Capacity Planning & Line Balancing

Chapter 6
Capacity Economics and Decision-Making Under Uncertainty

Graduate Program in Operation Management (GPOM)
Capacity Planning & Line Balancing   •   Graduate

Capacity Economics and Decision-Making Under Uncertainty

Introduction

Capacity decisions determine the scale, flexibility, cost structure, and risk profile of an operating system. A manager deciding whether to add a production line, outsource demand, automate a process, open a facility, or delay investment is not merely choosing equipment. The manager is committing financial resources under uncertain conditions while attempting to match future capacity with demand.

Capacity economics links operations management with managerial accounting, finance, economics, and decision analysis. Its central question is: Which capacity alternative creates the greatest economic value, given expected demand, cost behavior, timing, flexibility, and uncertainty?

A sound analysis must distinguish accounting profit from cash flow, fixed costs from variable costs, relevant from irrelevant costs, and expected value from risk. It must also recognize that capacity has strategic value: an asset may provide flexibility, speed, quality, learning, or an option to expand later.

Learning Objectives

By the end of this chapter, the reader should be able to:

  1. Apply cost–volume–profit and break-even analysis to capacity alternatives.
  2. Identify relevant costs and avoid common sunk-cost and allocated-cost errors.
  3. Evaluate capacity investments using discounted cash flow and net present value.
  4. Model uncertainty with decision trees, scenarios, and sensitivity analysis.
  5. Explain real options and the value of flexibility in capacity decisions.
  6. Select risk-adjusted decision criteria appropriate to the decision context.
  7. Critically evaluate the limitations, ethical implications, and governance requirements of capacity economics.

1. The Economic Structure of Capacity Decisions

A capacity alternative usually involves four economic components:

  • Initial investment: equipment, construction, installation, training, information systems, and commissioning.
  • Operating costs: labor, materials, energy, maintenance, quality costs, logistics, and supervision.
  • Revenue or avoided cost: sales generated, internal production value, or external spending avoided.
  • Residual and strategic value: resale value, tax effects, flexibility, future expansion potential, reliability, and learning.

Capacity economics should be conducted over a defined planning horizon. The relevant horizon may be the physical life of an asset, its economic life, the planning period, or the time until a replacement decision becomes necessary. A short horizon can make a long-lived investment appear unattractive if terminal value is omitted; a long horizon can create false precision about uncertain forecasts.

Capacity is not identical to output. Design capacity is the theoretical maximum under specified conditions. Effective capacity is the maximum practical output after allowing for product mix, maintenance, breaks, quality procedures, and other constraints. Actual output is what the system produces. Two useful measures are:

Utilization = Actual output ÷ Design capacity
Efficiency = Actual output ÷ Effective capacity

These ratios are dimensionless when numerator and denominator use the same time and output units. High utilization is not automatically desirable: excessive utilization can increase congestion, overtime, breakdowns, and quality failures.

2. Cost–Volume–Profit and Break-Even Analysis

Cost–volume–profit (CVP) analysis examines how volume, price, variable cost, and fixed cost affect operating profit. For a single product, with constant unit economics, operating profit is:

Π = pQ − vQ − F = (p − v)Q − F

where Π is operating profit per period, p is selling price per unit, v is variable cost per unit, Q is volume, and F is total fixed operating cost. All monetary variables must be expressed in the same currency and period.

The term p − v is the unit contribution margin. It is the amount available first to cover fixed costs and then to generate profit. The contribution-margin ratio is:

CM ratio = (p − v) ÷ p

The break-even volume is the output at which operating profit equals zero:

QBE = F ÷ (p − v)

This formula assumes a constant selling price, constant unit variable cost, a single product or constant sales mix, linear cost behavior within the relevant range, and that output sold equals output produced. If there are multiple products, the contribution margin must be calculated using a stable sales mix or a weighted-average contribution margin.

Break-even sales revenue can be calculated as:

SBE = F ÷ CM ratio

The margin of safety measures how far expected sales exceed break-even sales:

Margin of safety = (Expected sales − Break-even sales) ÷ Expected sales

Worked Example 1: Comparing Two Capacity Technologies

A firm expects annual demand of 40,000 units. It is considering two alternatives:

AlternativeFixed cost per yearVariable cost per unitSelling price
Flexible line$240,000$18$30
Automated line$600,000$9$30

For the flexible line:

QBE = $240,000 ÷ ($30 − $18) = 20,000 units

For the automated line:

QBE = $600,000 ÷ ($30 − $9) ≈ 28,571 units

At 40,000 units, annual operating profit is:

ΠF = ($30 − $18)(40,000) − $240,000 = $240,000
ΠA = ($30 − $9)(40,000) − $600,000 = $240,000

The alternatives have equal profit at the volume where their total costs are equal:

$240,000 + $18Q = $600,000 + $9Q
Q = 40,000 units

Below 40,000 units, the flexible line is economically superior; above 40,000 units, the automated line is superior, subject to service, quality, reliability, and investment constraints. This crossover volume is not necessarily the final decision point because demand is uncertain and cash flows occur over time.

