Capacity Planning & Line Balancing

Chapter 4
Capacity Planning Process and Strategic Alternatives

Graduate Program in Operation Management (GPOM)
Capacity Planning & Line Balancing   •   Graduate

Capacity Planning Process and Strategic Alternatives

Introduction

Capacity planning is the strategic process of determining the resources required to meet anticipated demand over a specified planning horizon. Capacity includes more than equipment or floor space. It encompasses labor, facilities, technology, suppliers, time, information-processing capability, logistics, and managerial attention. In operations management, the central question is not simply “How much can the operation produce?” but “How much capability should it possess, when should that capability be available, and how should it be configured to support competitive priorities?”

Capacity decisions are strategically important because they are expensive, difficult to reverse, and closely connected to customer service, cost, quality, delivery, flexibility, innovation, and risk. Excess capacity raises fixed costs and may create pressure to accept unprofitable work. Insufficient capacity produces queues, overtime, expediting, lost sales, employee fatigue, and deteriorating quality. Effective planning therefore aligns capacity with the organization’s market strategy and its uncertainty about future demand.

This chapter explains the capacity-planning process and examines lead, lag, match, expansion, contraction, outsourcing, subcontracting, flexible-resource, and capacity-sharing strategies. It also develops quantitative tools for evaluating capacity and applies them to a detailed illustrative case.

Learning Objectives

By the end of this chapter, students should be able to:

  1. Distinguish design, effective, and actual capacity.
  2. Calculate utilization, efficiency, capacity cushion, and break-even volume.
  3. Develop a capacity plan across short-, medium-, and long-term horizons.
  4. Compare lead, lag, and match strategies under uncertainty.
  5. Evaluate expansion, contraction, outsourcing, subcontracting, flexible-resource, and capacity-sharing alternatives.
  6. Align capacity decisions with competitive priorities and risk-management requirements.
  7. Critically assess technology, sustainability, governance, and implementation issues in capacity planning.

1. Capacity as a Strategic Resource

Design capacity is the theoretical maximum output of a system under ideal conditions. Effective capacity is the maximum output that can realistically be achieved after allowing for product mix, maintenance, setups, breaks, quality procedures, staffing constraints, and other operating conditions. Actual output is what the system produces in a given period.

Capacity must be expressed with a time basis and a unit of output. Examples include patients per day, tonnes per month, machine-hours per week, transactions per second, or available consulting hours per quarter. A capacity statement without a time period or output definition is incomplete.

Two measures are especially useful:

Utilization = Actual output ÷ Design capacity × 100%
Efficiency = Actual output ÷ Effective capacity × 100%

Utilization compares performance with the ideal technical limit, whereas efficiency compares performance with a realistic operating standard. The measures are percentages and should not be interpreted as interchangeable. For example, a system may have 80% utilization but 95% efficiency if effective capacity is substantially below design capacity.

A related concept is the capacity cushion. In a simple output-based form:

Capacity cushion = 1 − (Expected demand ÷ Rated capacity)

Here, expected demand and rated capacity must refer to the same period and units. A positive cushion indicates reserve capacity; a negative value indicates that expected demand exceeds rated capacity. The formula is most useful when “rated capacity” represents practical available capacity rather than a theoretical maximum.

Capacity cushions are valuable when demand is volatile, shortages are costly, service-level commitments are strict, or expansion lead times are long. They are less attractive when demand is stable, capital is expensive, and unused capacity can be redeployed easily. The appropriate cushion is therefore a strategic choice rather than a universal percentage.

