Advanced Manufacturing Technology

Chapter 12
Process Planning, Modelling and Manufacturing Economics

Bachelors Program in Mechnical Engineering
Advanced Manufacturing Technology   •   Bachelor

Process Planning, Modelling and Manufacturing Economics

Introduction and Context

Advanced manufacturing is not only a matter of selecting a machine and removing material. A successful production system must convert a product specification into a sequence of operations that achieves geometric accuracy, surface integrity, delivery requirements, safety, sustainability and acceptable cost. Process planning provides this translation. Process modelling predicts the technical and economic consequences of alternative plans, while manufacturing economics supports rational decisions about equipment, capacity, outsourcing and technology investment.

These activities are strategically important because manufacturing decisions are difficult and expensive to reverse. A poorly selected process may require excessive inspection, generate scrap, create bottlenecks or expose workers and the environment to unnecessary risk. Conversely, a well-designed plan can reduce setup time, energy use and total cost while improving reliability and responsiveness.

This chapter treats process planning as an integrated engineering decision rather than as an isolated routing exercise. The discussion applies particularly to machining and other material-removal operations, but the principles also extend to additive, forming, joining and hybrid manufacturing.

Learning Objectives

After studying this chapter, the reader should be able to:

  1. Develop a process plan from a part drawing, material specification and production requirement.
  2. Model material removal, machining time, energy, capacity and manufacturing cost.
  3. Compare process alternatives using productivity, risk, life-cycle and multi-criteria methods.
  4. Distinguish fixed, variable, direct, indirect, avoidable and opportunity costs.
  5. Evaluate make-or-buy decisions and technology-investment proposals.
  6. Recognize the effects of uncertainty, quality, sustainability, ethics and digital technology on manufacturing decisions.

1. Process Planning as an Engineering System

A process plan specifies how a product will be made. It normally includes:

  • interpretation of the design and functional requirements;
  • material, blank and stock selection;
  • datum and workholding strategy;
  • operation sequence and machine selection;
  • cutting tools, fixtures, gauges and inspection operations;
  • process parameters and quality-control requirements;
  • labor, handling, safety and environmental requirements; and
  • estimated time, capacity, cost and risks.

A plan is constrained by several interacting factors. The part must satisfy dimensional and geometric tolerances, surface-finish requirements, material properties, batch size, delivery date, available equipment, operator competence, regulatory requirements and economic targets. Optimization of one factor can worsen another. For example, a high cutting speed may reduce machining time but increase tool wear, thermal damage or scrap.

1.1 Product and production information

The planner should first establish:

InformationTypical questions
Product functionWhich dimensions and surfaces are functionally critical?
MaterialWhat are hardness, strength, machinability and environmental constraints?
QuantityIs production one-off, batch, repetitive or mass production?
QualityWhat tolerances, surface finishes and inspection evidence are required?
ResourcesWhich machines, tools, fixtures, skills and software are available?
DeliveryWhat completion date and demand pattern must be supported?
ComplianceWhich safety, quality, traceability and environmental rules apply?

A planner should separate design requirements from process preferences. A drawing may require a positional tolerance and a surface roughness, but it does not necessarily prescribe a particular machine. This distinction creates scope for alternative process plans.

1.2 Features, datums and precedence

Feature-based planning represents a component as manufacturing features such as holes, pockets, slots, bosses, turned diameters, threads and free-form surfaces. Each feature has attributes including dimensions, tolerance, surface condition and material condition. Feature precedence is governed by design logic and process capability. For example, a datum surface may need to be produced before accurately locating a hole pattern; rough machining usually precedes finish machining; and heat treatment may occur between roughing and finishing when distortion is expected.

The datum scheme should preserve functional relationships. A workholding arrangement that references a nonfunctional surface may produce an acceptable individual dimension but poor assembly accuracy. The planner therefore considers the 3-2-1 locating principle, in which three points constrain one plane, two constrain a second direction and one constrains the final direction. The exact fixture design depends on the part, but the general aim is repeatable and sufficiently rigid location without damaging the workpiece.