Limitations of CVP Analysis

CVP is useful as a screening tool but rests on restrictive assumptions. Fixed costs may step upward when capacity blocks are added. Variable costs may decline through learning or rise through congestion. Prices may change with volume, and demand may be affected by the capacity choice itself. Product mix, service levels, working capital, taxes, financing, and asset replacement are excluded from the basic model. Managers should therefore use CVP to identify economic relationships, not to claim an exact forecast.

3. Relevant Costing for Capacity Choices

A cost is relevant to a decision if it is future-oriented and differs between alternatives. Relevant costs include avoidable fixed costs, incremental variable costs, opportunity costs, additional working capital, and disposal or implementation costs. Irrelevant costs include sunk costs and costs that remain identical under every alternative.

An opportunity cost is the value of the best forgone alternative. If an existing facility could be rented for $100,000 per year, using it internally creates a $100,000 opportunity cost even if no cash payment is made. By contrast, the historical purchase price of the facility is sunk and should not affect a future choice.

Allocated corporate overhead requires careful treatment. An allocation is relevant only if the decision changes the underlying cash cost. A department may appear unprofitable because it receives an allocation of headquarters expense that will continue after closure. Closing the department would not eliminate that allocation and may therefore reduce, rather than increase, total profit.

Make-or-Buy and Outsourcing

The relevant comparison is not full internal cost versus supplier price. It is:

  • avoidable internal costs;
  • opportunity cost of capacity released;
  • supplier price and transaction costs;
  • quality, delivery, switching, and coordination risks;
  • strategic effects on knowledge, resilience, and dependence.

A supplier price below avoidable internal cost does not automatically justify outsourcing if outsourcing compromises continuity or uses scarce capacity that could produce a more valuable item.

4. Discounted Cash Flow and Net Present Value

A dollar received today is generally worth more than a dollar received later because it can be invested, uncertainty exists, and capital has alternative uses. Discounted cash flow (DCF) incorporates timing into investment evaluation.

The net present value (NPV) of an investment is:

NPV = −I₀ + ∑[t=1 to T] CFt ÷ (1 + r)t + TV ÷ (1 + r)T

Here, I₀ is the initial cash outflow at time zero, CF_t is net cash flow in period t, T is the number of periods, r is the discount rate per period, and TV is terminal cash flow, including after-tax disposal value and recovery of working capital where applicable. A project is financially attractive relative to the chosen benchmark when NPV is positive. Among mutually exclusive projects with comparable risk, the project with the highest NPV generally creates the greatest value.

If a constant annual cash flow A continues for T periods, its present value is:

PV of annuity = A × [1 − (1 + r)^−T] ÷ r

For an indefinitely recurring constant cash flow, the perpetuity formula is PV = A ÷ r, but this special case is rarely appropriate for physical capacity without considering maintenance, obsolescence, and changing conditions.

The discount rate must be consistent with the cash flows. Nominal cash flows, which include expected inflation, should be discounted at a nominal rate. Real cash flows should be discounted at a real rate. If tax effects are included, the analysis should use after-tax cash flows and a rate consistent with their risk.

Worked Example 2: Capacity Investment

A new line requires $1,000,000 immediately. It is expected to generate annual after-tax net cash inflow of $300,000 for four years. Its after-tax terminal value is $100,000 at the end of year four. Using an 8% discount rate:

The four-year annuity factor is approximately 3.3121. Therefore:

PV operating cash flows = $300,000 × 3.3121 = $993,630

The terminal value factor is approximately 0.7350:

PV terminal value = $100,000 × 0.7350 = $73,500

Thus:

NPV = −$1,000,000 + $993,630 + $73,500 = $67,130

The investment has a positive NPV under the stated assumptions. The conclusion remains conditional on the forecast, discount rate, tax treatment, maintenance requirements, and terminal value.

