorizing one hour of overtime D. Moving a maintenance task to next week Correct Answer: A. Selecting a site for a new facility Question 7Why can average demand be inadequate for service-level capacity planning? A. Variability can create peaks and waiting even when average capacity is sufficient B. Average demand always exceeds actual demand C. Service levels are unrelated to capacity D. Variability eliminates the need for forecasts Correct Answer: A. Variability can create peaks and waiting even when average capacity is sufficient Question 8A product requires 0.4 machine-hours per unit, and 1,200 units are planned. Ignoring setups, what is the workload? A. 480 machine-hours B. 300 machine-hours C. 1,600 machine-hours D. 4,800 machine-hours Correct Answer: A. 480 machine-hours Question 9Which statement about MAPE is correct? A. It can be undefined when actual demand is zero B. It always treats large errors more heavily than RMSE C. It has units of machine-hours D. It requires all forecast errors to be positive Correct Answer: A. It can be undefined when actual demand is zero Question 10In line balancing, cycle time is calculated as: A. Available production time divided by required units B. Required units divided by available production time C. Total task time multiplied by workstations D. Design capacity divided by forecast error Correct Answer: A. Available production time divided by required units
|