Capacity and competitive priorities

Capacity decisions influence the following competitive priorities:

Competitive priorityCapacity implication
CostHigh utilization, standardization, scale economies, and limited idle resources
QualitySufficient time for prevention, inspection, maintenance, and employee learning
DeliveryReserve capacity, short queues, reliable suppliers, and rapid recovery
FlexibilityCross-trained labor, modular equipment, adaptable layouts, and multiple sourcing
InnovationExperimental capacity, skilled specialists, and protected development time
SustainabilityEnergy-efficient assets, resource efficiency, repairability, and avoidance of unnecessary expansion

A strategy that maximizes utilization may conflict with rapid delivery or flexibility. Strategic capacity planning is therefore a balancing exercise rather than a search for maximum output alone.

2. The Capacity Planning Process

Capacity planning is normally conducted through an iterative hierarchy.

Step 1: Clarify the strategic intent

Managers first identify the competitive priorities, target markets, service promises, regulatory requirements, and risk tolerance. A low-cost commodity producer may emphasize scale and stable utilization. A hospital, emergency service, or cloud platform may require substantial reserve capacity because demand surges and service failures are consequential.

Step 2: Define the planning horizon and unit of capacity

Strategic capacity decisions often cover several years and include facilities, major technologies, network design, and supplier architecture. Tactical decisions may cover months and address workforce levels, shifts, subcontracting, and inventory. Operational decisions may cover days or weeks and involve schedules, overtime, routing, and maintenance timing.

The planner should define the capacity unit carefully. For a product operation, a common unit may be finished units per month. For a product-mix environment, capacity may be measured in standard labor-hours or machine-hours, provided conversion factors are reliable.

Step 3: Forecast demand and characterize uncertainty

A forecast should include a central estimate, a range of plausible outcomes, seasonality, trend, demand variability, and the consequences of forecast error. Capacity decisions should not rely only on a single point forecast. Scenario analysis can represent low, expected, and high demand; more advanced approaches use probability distributions, simulation, or robust optimization.

Demand should be translated into resource requirements. If product i requires ai hours of a constrained resource and forecast volume is Di, required hours are:

Required resource hours = ∑(i=1 to n) Di ai

The summation applies when multiple products consume a common resource. The units are product units × hours per product unit, producing hours. The calculation assumes that processing times are sufficiently stable and that all relevant products are included.

Step 4: Audit current capacity

The audit identifies available assets, labor skills, operating hours, bottlenecks, maintenance requirements, yield losses, changeover time, absenteeism, supplier constraints, and quality-related downtime. Capacity should be measured at the bottleneck, because a non-bottleneck resource cannot compensate for a constrained operation without additional process changes.

For a resource available for h scheduled hours per period, with m parallel units, utilization of u and yield y, an approximate effective output-hour capacity is:

Effective hours = h × m × u × y

Here, u and y are expressed as decimals. This is a planning approximation; it assumes that losses can be represented multiplicatively and that the factors are sufficiently independent. If downtime, yield, and utilization interact materially, a detailed simulation or time-based loss model is preferable.

Step 5: Identify the gap

The capacity gap is the difference between required capacity and available effective capacity:

Capacity gap = Required capacity − Available effective capacity

A positive gap indicates a shortage; a negative gap indicates surplus. The gap should be calculated for each critical resource and period, not merely for total facility output.

Step 6: Generate alternatives

Alternatives may include additional shifts, overtime, cross-training, process improvement, new equipment, facility expansion, inventory, postponement, outsourcing, subcontracting, demand management, product redesign, or cooperation with other sites. Alternatives differ in cost, speed, reversibility, quality risk, dependence, and strategic value.

Step 7: Evaluate financially and strategically

Financial analysis should include fixed costs, variable costs, transition costs, transport, inventory, quality failure, service penalties, financing, taxes where relevant, and the residual value of assets. Strategic analysis should assess flexibility, resilience, learning, intellectual property, employment, sustainability, and supplier power.

For a single product with constant unit economics, the break-even volume is:

Break-even volume = Fixed cost ÷ (Selling price per unit − Variable cost per unit)

The denominator is contribution margin per unit. The formula assumes a constant selling price and variable cost, a single relevant product or a stable sales mix, linear cost behavior, and that fixed costs remain unchanged over the relevant range. It should not be applied uncritically where capacity additions create step-fixed costs.