Economic Life and Equivalent Annual Cost

When alternatives have unequal lives, comparing raw NPVs may be misleading if each asset can be replaced indefinitely. The equivalent annual cost (EAC) converts a present value of cost into an equal annual amount:

EAC = PV of costs × r ÷ [1 − (1 + r)^−T]

EAC is appropriate when alternatives provide equivalent service and replacement assumptions are credible. It should not be used mechanically when technologies differ in output quality, flexibility, risk, or strategic capability.

5. Decision-Making Under Uncertainty

A forecast is not a fact. Capacity decisions are exposed to uncertainty in demand, price, labor availability, energy cost, technology performance, regulation, and supply continuity. Three complementary methods are especially useful: scenarios, sensitivity analysis, and decision trees.

Scenarios

A scenario is a coherent description of how several uncertain variables may develop together. For example, a high-demand scenario may also involve higher labor costs and more intense competition. Scenarios should not be confused with arbitrary changes to one variable. They are useful for testing strategy under internally consistent conditions.

A scenario table may include:

ScenarioProbabilityDemandPriceNPV
Low0.3025,000$28−$180,000
Base0.5040,000$30$67,000
High0.2055,000$31$310,000

The expected monetary value (EMV) is:

EMV = ∑[i=1 to n] pi Vi

where p_i is the probability of state i and V_i is the value under that state. For this illustration:

EMV = (0.30 × −$180,000) + (0.50 × $67,000) + (0.20 × $310,000) = $24,500

EMV is a probability-weighted average, not a guarantee and not a complete measure of desirability. It is most defensible when probabilities are credible and the decision maker is approximately risk neutral or can diversify the risk.

Sensitivity Analysis

Sensitivity analysis changes one assumption at a time, holding others constant, to identify variables that most influence the result. Typical variables include demand, price, variable cost, construction cost, discount rate, start-up delay, and terminal value.

For a simple project with annual volume Q and contribution margin m = p − v, the annual operating contribution is mQ. If fixed cash operating cost is F, the project is sensitive to the difference between contribution and fixed cost. The analysis can identify a critical demand level at which NPV equals zero, although that level may require numerical solving when cash flows vary by year.

One-at-a-time sensitivity analysis does not capture correlations. Monte Carlo simulation can vary several uncertain inputs simultaneously using specified probability distributions, producing a distribution of NPV rather than one estimate. Simulation quality depends on the validity of the distributions, correlations, and model structure; sophisticated computation cannot repair poor assumptions.

Decision Trees

A decision tree represents sequential decisions and uncertain events. Decision nodes are usually shown as squares, chance nodes as circles, and terminal outcomes as branches. The analysis proceeds from right to left: calculate the expected value at chance nodes and choose the best feasible alternative at decision nodes.

Suppose a firm may build a small line immediately for $400,000 or build a large line for $700,000. If it builds small, there is a 0.6 probability of high demand producing a payoff of $1,000,000 and a 0.4 probability of low demand producing $500,000. The net outcomes are $600,000 and $100,000, respectively. The EMV of the small line is:

EMVsmall = (0.6 × $600,000) + (0.4 × $100,000) = $400,000

If the large line produces net outcomes of $800,000 under high demand and $150,000 under low demand, then:

EMVlarge = (0.6 × $800,000) + (0.4 × $150,000) = $540,000

On EMV alone, the large line is preferred. However, a manager may prefer the small line if downside exposure, financial constraints, or reversibility is important. If the firm can observe demand before expanding, the value of that information and flexibility must be included.

6. Risk-Adjusted Decision Criteria

No single risk measure is universally correct. Appropriate criteria depend on the decision maker’s objectives, financial capacity, and ability to diversify.

  • Expected monetary value: maximizes probability-weighted value but may understate aversion to severe losses.
  • Risk-adjusted NPV: uses a discount rate reflecting systematic risk, or adjusts cash flows for risk. The two approaches should not be mixed inconsistently.
  • Certainty equivalent: converts a risky cash flow into the certain amount considered equally attractive by the decision maker.
  • Value at Risk (VaR): estimates a loss threshold not exceeded at a specified confidence level over a specified horizon. It does not describe losses beyond that threshold.
  • Conditional Value at Risk (CVaR): estimates the average loss in the tail beyond the VaR threshold and is often more informative for severe downside risk.
  • Maximum regret: evaluates the largest opportunity loss relative to the best action after the state is known.
  • Minimax: chooses the alternative with the best worst-case outcome; it is conservative and can ignore plausible upside.
  • Safety-first criteria: require a specified probability or confidence that performance will exceed a minimum target.

