Workforce and Capacity PlanningIntroductionAggregate production planning converts medium-term demand expectations into feasible policies for labor, equipment, time, and external supply. Workforce and capacity planning is the central feasibility problem: a plan is valuable only when the organization can produce the required volume, at the required quality, within acceptable cost and service limits. The planning horizon commonly ranges from three months to two years. Decisions at this level do not normally specify the exact sequence of every job. Instead, they determine workforce size, shift patterns, overtime, temporary labor, subcontracting, equipment utilization, maintenance availability, and the timing of capacity expansion or reduction. These decisions influence production cost, inventory, employee well-being, delivery reliability, flexibility, and long-term competitiveness. A sound policy balances four questions: - How much capacity is required over each planning period?
- How much regular capacity is available?
- Which mechanisms should close any capacity gap?
- What financial, operational, human, and strategic consequences follow?
Workforce and capacity planning therefore combines operations management, human-resource management, cost analysis, industrial engineering, and strategic decision-making. Learning ObjectivesAfter studying this chapter, the reader should be able to: - distinguish workforce capacity from equipment and effective capacity;
- calculate regular-time, overtime, and aggregate capacity;
- evaluate staffing, shift, flexible-labor, and subcontracting policies;
- incorporate learning effects into labor-hour estimates;
- analyze equipment availability, maintenance, and bottleneck constraints;
- compare capacity expansion and reduction alternatives;
- formulate and interpret a practical aggregate capacity plan;
- recognize ethical, technological, and governance issues in workforce decisions.
1. Capacity as a Planning Concept1.1 Design, demonstrated, and effective capacityDesign capacity is the theoretical maximum output under specified technical conditions. Demonstrated capacity is the output historically achieved. Effective capacity is the realistic output after allowing for product mix, setups, maintenance, quality losses, absenteeism, breaks, material shortages, and operating policies. Capacity must always be expressed in a common unit, such as units per month, standard labor-hours per month, machine-hours per week, tonnes per day, or service transactions per hour. The unit should reflect the resource that constrains output. A mixed-product factory may use standard hours rather than physical units because one product may require twice as much work as another. A useful distinction is: - Available capacity: resource time scheduled for production.
- Effective capacity: available capacity adjusted for expected losses.
- Required capacity: workload implied by the aggregate production plan.
- Unused or reserve capacity: effective capacity not assigned to planned work.
For a single resource, utilization and efficiency are often reported as: Utilization = Actual output ÷ Design capacity Efficiency = Actual output ÷ Effective capacity Both ratios are dimensionless. Utilization compares actual output with a theoretical maximum, whereas efficiency compares it with a realistic operating standard. A high utilization rate may be undesirable if it leaves no protection against demand variability or disruptions. 1.2 Labor-hour capacityIf each worker is scheduled for h productive hours per period, N workers are employed, and the expected productive fraction is α, regular labor capacity is: CR = N × h × α where CR is regular productive labor-hours per period. The factor α includes breaks, meetings, absenteeism, training, minor delays, and other planned losses. The formula assumes workers are sufficiently interchangeable and that labor-hours can be aggregated meaningfully. If product i requires ai standard labor-hours per unit and planned output is Qi, required labor-hours are: H = ∑(i=1 to k) ai × Qi where k is the number of products. The units are labor-hours. Feasibility requires required hours not to exceed available hours for the relevant skill category, period, and work center. 1.3 Bottlenecks and constrained capacityAggregate capacity is not simply the sum of all resources. A plant with ample assembly labor may still be constrained by a heat-treatment furnace, specialist certification, testing equipment, or supplier availability. The bottleneck is the resource whose capacity most restricts system throughput at a particular time. Capacity planning should therefore use a resource profile: demand is translated into requirements for labor categories, machines, tools, facilities, materials, and support services. A plan feasible in total hours may be infeasible at a bottleneck or at a required skill level. 2. Workforce Policies2.1 Staffing alternativesA workforce policy specifies how the organization responds to changing workload. The principal alternatives are shown below. | Policy | Main mechanism | Advantages | Risks or limitations |
|---|