Step 8: Select, implement, and review

A capacity plan should specify timing, responsibility, milestones, trigger conditions, and contingency actions. Managers should monitor leading indicators such as bookings, backlog, supplier lead time, absenteeism, order cancellation, and forecast bias. The plan must be revised as evidence changes; capacity planning is a control cycle, not a one-time decision.

3. Timing Strategies: Lead, Lag, and Match

Lead strategy

A lead strategy adds capacity before demand is fully realized. It protects delivery performance, supports market growth, reduces the risk of lost customers, and can deter competitors. Its disadvantages are idle capacity, premature capital commitment, depreciation, and the possibility that demand never materializes.

Lead strategies are suitable when expansion takes a long time, service failure is highly damaging, demand growth is credible, or the organization competes on speed and availability. They require disciplined investment gates so that optimism does not become overcapacity.

Lag strategy

A lag strategy adds capacity only after demand has increased sufficiently. It minimizes idle assets and is attractive when capital is scarce, demand is uncertain, or customers tolerate waiting. However, it can create queues, overtime, quality problems, lost market share, and dependence on emergency outsourcing.

Lag is more defensible when products are standardized, customers can wait, capacity can be added quickly, and temporary demand can be handled through inventory or external partners.

Match strategy

A match strategy adds capacity in smaller increments as demand develops. It seeks a balance between responsiveness and asset utilization. Its effectiveness depends on the availability of modular equipment, scalable facilities, flexible labor, and reliable demand signals. Match strategies can be administratively complex because they require frequent decisions and coordination.

No timing strategy is universally superior. The decision depends on demand uncertainty, expansion lead time, cost of idle capacity, cost of shortage, reversibility, and competitive positioning.

4. Expansion and Contraction Alternatives

Expansion alternatives

Expansion may involve adding shifts, extending operating hours, acquiring equipment, enlarging facilities, opening a new site, automating a process, or redesigning the product. Expansion can be internal or external. Internal expansion preserves control and learning but requires capital and management attention. External expansion through acquisition or partnership can be faster but introduces integration risk.

A sound expansion decision distinguishes capacity size from capacity timing. A large facility may offer economies of scale, but modular investment may reduce risk. Managers should examine the range over which unit cost declines, the point at which congestion increases, and the effect of product mix on bottleneck loading.

Contraction alternatives

Contraction becomes relevant when demand declines permanently, technology changes, or a network contains redundant resources. Options include reducing shifts, selling assets, closing a line or site, redeploying employees, consolidating facilities, discontinuing products, and transferring work to partners.

Contraction can improve cost and utilization but may destroy capabilities that are expensive to rebuild. It also has employment, community, supplier, and reputational effects. Ethical implementation requires transparent criteria, lawful consultation, fair treatment, and attention to affected stakeholders.

5. External Capacity: Outsourcing and Subcontracting

Outsourcing is the decision to obtain an activity or capability from an external provider rather than perform it internally. Subcontracting is a specific form of external production in which another organization performs all or part of the work under an agreed contract. The terms overlap in practice, but outsourcing often includes services such as information technology, logistics, maintenance, or customer support, while subcontracting commonly refers to production or project work.

External capacity can provide speed, specialist expertise, variable cost, geographic reach, and access to technology. Risks include quality variation, delivery dependence, data exposure, intellectual-property loss, hidden coordination costs, supplier opportunism, labor-rights concerns, and reduced internal learning.

A basic relevant-cost comparison is:

Net advantage of outsourcing = Avoidable internal cost − (Supplier price + External transaction costs)

The result is positive when outsourcing is financially favorable under the stated assumptions. Avoidable internal cost excludes fixed costs that will remain after outsourcing. External transaction costs include qualification, contracting, inspection, transport, coordination, switching, and expected disruption costs. Strategic capabilities and compliance obligations must be considered in addition to this arithmetic.