A major governance principle is to report both value and dispersion. An investment with slightly higher expected NPV but a substantial probability of financial distress may not dominate a more stable alternative.

7. Real Options and the Value of Flexibility

Traditional NPV often assumes a now-or-never decision and a fixed operating policy. In practice, capacity creates choices. These choices are real options, because they concern physical or organizational assets rather than traded financial securities.

Common capacity-related options include:

  • Option to defer: wait for better demand information before investing.
  • Option to expand: begin with a modest facility and add capacity if demand is strong.
  • Option to contract: sell assets, reduce shifts, or outsource if demand weakens.
  • Option to abandon: discontinue a project and recover residual value.
  • Switching option: shift between fuels, suppliers, products, or production technologies.
  • Staged investment option: invest sequentially, preserving the right but not the obligation to continue.

The value of flexibility is particularly high when uncertainty is large, decisions are partially reversible, investment is staged, and information arrives over time. A flexible machine may have a higher purchase price but lower expected downside and greater strategic value than a specialized machine.

Real-option reasoning should not be used as vague optimism. The option must be defined, the triggering information identified, the exercise cost estimated, and the alternative to exercising specified. A staged project may have a lower static NPV but a higher value after accounting for the ability to abandon unfavorable paths.

8. Integrated Case: Northstar Components

Background

Northstar Components produces precision housings for industrial pumps. Demand has grown, but forecasts range widely because a major customer is considering a new product platform. Northstar must add capacity within twelve months.

Management is considering three alternatives:

  1. Expand the existing plant: investment of $1.2 million, annual capacity of 50,000 units, unit variable cost of $22.
  2. Build a dedicated automated cell: investment of $2.0 million, annual capacity of 80,000 units, unit variable cost of $15.
  3. Use a contract manufacturer: no major investment, purchase cost of $27 per unit, with a two-year agreement and limited priority during industry shortages.

The expected selling price is $35 per unit. Annual fixed operating costs are $400,000 for the expansion and $800,000 for the automated cell. Demand may be low, base, or high: 30,000, 50,000, or 75,000 units, with probabilities 0.25, 0.50, and 0.25. The automated cell can be built in stages: an initial $1.4 million cell supports 50,000 units, with a $0.8 million expansion available after demand information arrives.

Problem

A single forecast would conceal the trade-off. The expansion has moderate fixed cost and moderate variable cost. Automation has greater scale economies but higher exposure if demand is weak. Contracting preserves capital but sacrifices margin and supply security.

Analysis

At 50,000 units, the annual operating profit before investment recovery is:

Πexpansion = ($35 − $22)(50,000) − $400,000 = $250,000
Πautomation = ($35 − $15)(50,000) − $800,000 = $200,000

The contract manufacturer produces:

Πcontract = ($35 − $27)(50,000) = $400,000

These figures alone favor contracting, but they omit the investment cost, capacity limits, long-run cash flows, quality costs, supplier risk, and the value of ownership. At 75,000 units, the expansion cannot meet all demand, whereas automation can. Lost contribution, subcontracting, or customer dissatisfaction must be modeled rather than ignored.

The crossover volume between expansion and automation is obtained from:

$400,000 + $22Q = $800,000 + $15Q
Q ≈ 57,143 units

Thus automation becomes cheaper above approximately 57,143 units, before considering capital recovery. The staged option is attractive because Northstar can preserve the right to expand after observing early demand. Its economic value comes from avoiding the full $2.0 million commitment when demand is weak while retaining access to high-volume economics when demand is strong.

A complete evaluation would discount the investment and operating cash flows, include taxes and working capital, estimate the probability of customer adoption, and assign values to quality and delivery reliability. It would also test whether the contract manufacturer can meet Northstar’s service-level requirements.

Approach and Recommendation

Northstar should not select an alternative solely from the base-case profit. A defensible process is:

  1. Establish a common planning horizon and after-tax cash-flow convention.
  2. Estimate demand scenarios and explicitly document probabilities.
  3. Calculate NPV for each alternative under each scenario.
  4. Test demand, price, labor cost, supplier cost, delay, and investment sensitivity.
  5. Evaluate the staged expansion as a real option.
  6. Assess strategic and operational risks, including supplier dependency and quality.
  7. Use a governance threshold requiring approval if downside NPV or cash exposure exceeds a defined limit.

Illustratively, the staged automated option may be preferred even if its static base-case NPV is not highest, because it limits initial exposure and preserves expansion capability. A dual-source contract arrangement could also be used temporarily while demand information improves.