| Level workforce | Keep core staffing stable; use inventory or backlog | Stability, retention, predictable employment | Inventory cost, obsolete stock, delayed service | | Chase demand | Hire or release to follow workload | Low inventory and backlog | Recruitment, severance, morale, and skill risks | | Hybrid | Maintain core workforce and adjust at the margin | Balance of stability and flexibility | More complex coordination | | Flexible labor | Use temporary, part-time, cross-trained, or agency workers | Rapid response to peaks | Training, quality, legal, and commitment issues | | External capacity | Subcontract selected work | Avoids permanent investment | Supplier dependence, intellectual-property and quality risks |
The level strategy is appropriate where skills are scarce, employment relationships are important, demand is relatively stable, or inventory is economical. A chase strategy may suit standardized work with readily available labor and highly seasonal demand. Most organizations use a hybrid strategy: a stable core workforce handles normal demand, while overtime, temporary labor, inventory, subcontracting, or schedule changes absorb variation. 2.2 Staffing and hiring decisionsHiring creates capacity but also creates fixed or semi-fixed obligations. Relevant costs include recruitment, selection, onboarding, training, wages, benefits, supervision, equipment, and the risk that demand will not materialize. Managers should distinguish immediate headcount from productive headcount: a newly hired employee may not yet deliver the output of an experienced worker. Release decisions should consider severance, redeployment, legal requirements, union agreements, loss of scarce skills, and the cost of rehiring later. A purely short-term cost comparison can produce a false economy if it destroys organizational capability. 2.3 Shifts and schedulingShift planning determines when capacity is available. A second shift can increase asset utilization without purchasing another facility, but it may require shift premiums, additional supervision, maintenance windows, security, transportation, and support services. Night work can create health and fatigue concerns and may affect quality and safety. Shift patterns should be assessed against: - demand timing and customer service windows;
- equipment warm-up, changeover, and cleaning requirements;
- labor-law limits on working time and rest;
- skill coverage on every shift;
- maintenance and emergency-response capability;
- transportation and employee accessibility;
- energy prices and environmental constraints.
A nominal two-shift schedule does not automatically provide twice the capacity of one shift. Support functions, changeovers, absenteeism, and maintenance may prevent proportional growth. 2.4 OvertimeOvertime is a short-term capacity lever. If N workers each perform o overtime hours and the productive fraction is β, overtime capacity is: CO = N × o × β The formula assumes overtime is legally permitted and that workers possess the required skills. Overtime cost should include premium wages, fatigue-related productivity loss, accident risk, absenteeism, quality defects, and possible equipment wear—not merely the wage premium. Overtime is generally suitable for temporary peaks, urgent recovery, or a short delay in commissioning new capacity. Sustained overtime may indicate under-staffing, poor maintenance, unrealistic standards, or a structural capacity deficit. 2.5 Flexible and contingent laborFlexible labor includes part-time employees, temporary agency workers, contractors, job sharing, seasonal labor, and cross-trained internal employees. Flexibility can be numerical, temporal, functional, or locational: - Numerical flexibility: vary the number of workers.
- Temporal flexibility: vary hours or shift timing.
- Functional flexibility: move workers among tasks.
- Locational flexibility: use remote, distributed, or external work.
Cross-training is especially valuable when demand varies among work centers. Its value is not unlimited: training time, certification requirements, learning curves, and cognitive overload can reduce the apparent benefit. A skills matrix should identify which employees are qualified for which tasks and the minimum coverage required per shift. 3. Learning Effects and Workforce ProductivityNew workers and new processes often require more time initially. Repetition, feedback, improved methods, and reduced errors can lower labor content. A common cumulative-average learning-curve model is: Y = aXb where Y is the average time per unit for the first X cumulative units, a is the time for the first unit, and b is the learning exponent. For a learning rate r between 0 and 1, when output doubles, r = 2b, so: b = log(r) ÷ log(2) The model assumes that the principal driver of improvement is cumulative experience and that the production method, product design, and workforce conditions remain sufficiently stable. It is inappropriate to extrapolate indefinitely: learning eventually plateaus, and automation, redesign, worker turnover, or interruptions may reset the curve. The cumulative-average model must not be confused with the unit-time model. In the cumulative-average model, Y is the average time for all units through unit X. In the unit-time model, the time for the Xth unit itself is represented by the power function. The chosen model must match the organization’s empirical data and costing convention. Illustrative calculation. Suppose the first unit requires 100 labor-hours and the cumulative-average learning rate is 80%. At 2 cumulative units, average time is 80 hours per unit and total time is 