A make-or-buy decision should assess:

  • total landed cost rather than quoted price alone;
  • supplier capacity and financial stability;
  • quality systems and traceability;
  • lead time, flexibility, and recovery capability;
  • cybersecurity, confidentiality, and intellectual property;
  • labor, environmental, and human-rights standards;
  • contractual remedies and exit options; and
  • whether the activity is strategically distinctive or a source of organizational learning.

Dual sourcing or a qualified backup supplier can reduce dependence, although it may sacrifice some volume economies.

6. Flexible Resources and Capacity Sharing

Flexible resources

Flexible resources can serve multiple products, processes, locations, or demand classes. Examples include cross-trained employees, general-purpose equipment, mobile teams, modular automation, cloud computing, and multi-skilled maintenance personnel. Flexibility is valuable when demand is uncertain or correlated peaks are uncommon.

Flexibility has costs. Cross-training requires time and can reduce specialization; general-purpose equipment may be slower than dedicated equipment; frequent changeovers can reduce availability; and excessive task switching may harm quality. The economic value of flexibility depends on the probability and cost of different demand states.

A practical design is a flexible core with specialist support: maintain a stable base of efficient resources while retaining a smaller pool that can be redeployed during peaks or disruptions. Skill matrices, certification, standard work, and cross-training refreshers are necessary to make labor flexibility real rather than nominal.

Capacity sharing

Capacity sharing occurs when units, sites, firms, or supply-chain partners make capacity available to one another. Internal sharing may involve a common service center, pooled equipment, or a network of plants. External sharing may involve reciprocal agreements, contract manufacturing, industry consortia, or platform-based capacity markets.

Pooling can reduce the total reserve required when demand peaks are not perfectly synchronized. However, sharing creates governance questions: who receives priority during simultaneous shortages, how are costs allocated, how is quality controlled, and what information is disclosed? Service-level agreements should specify allocation rules, response times, quality standards, data rights, escalation procedures, and termination conditions.

7. A Quantitative Framework for Capacity Plans

Consider an operation with forecast demand Dt in period t, processing requirement a hours per unit, and available effective hours Ct. The load ratio is:

Load ratiot = (Dt × a) ÷ Ct

A load ratio above 1 indicates that demand exceeds available effective capacity, assuming no inventory, overtime, outsourcing, or backlog. A ratio below 1 indicates nominal spare capacity, although operational constraints may still exist.

Worked example

An assembly cell forecasts 2,400 units next month. Each unit requires 0.40 direct labor-hours. The cell has 8 employees, each scheduled for 160 hours. After breaks, meetings, training, and normal absence, only 85% of scheduled time is available for productive work. The required hours are:

2,400 × 0.40 = 960 labor-hours.

Available effective hours are:

8 × 160 × 0.85 = 1,088 labor-hours.

The load ratio is:

960 ÷ 1,088 ≈ 0.882, or 88.2%.

The cell therefore has approximately 128 effective labor-hours of nominal reserve. If demand rises to 2,900 units, required hours become 2,900 × 0.40 = 1,160, producing a shortage of 72 hours. Management could respond through overtime, temporary labor, cross-training, subcontracting, productivity improvement, or demand rescheduling. The appropriate choice depends on cost, urgency, quality risk, and whether the increase is temporary or structural.

The example also illustrates why design capacity is misleading. The nominal scheduled time is 8 × 160 = 1,280 hours, but effective capacity is only 1,088 hours after normal losses.

8. Integrated Illustrative Case: Northstar Medical Devices

This is a fictional illustrative case designed for educational use.

Background

Northstar Medical Devices produces a standardized diagnostic cartridge for hospitals. Demand has grown rapidly, but monthly orders fluctuate between 8,000 and 12,000 units. The plant currently has design capacity of 12,000 units per month, while effective capacity is approximately 9,600 units because of changeovers, preventive maintenance, training, and quality checks. The company competes primarily on regulatory quality and dependable delivery, not on the lowest price.