Outcome and Learning Points

The case demonstrates that capacity economics is a portfolio of analyses, not a single formula. CVP identifies scale relationships; relevant costing prevents distorted comparisons; DCF incorporates timing; scenarios and sensitivity reveal fragility; and real options capture the value of waiting and staging. The final decision should integrate financial value with service, resilience, quality, workforce, and strategic considerations.

9. Implementation, Governance, and Ethical Issues

A capacity model should be auditable. Managers should document assumptions, data sources, forecast ownership, probability judgments, discount rates, tax treatment, capacity definitions, and terminal values. Independent review is especially important when a project sponsor benefits from approval.

Ethical issues arise when managers deliberately bias demand forecasts, hide downside scenarios, capitalize operating expenses improperly, or use unrealistic terminal values to obtain investment approval. Models should disclose uncertainty rather than create an illusion of precision. Sensitivity ranges should be communicated to boards and investment committees.

Capacity decisions also affect employees and communities. Automation may improve safety and consistency but displace roles or require retraining. Outsourcing may transfer environmental or labor risks to suppliers. Responsible governance therefore includes workforce transition plans, supplier due diligence, environmental assessment, and compliance with labor, safety, competition, and financial-reporting requirements.

10. Technology and Contemporary Developments

Digital twins, advanced planning systems, and machine-learning forecasts can improve capacity analysis by integrating demand, process, maintenance, and cost data. Predictive maintenance can alter expected availability and reduce downtime. Cloud manufacturing and flexible automation can reduce the irreversibility of capacity investment.

However, algorithmic forecasts inherit data bias and may fail under structural breaks, such as pandemics, geopolitical disruption, or new technology. Managers should monitor forecast error, use human review for regime changes, and maintain model version control. AI-generated scenarios are decision-support tools, not substitutes for accountability. A model should report confidence ranges, assumptions, and data provenance whenever possible.

Best Practices

  1. Define the decision, time horizon, capacity units, and objective before calculating.
  2. Separate sunk, fixed, variable, avoidable, and opportunity costs.
  3. Use contribution analysis for short-run decisions and DCF for investment decisions.
  4. Keep cash flows, discount rates, inflation, taxes, and timing internally consistent.
  5. Evaluate alternatives under multiple coherent scenarios.
  6. Report break-even volume, downside exposure, and key sensitivities.
  7. Account explicitly for capacity limits, step costs, bottlenecks, and service effects.
  8. Consider staged investment and reversibility as real economic value.
  9. Validate probabilities and assumptions with operational and commercial experts.
  10. Treat ethics, resilience, workforce effects, and regulatory compliance as decision criteria, not afterthoughts.

Chapter Summary

Capacity economics evaluates how scale, cost behavior, timing, uncertainty, and flexibility affect operating decisions. CVP analysis explains contribution, break-even volume, and crossover points, but its linear assumptions limit its use in complex systems. Relevant costing focuses attention on future costs that differ between alternatives and prevents sunk costs and arbitrary allocations from distorting decisions.

Discounted cash flow and NPV recognize the time value of money and are central to long-lived capacity investments. Scenarios, sensitivity analysis, and decision trees expose uncertainty and sequential choices. Expected monetary value is useful when probabilities are credible, but risk-adjusted criteria are needed when downside exposure matters. Real options extend NPV by valuing the ability to defer, expand, contract, abandon, or switch.

Professional capacity decisions combine quantitative analysis with operational judgment. They require transparent assumptions, auditable models, ethical governance, and attention to resilience, workforce consequences, technology limitations, and strategic capability.

Key Terms

Capacity: The maximum feasible output of a process under specified conditions.

Design capacity: The theoretical maximum output under ideal operating conditions.

Effective capacity: Practical maximum output after normal constraints are considered.

Utilization: Actual output divided by design capacity.

Efficiency: Actual output divided by effective capacity.

Fixed cost: Cost that remains constant within a relevant operating range.

Variable cost: Cost that changes with activity volume within a relevant range.

Contribution margin: Selling price minus variable cost per unit.

Break-even point: Volume or revenue at which profit equals zero.

Relevant cost: Future cost that differs among decision alternatives.

Sunk cost: Past cost that cannot be changed by a current decision.

Opportunity cost: Value of the best alternative forgone.

Net present value: Present value of future cash flows minus initial investment.

Discount rate: Rate used to convert future cash flows into present value.

Scenario analysis: Evaluation of alternatives under coherent combinations of assumptions.