160 hours. At 4 cumulative units, average time is 64 hours per unit and total time is 256 hours. Thus the time for units 3 and 4 together is 96 hours. This calculation illustrates why aggregate labor requirements should not be obtained by multiplying the first-unit time by total output. Learning effects have managerial implications. They support early production, pilot runs, stable teams, standardized work, and knowledge retention. However, accelerating output may require training costs, quality assurance, and temporary supervisory capacity. Learning estimates should be validated with actual time and quality data. 4. Equipment Availability and Effective CapacityEquipment capacity depends on more than nameplate speed. If a machine is scheduled for T hours, has availability A, performance efficiency P, and quality yield Q, its overall equipment effectiveness is: OEE = A × P × Q Each factor is expressed as a decimal between 0 and 1. Availability is operating time divided by planned production time; performance compares actual speed with the ideal speed for the work; quality is good output divided by total output. OEE is a diagnostic measure, not a universal measure of economic success. It should not be used to reward maximum running time when demand, maintenance, or safety requires planned idle time. If a machine is scheduled for 1,000 hours, availability is 0.90, performance is 0.95, and quality is 0.98, effective good-production time equivalent is: 1,000 × 0.90 × 0.95 × 0.98 = 837.9 good-equivalent hours The calculation is valid when the factors are defined consistently and their product is a useful approximation. Correlation among losses can make simple multiplication imperfect. Capacity planning must also consider preventive maintenance, corrective maintenance, tooling, calibration, spare parts, utilities, and operator availability. Planned maintenance reduces short-term available hours but may improve long-term availability. The relevant question is not whether maintenance consumes capacity; it is whether the chosen maintenance policy produces the required reliable capacity at acceptable life-cycle cost. 5. Subcontracting and External CapacitySubcontracting converts part of a fixed-capacity problem into a supplier-management problem. It may be used for overflow, specialized processes, geographic proximity, temporary peaks, or products outside the organization’s strategic competence. A make-or-buy comparison should include more than the supplier quotation. Relevant costs include variable internal cost, avoidable fixed cost, supplier price, transportation, inspection, coordination, inventory in transit, quality failures, switching cost, contract administration, intellectual-property protection, and disruption risk. Fixed costs that remain after outsourcing are not avoidable and should not be incorrectly treated as savings. Subcontracting is attractive when external capacity is reliable and internal capacity has a high opportunity cost. It is less attractive when the work contains proprietary knowledge, is central to quality, has uncertain supplier capacity, or is needed continuously. Contracts should specify capacity reservations, lead times, quality standards, traceability, change control, audit rights, business continuity, labor standards, and data protection. Ethically, organizations remain responsible for labor conditions and environmental impacts in their supply chains. Low-cost subcontracting that depends on unsafe work, forced labor, excessive working hours, or discriminatory practices is neither a sound governance policy nor an acceptable aggregate-planning solution. 6. Capacity Expansion and ReductionCapacity expansion alternatives include overtime, additional shifts, cross-training, equipment acquisition, facility expansion, process redesign, technology investment, and subcontracting. Their time-to-capacity and reversibility differ substantially. | Alternative | Lead time | Reversibility | Typical use |
|---|
| Overtime | Very short | High | Temporary peak | | Temporary labor | Short | High | Seasonal or uncertain demand | | Additional shift | Short to medium | Medium | Sustained utilization increase | | Subcontracting | Short to medium | Medium | Overflow or specialized work | | Equipment purchase | Medium to long | Low | Persistent capacity deficit | | Facility expansion | Long | Very low | Strategic long-term growth | | Process redesign | Medium | Variable | Structural productivity improvement |
Reduction alternatives include attrition, redeployment, reduced shifts, temporary layoffs where lawful, sale or lease of equipment, facility consolidation, and supplier transfer. Reduction can generate immediate savings but may reduce resilience and make future expansion expensive. For investment decisions, discounted cash-flow analysis may be used. The net present value of an alternative is: NPV = −I₀ + ∑(t=1 to n) CFt ÷ (1 + i)t where I0 is the initial investment, CFt is the net cash flow in period t, i is the discount rate per period, and n is the analysis horizon. The equation assumes cash flows are measured consistently and that the discount rate reflects timing and risk. Capacity investments should also be tested under alternative demand scenarios because a positive expected NPV may conceal severe downside exposure. A real-options perspective adds managerial flexibility. A modular machine, leased facility, or staged expansion may cost more per unit but preserve the option to defer, expand, or abandon as demand information improves. 