Problem

A new hospital contract may increase demand to 11,000 units per month within nine months. A new production line would require twelve months to qualify and validate. Management must choose among a lead expansion, a lag approach, subcontracting, and a flexible-resource plan. Regulatory rules require validated processes and documented supplier controls.

Analysis

The current effective capacity of 9,600 units creates a potential shortage of 1,400 units at expected demand. Because the new line cannot be qualified before the likely demand increase, a pure lag strategy would jeopardize delivery. The cost of a stockout is high because hospitals may switch suppliers and emergency substitution is difficult.

Northstar evaluates four alternatives:

AlternativeBenefitsPrincipal risks
Immediate full expansionProtects long-term availability; supports lead strategyCapital commitment if contract is lost
Wait for confirmed demandLimits idle capacityTwelve-month qualification delay and service failure
Qualified subcontractorRapid supplemental capacityQuality, confidentiality, and supplier-dependence risk
Flexible-resource combinationUses cross-training, changeover reduction, and limited external capacityRequires coordination and disciplined validation

Approach and solution

Northstar adopts a match-oriented plan with a temporary lead element. It first reduces changeover time through standardized setups and schedules similar products together. It cross-trains operators and creates a certified relief team. These actions raise effective internal capacity to an estimated 10,300 units per month without purchasing a new line.

The company then qualifies a subcontractor for up to 1,500 units per month, using the same validated materials, inspection procedures, traceability requirements, and audit schedule. The subcontractor is used only when the rolling eight-week forecast exceeds internal capacity. Northstar authorizes the new line after the hospital contract reaches a contractual commitment threshold and continues validation during the interim period.

This plan combines internal flexibility, capacity sharing with an external partner, and a staged expansion trigger. It does not assume that subcontractor capacity is automatically available; the contract reserves capacity and specifies response times.

Outcome

In the first six months, internal improvements provide sufficient capacity for normal demand. During two high-demand months, the qualified subcontractor supplies the overflow without missed deliveries. After demand remains above 10,500 units for three consecutive forecast cycles, Northstar proceeds with the validated line. The company avoids an immediate full-scale investment while protecting service and regulatory performance.

Learning points

  1. Effective capacity, not nameplate capacity, determines the practical gap.
  2. A mixed strategy can be superior to choosing a single pure strategy.
  3. In regulated industries, external capacity must be qualified before it is needed.
  4. Capacity triggers should be linked to evidence, not managerial optimism.
  5. Flexibility improvements can postpone capital expenditure but rarely eliminate the need for structural expansion when demand is sustained.

9. Technology, Analytics, and Contemporary Issues

Enterprise resource planning, manufacturing execution systems, digital twins, and advanced planning systems can connect demand, inventory, labor, maintenance, and capacity data. Predictive maintenance can reduce unplanned downtime, while simulation can test alternative shift patterns, layouts, and outsourcing policies before implementation.

Artificial intelligence can improve demand sensing, anomaly detection, workforce scheduling, and scenario generation. Its recommendations should not be treated as automatically objective. Managers must examine data quality, model drift, explainability, bias, cybersecurity, and accountability. A model trained on historical overtime may incorrectly conclude that chronic overloading is a normal capacity requirement. Human review and documented decision rights remain essential.

Contemporary capacity planning also includes resilience and sustainability. Resilience may favor geographically dispersed capacity, dual sourcing, strategic buffers, and modular expansion. Sustainability may favor energy-efficient equipment, remanufacturing, renewable power, reduced travel, and capacity decisions based on life-cycle cost rather than purchase price. These objectives can conflict with short-term utilization, so trade-offs should be made explicit.