Sensitivity analysis: Examination of how results change when an assumption changes.

Decision tree: A representation of sequential decisions and uncertain events.

Expected monetary value: Probability-weighted average of possible outcomes.

Real option: The value of managerial flexibility associated with a real asset or project.

Equivalent annual cost: Annualized present value of the cost of an alternative.

Review Questions

Short Answer Questions

  1. Distinguish design capacity, effective capacity, utilization, and efficiency.
  2. What conditions are required for the basic break-even formula to be valid?
  3. Why is a sunk cost irrelevant to a future capacity decision?
  4. What is the difference between NPV and expected monetary value?
  5. Give two examples of real options in capacity planning.

Long Answer Questions

  1. Explain how CVP analysis can support, but cannot replace, a capacity investment evaluation.
  2. Discuss the role of relevant costing in make-or-buy and outsourcing decisions.
  3. Explain how a decision tree represents sequential capacity decisions under uncertainty.
  4. Compare expected monetary value, minimax, maximum regret, and risk-adjusted NPV.
  5. Critically evaluate the advantages and limitations of real-options reasoning.

Analytical / Application Questions

  1. A product sells for $50, has a variable cost of $30, and annual fixed cost of $600,000. Calculate the break-even volume and the operating profit at 40,000 units. State the assumptions behind your calculation.
  2. A project requires $500,000 today and generates $180,000 at the end of each year for four years, with no terminal value. Calculate its NPV at 10% and interpret the result.
  3. Design a decision tree for a firm choosing between immediate expansion and a smaller investment followed by a possible expansion after demand information arrives. Identify the data required to compare the alternatives fairly.

Multiple Choice Questions with Answers

Question 1

Which expression represents operating profit for a single product under basic CVP assumptions?

A. Π = (p + v)Q + F

B. Π = (p − v)Q − F

C. Π = F ÷ (p − v)

D. Π = p ÷ v − FQ

Correct Answer: B. Π = (p − v)Q − F

Question 2

A product sells for $40, has a variable cost of $24, and fixed costs are $160,000. What is the break-even volume?

A. 4,000 units

B. 6,667 units

C. 10,000 units

D. 16,000 units

Correct Answer: C. 10,000 units

Question 3

Which cost is generally relevant when an existing facility could otherwise be rented to another firm?

A. The facility’s historical purchase price

B. A corporate overhead allocation that will continue

C. The forgone rental income

D. Depreciation recorded in prior years

Correct Answer: C. The forgone rental income

Question 4

A project requires $100,000 and produces $60,000 at the end of each of two years. At a 10% discount rate, its NPV is closest to:

A. −$4,132

B. $0

C. $4,132

D. $20,000

Correct Answer: C. $4,132

Question 5

What is the principal purpose of sensitivity analysis?

A. To guarantee the most likely forecast

B. To examine how results change when assumptions change

C. To eliminate all uncertainty from a model

D. To replace cash-flow analysis with accounting profit

Correct Answer: B. To examine how results change when assumptions change

Question 6

At a chance node in a decision tree, the usual calculation is:

A. The maximum possible outcome only

B. The probability-weighted value of branch outcomes

C. The historical average cost only

D. The minimum outcome regardless of probability

Correct Answer: B. The probability-weighted value of branch outcomes

Question 7

Which criterion is most explicitly concerned with losses in the extreme tail beyond a specified threshold?

A. Contribution margin

B. CVP analysis

C. Conditional Value at Risk

D. Break-even volume

Correct Answer: C. Conditional Value at Risk

Question 8

Which situation most strongly increases the value of a real option to defer investment?

A. The investment is fully reversible and uncertainty is negligible

B. Demand is uncertain and information is expected soon

C. All future cash flows are contractually fixed

D. The asset has no alternative use

Correct Answer: B. Demand is uncertain and information is expected soon

Question 9

If two alternatives have equal total cost at 40,000 units, which alternative is generally preferred below that volume when it has lower fixed cost but higher variable cost?

A. The lower-fixed-cost alternative

B. The higher-fixed-cost alternative

C. Both must have identical profit at every volume

D. Neither can be evaluated using cost information

Correct Answer: A. The lower-fixed-cost alternative

Question 10

Which statement about discounted cash flow is correct?

A. Nominal cash flows should normally be paired with a real discount rate

B. Timing of cash flows is ignored in NPV

C. The discount rate and cash-flow convention should be consistent

D. Terminal value is never relevant to capacity investments

Correct Answer: C. The discount rate and cash-flow convention should be consistent