7. Integrated Capacity Planning MethodA practical planning process can be organized as follows. Step 1: Translate demand into workloadForecast demand by period and product family. Convert units into standard labor-hours, machine-hours, or other resource requirements using valid rates. Include expected scrap, rework, setup, and changeover requirements where appropriate. Step 2: Profile available capacityFor each resource, calculate regular hours, overtime limits, shift availability, maintenance time, absenteeism, skill coverage, and equipment effectiveness. Separate capacity by skill and work center rather than relying on a single plant-wide number. Step 3: Identify gaps and bottlenecksCompare required workload with effective capacity. A gap can be positive, indicating surplus, or negative, indicating a deficit. Examine whether the gap is temporary, seasonal, structural, or caused by poor scheduling or low reliability. Step 4: Generate alternativesConsider inventory, backlog, overtime, shift changes, cross-training, hiring, temporary labor, subcontracting, process improvement, equipment acquisition, and demand-management actions. Alternatives should be evaluated together because one action may alter another resource’s requirement. Step 5: Evaluate total consequencesAssess direct costs, service level, lead time, quality, safety, morale, legal compliance, supplier risk, cash requirements, emissions, and strategic capability. A low wage bill can be economically inferior if it produces late delivery, defects, or employee turnover. Step 6: Select and stress-test a policyTest the preferred plan against high and low demand, absenteeism, machine failure, supplier disruption, hiring delays, and longer learning periods. Robust plans retain feasible responses under plausible shocks. Step 7: Execute and controlAssign accountability, establish trigger points, monitor leading indicators, and revise the plan through a rolling process. Important indicators include backlog, overtime hours, absenteeism, schedule adherence, OEE, yield, labor turnover, training completion, supplier performance, and capacity headroom. 8. Worked Application: Meridian AppliancesThe following is a fictional illustrative case. Meridian Appliances produces two product families over one month: Standard units and Premium units. Demand is 2,000 Standard units and 1,000 Premium units. Each Standard unit requires 2 labor-hours and each Premium unit requires 3 labor-hours. Background and problemMeridian has 30 trained production employees. Each employee is scheduled for 160 paid hours per month. The expected productive fraction is 85%. Management permits a maximum of 20 overtime hours per employee, with an expected productive fraction of 75%. A subcontractor can supply up to 400 equivalent labor-hours at a fully delivered cost of $32 per hour. Internal regular labor costs $24 per paid hour; overtime costs $36 per paid hour. For simplicity, this analysis treats the workforce as sufficiently cross-trained and excludes inventory and backlog effects. AnalysisRequired labor-hours are: H = (2,000 × 2) + (1,000 × 3) = 7,000 labor-hours Regular productive capacity is: CR = 30 × 160 × 0.85 = 4,080 labor-hours Maximum overtime productive capacity is: CO = 30 × 20 × 0.75 = 450 labor-hours Therefore, regular time plus maximum overtime provides 4,530 productive hours, leaving: 7,000 − 4,530 = 2,470 labor-hours of unmet workload. The gap is too large to solve through overtime alone. Meridian must add labor, subcontracting, another shift, productivity improvement, or a combination. Suppose Meridian considers hiring 15 additional employees. Their regular productive capacity is: 15 × 160 × 0.85 = 2,040 labor-hours Even with these hires and maximum overtime for all 45 employees, total productive capacity would be: (45 × 160 × 0.85) + (45 × 20 × 0.75) = 6,795 labor-hours A further 205-hour gap remains. The organization could subcontract 205 hours, redesign work, add a shift, or revise the demand and service commitment. Approach and solutionA balanced policy is to retain the core workforce, hire 15 employees if demand is expected to persist, use limited overtime during the learning period, and subcontract 205 hours for the current peak. If the demand is a one-month event, hiring 15 people may be inferior to temporary labor and larger subcontracting. If demand is recurring, permanent hiring and process improvement may be superior. The decision should not be based only on the arithmetic capacity gap. Meridian should examine recruitment lead time, training capacity, quality during learning, subcontractor reliability, and the Premium product’s specialist skills. If Premium work requires a constrained certification, the labor-hour calculation must be separated by skill category. Outcome and learning pointsThe case demonstrates that: - aggregate demand must be translated into resource-specific hours;
- productive hours differ from paid hours;
- maximum overtime may be inadequate for a structural deficit;
- hiring decisions depend on demand persistence and learning time;
- subcontracting can close a temporary gap but introduces supplier risk;
- feasibility analysis must be complemented by cost, quality, and workforce considerations.