10. Challenges and Limitations

Capacity models are simplified representations. Common limitations include:

  • forecast error and structural market change;
  • bottleneck migration after an improvement;
  • unstable processing times and product mix;
  • hidden downtime, rework, and learning effects;
  • labor shortages and skill certification limits;
  • non-linear congestion when utilization becomes high;
  • supplier disruption and correlated risks;
  • fixed-cost step changes after expansion; and
  • behavioral responses, such as employees accelerating work at the expense of quality.

High utilization is not always efficient. As a system approaches full loading, queues and recovery time may increase disproportionately. Managers should therefore evaluate flow time, quality, employee well-being, and service reliability alongside utilization.

11. Best-Practice Guidelines

  1. Define capacity in economically meaningful units and time periods.
  2. Measure effective capacity rather than relying on nameplate specifications.
  3. Locate and manage the true bottleneck.
  4. Use demand ranges and scenarios, not a single forecast.
  5. Match strategy choice to shortage cost, idle-capacity cost, and reversibility.
  6. Treat outsourcing as a total-cost and governance decision.
  7. Build flexibility through cross-training, modularity, and qualified partners.
  8. Use trigger-based investment gates for major expansions.
  9. Include quality, safety, labor, environmental, and data-governance criteria.
  10. Review capacity plans continuously using actual operating evidence.

Chapter Summary

Capacity planning determines the resources, timing, and configuration required to meet demand while supporting competitive priorities. Design capacity represents theoretical maximum output; effective capacity reflects realistic operating conditions; and actual output is observed performance. Utilization, efficiency, capacity cushion, load ratio, and break-even analysis provide useful quantitative foundations, but their assumptions must be understood.

The planning process begins with strategy and demand analysis, audits current resources, identifies capacity gaps, evaluates alternatives, and implements a monitored plan. Lead strategies protect future service but risk idle assets; lag strategies limit premature investment but risk shortages; and match strategies add capacity incrementally. Expansion and contraction should consider reversibility, learning, stakeholders, and long-term capability.

Outsourcing and subcontracting can provide speed and specialist capacity but create quality, dependence, governance, and intellectual-property risks. Flexible resources and capacity sharing improve responsiveness when supported by training, modularity, clear contracts, and allocation rules. Modern analytics and AI can strengthen planning, but data quality, explainability, cybersecurity, and human accountability remain necessary. The best capacity plan is not simply the largest or cheapest plan; it is the plan that balances cost, service, flexibility, resilience, sustainability, and strategic purpose.

Key Terms

Design capacity: Theoretical maximum output under ideal conditions.

Effective capacity: Realistic maximum output after normal operating losses.

Actual output: Quantity actually produced or served in a period.

Utilization: Actual output expressed as a percentage of design capacity.

Efficiency: Actual output expressed as a percentage of effective capacity.

Capacity cushion: Reserved capacity available above expected demand.

Capacity gap: Difference between required capacity and available capacity.

Bottleneck: Resource whose constraint limits total system throughput.

Lead strategy: Adding capacity before demand fully materializes.

Lag strategy: Adding capacity after demand has been demonstrated.

Match strategy: Adding capacity in increments aligned with demand growth.

Expansion: Increasing the amount or capability of capacity.

Contraction: Reducing, closing, selling, or redeploying capacity.

Outsourcing: Obtaining an activity or capability from an external provider.

Subcontracting: Contracting an external organization to perform specified work.

Flexible resource: Resource capable of serving multiple products, tasks, or locations.

Capacity sharing: Pooling or exchanging capacity among units or organizations.

Load ratio: Required resource load divided by available effective capacity.

Capacity trigger: Evidence-based condition that authorizes a capacity action.

Relevant cost: Cost that changes as a result of the decision being evaluated.

Review Questions

Short Answer Questions

  1. How do design capacity and effective capacity differ?
  2. What is the main strategic logic of a lead capacity strategy?
  3. Why can high utilization create operational problems?
  4. Identify two risks associated with outsourcing.
  5. What conditions make capacity sharing attractive?

Long Answer Questions

  1. Explain the capacity planning process from strategic intent through implementation and review.
  2. Compare lead, lag, and match strategies, including the conditions under which each is appropriate.
  3. Discuss how capacity decisions support or conflict with cost, quality, delivery, flexibility, and sustainability priorities.
  4. Explain why effective capacity is generally more useful than design capacity for operational planning.
  5. Evaluate the managerial and governance issues involved in subcontracting critical production.

Analytical / Application Questions

  1. An operation forecasts 3,600 units per month, requiring 0.5 labor-hours per unit. Ten employees are each scheduled for 150 hours, but only 80% is productive time. Calculate required hours, effective available hours, the load ratio, and the resulting capacity gap or surplus. Recommend one response.
  2. A firm can produce internally at an avoidable cost of $18 per unit. An external supplier charges $16 per unit, while transport, inspection, contract management, and expected disruption cost add $3 per unit. Should the firm outsource on relevant cost grounds? What strategic factors could change the decision?
  3. A hospital expects demand to increase, but the probability of the increase is uncertain and a new facility requires eighteen months to open. Develop a capacity strategy using at least three of the alternatives discussed in this chapter and justify the timing, risk controls, and trigger conditions.

Multiple Choice Questions with Answers

Question 1

Which measure compares actual output with effective capacity?

A. Utilization

B. Efficiency

C. Capacity cushion

D. Load ratio

Correct Answer: B. Efficiency

Question 2

A lead capacity strategy adds capacity:

A. Only after demand exceeds current capacity

B. Before demand is fully realized

C. Only through outsourcing

D. After a facility is closed

Correct Answer: B. Before demand is fully realized

Question 3

A key risk of a lag strategy is:

A. Excessive idle capacity before demand occurs

B. Premature depreciation

C. Lost sales and deteriorating delivery performance

D. Guaranteed supplier quality

Correct Answer: C. Lost sales and deteriorating delivery performance

Question 4

Forecast demand is 2,000 units, each requiring 0.25 hours. Available effective capacity is 450 hours. What is the load ratio?

A. 0.90

B. 1.11

C. 1.25

D. 1.80

Correct Answer: B. 1.11

Question 5

Which cost should generally be excluded from a make-or-buy comparison if it remains after outsourcing?

A. Avoidable direct labor cost

B. Supplier transport cost

C. Fixed cost that cannot be avoided

D. External inspection cost

Correct Answer: C. Fixed cost that cannot be avoided

Question 6

Which resource is most accurately described as flexible?

A. A dedicated machine producing one product only

B. A cross-trained team able to perform several certified tasks

C. A facility that cannot change its operating hours

D. A supplier with no backup capability

Correct Answer: B. A cross-trained team able to perform several certified tasks

Question 7

Capacity sharing requires particular attention to:

A. Eliminating all service agreements

B. Priority and allocation rules during simultaneous shortages

C. Maximizing product variety regardless of demand

D. Avoiding performance measures

Correct Answer: B. Priority and allocation rules during simultaneous shortages

Question 8

An operation has actual output of 800 units and design capacity of 1,000 units. Its utilization is:

A. 20%

B. P80%

C. 100%

D. 125%

Correct Answer: B. P80%

Question 9

Which statement about effective capacity is correct?

A. It always equals design capacity

B. It accounts for normal losses such as maintenance and setups

C. It excludes product mix

D. It is always lower than actual output

Correct Answer: B. It accounts for normal losses such as maintenance and setups

Question 10

A major reason to use scenario analysis in capacity planning is to:

A. Replace all managerial judgment

B. Assume demand is perfectly known

C. Evaluate plans under different plausible demand conditions

D. Guarantee that forecasts are accurate

Correct Answer: C. Evaluate plans under different plausible demand conditions

Capacity Planning & Line Balancing
Chapter 4 of 14