9. Technology, Analytics, and Contemporary PracticeDigital workforce-management systems integrate forecasts, skills matrices, time records, maintenance plans, and production schedules. Advanced planning and scheduling systems can identify bottlenecks and simulate alternative shift patterns. Digital twins may represent equipment availability, changeovers, labor constraints, and material flows before a policy is implemented. Artificial intelligence can support demand scenarios, absence prediction, skill matching, and maintenance forecasting. However, predictive accuracy depends on data quality and stable relationships. Workforce analytics may reproduce historical discrimination if recruitment, promotion, absence, or performance data reflect biased practices. Human review, explainability, data minimization, access controls, and appeal mechanisms are essential when algorithmic recommendations affect hiring, scheduling, pay, or release. Contemporary capacity planning increasingly includes decarbonization and resilience. Energy-intensive equipment may be scheduled around renewable-energy availability or tariff periods. Dual sourcing, regional suppliers, modular equipment, and cross-training may provide resilience against geopolitical, climate, health, and logistics disruptions. These measures may raise immediate cost while reducing expected disruption loss. 10. Challenges, Limitations, and Best PracticesCapacity plans are limited by forecast error, uncertain productivity, absenteeism, machine failures, changing product mix, and imperfect cost data. A plan that is mathematically feasible may fail because workers cannot be hired in time, a supplier lacks quality capability, or the bottleneck shifts after an improvement. Best practices include: - Use standard hours carefully and update them when methods or product designs change.
- Separate capacity by skill, work center, and time period.
- Treat maintenance and quality losses as capacity realities, not unexplained exceptions.
- Maintain a stable core workforce where knowledge and safety are strategically important.
- Use overtime as a controlled buffer rather than a permanent operating model.
- Quantify total cost, including fatigue, defects, turnover, and supplier risk.
- Validate learning curves with operational data and recognize their plateau.
- Stress-test plans against demand and disruption scenarios.
- Protect employee health, dignity, privacy, and legal rights.
- Review capacity policies through a rolling, cross-functional governance process.
Chapter SummaryWorkforce and capacity planning determines whether aggregate production plans can be delivered with acceptable cost, service, quality, and risk. Capacity must be expressed in appropriate common units and distinguished as design, available, effective, and required capacity. Labor capacity depends on staffing, scheduled hours, productive fractions, skills, and work organization; equipment capacity depends on availability, performance, quality, maintenance, and bottlenecks. Organizations use level, chase, and hybrid workforce policies, supported by shifts, overtime, flexible labor, cross-training, subcontracting, inventory, and backlog. Overtime is useful for temporary peaks but dangerous as a permanent solution. Learning effects reduce labor content with experience but must be modeled with the correct learning-curve convention and validated empirically. Subcontracting can provide flexibility but creates quality, dependency, ethical, and governance obligations. Capacity expansion and reduction decisions differ in lead time, reversibility, investment, and strategic effect. A robust planning process translates demand into resource requirements, profiles effective capacity, identifies bottlenecks, evaluates alternatives, stress-tests uncertainty, and monitors execution. Modern digital and AI tools can improve visibility and scenario analysis, but they require responsible data governance and human oversight. Key TermsDesign capacity: Theoretical maximum output under specified technical conditions. Effective capacity: Realistic capacity after planned losses and operating constraints. Required capacity: Resource workload implied by the production plan. Utilization: Actual output divided by design capacity. Efficiency: Actual output divided by effective capacity. Bottleneck: Resource that most restricts system throughput. Level workforce policy: Policy maintaining relatively stable staffing. Chase strategy: Policy adjusting capacity or workforce to follow demand. Hybrid strategy: Combination of stable core capacity and flexible adjustments. Overtime: Labor performed beyond regular scheduled hours. Flexible labor: Labor whose number, timing, function, or location can be adjusted. Cross-training: Preparing employees to perform multiple tasks. Learning curve: Relationship between cumulative experience and productivity. Availability: Proportion of planned time during which equipment is operating. Overall equipment effectiveness (OEE): Product of availability, performance, and quality. Subcontracting: Procuring production or processing capacity from an external organization. Capacity headroom: Uncommitted effective capacity available for variation or disruption. Capacity expansion: Addition or improvement of resources to increase output capability. Capacity reduction: Deliberate removal, redeployment, or abandonment of capacity. Real option: Value of retaining flexibility to defer, expand, or abandon an investment. Review QuestionsShort Answer Questions- Distinguish design capacity, effective capacity, and required capacity.
- Why may overtime be unsuitable as a permanent capacity policy?
- Define a bottleneck and explain its significance in aggregate planning.
- What is the difference between a level workforce policy and a chase strategy?
- Identify three costs that should be included in a make-or-buy decision.
Long Answer Questions- Explain how staffing, shifts, overtime, flexible labor, and subcontracting can be combined in a hybrid workforce policy.
- Describe the assumptions and limitations of a cumulative-average learning-curve model.
- Explain how equipment availability, performance, quality, and maintenance affect effective capacity.
- Compare capacity expansion alternatives in terms of lead time, reversibility, cost, and strategic risk.
- Develop a systematic process for translating an aggregate production plan into a feasible workforce and capacity plan.
Analytical / Application Questions- A plant has 40 employees, each scheduled for 150 hours per month, with an 80% productive fraction. Overtime is limited to 15 hours per employee and has a 70% productive fraction. Calculate regular capacity, maximum overtime capacity, and total productive capacity.
- A product family requires 1.5 labor-hours per unit and forecast demand is 4,000 units. The plant has 4,800 regular productive labor-hours and can subcontract 500 hours. Determine the remaining capacity gap and recommend two possible responses.
- A firm must choose between hiring permanent workers for a recurring seasonal peak and subcontracting the peak. Analyze the decision using cost, learning, quality, resilience, ethical, and strategic criteria rather than direct labor cost alone.
Multiple Choice Questions with AnswersQuestion 1Which expression correctly calculates regular productive labor capacity? A. Number of workers × paid hours × productive fraction B. Demand × labor content × overtime premium C. Design capacity × scrap rate D. Machine hours ÷ number of workers Correct Answer: A. Number of workers × paid hours × productive fraction Question 2A plant schedules 1,000 machine-hours, with availability 0.90, performance 0.95, and quality 0.98. What is the effective good-equivalent capacity? A. 837.9 hours B. 850.0 hours C. 930.0 hours D. 980.0 hours Correct Answer: A. 837.9 hours Question 3Which policy maintains a relatively stable core workforce while using flexibility to absorb demand variation? A. Pure chase strategy B. Hybrid strategy C. Pure subcontracting strategy D. Zero-inventory strategy Correct Answer: B. Hybrid strategy Question 4In the cumulative-average learning-curve model, what does Y represent? A. The wage rate per employee B. The average time per unit through cumulative output X C. The total machine downtime D. The maximum overtime limit Correct Answer: B. The average time per unit through cumulative output X Question 5Which situation most strongly supports using overtime? A. A permanent structural capacity shortage B. A short-term demand peak C. A long-term need for proprietary capability D. A sustained need to reduce fatigue Correct Answer: B. A short-term demand peak Question 6Which factor is generally included in OEE? A. Availability B. Recruitment cost C. Supplier market share D. Inventory turnover Correct Answer: A. Availability Question 7Why must capacity be separated by skill category in some plans? A. All labor-hours are always interchangeable B. A surplus of one skill cannot necessarily satisfy a shortage of another C. Skill categories affect only accounting reports D. Skill separation eliminates bottlenecks Correct Answer: B. A surplus of one skill cannot necessarily satisfy a shortage of another Question 8Which cost should not automatically be counted as a saving from outsourcing? A. Avoidable internal labor cost B. Supplier transportation cost C. Fixed cost that remains after outsourcing D. External inspection cost Correct Answer: C. Fixed cost that remains after outsourcing Question 9What is a principal risk of using a high overtime level continuously? A. Guaranteed productivity improvement B. Lower fatigue and fewer defects C. Fatigue, quality loss, and absenteeism D. Automatic elimination of bottlenecks Correct Answer: C. Fatigue, quality loss, and absenteeism Question 10What is the main purpose of stress-testing a capacity plan? A. To guarantee that the forecast is correct B. To examine feasibility under plausible demand and disruption scenarios C. To eliminate the need for maintenance D. To replace all managerial judgment Correct Answer: B. To examine feasibility under plausible demand and disruption scenarios
|