2. Developing a Process Plan

A robust planning sequence is as follows:

  1. Examine the drawing, 3D model, material and revision status.
  2. Identify critical features, datums, tolerances and inspection requirements.
  3. Select a suitable raw-material form and determine the allowance for processing.
  4. Group operations according to machine capability, datum consistency and thermal or metallurgical requirements.
  5. Establish a roughing-to-finishing sequence.
  6. Select machines, tools, fixtures, workholding and inspection equipment.
  7. Determine cutting conditions within verified capability limits.
  8. Estimate setup, processing, handling, inspection and delay times.
  9. Evaluate quality, capacity, cost, risk, energy and environmental effects.
  10. Validate the plan through simulation, first-article production and feedback.

A process plan is often documented as a routing sheet or manufacturing bill of process. A useful routing record identifies the operation number, work centre, setup, tooling, instructions, inspection points, estimated time and acceptance criteria.

2.1 Roughing, semi-finishing and finishing

Roughing removes most excess material economically. It generally uses larger depths of cut or deposition rates and leaves an allowance for subsequent operations. Semi-finishing establishes intermediate geometry and reduces the burden on finishing. Finishing produces the final tolerance and surface condition, often with lower material-removal rates and more controlled parameters.

This division is not universal. A near-net-shape process may require little roughing, while hard machining may replace grinding. The correct sequence depends on material, distortion, residual stress, tool access and required accuracy.

2.2 Setup reduction and process integration

Every setup can introduce location error, clamping time and work-in-process. Combining operations in a machining centre, mill-turn centre or flexible cell can reduce handling and improve datum consistency. However, integration may increase equipment cost, programming complexity and dependence on a single machine. The decision must therefore compare total system performance rather than simply count operations.

3. Models of Material Removal and Production Time

Models are simplified representations used for prediction and comparison. Their value depends on explicit assumptions and calibration with actual production data.

3.1 Material-removal rate

For a milling operation with cutter width of cut w, axial depth of cut ap and table feed vf, the ideal volumetric material-removal rate is:

Q = w ap vf

where Q is material-removal rate in mm³/min when the dimensions are in mm and feed is in mm/min. This expression assumes approximately rectangular engagement and does not account for tool-path interruptions, chip thinning, entry and exit effects or machine limitations.

For turning, an approximate cross-sectional removal model is:

Q = π D n f ap

where D is workpiece diameter (mm), n is rotational speed (rev/min), f is feed per revolution (mm/rev), and ap is radial depth of cut (mm). Since πDn is cutting speed in mm/min, the units are mm³/min. For large diameter changes, a more exact volume calculation based on the initial and final cylindrical volumes is preferable.

The theoretical cutting speed for a rotating diameter is:

vc = π D n

Here vc is in mm/min if D is in mm. When cutting speed is specified in m/min:

vc = (π D n) ÷ 1000

The equations are kinematic relationships, not complete process models. Actual production must respect tool-maker recommendations, machine power, rigidity, chip control, workholding and material behaviour.

3.2 Machining time

If a volume V is removed at an effective removal rate Q, ideal cutting time is:

tc = V ÷ Q

The total operation time is better represented as:

top = tsetup ÷ N + tload + tc + ttool + tinspect + thandle + tdelay

where N is batch quantity and all terms are expressed in consistent time units. Setup time is allocated per part only when a batch is being evaluated. ttool may include tool changes and tool-setting activities; tdelay represents expected minor stoppages or other planned allowances.

For a simple turning pass over a length L, including approach distance La, feed per revolution f and speed n, the pass time is:

tc = (L + La) ÷ (f n)

This assumes constant diameter and feed, one continuous pass and negligible acceleration or deceleration time.

Worked Example 1: Turning time and capacity

A shaft requires a turning pass over 180 mm. The approach allowance is 5 mm, feed is 0.25 mm/rev and spindle speed is 800 rev/min. The cutting time is:

tc = (180 + 5) ÷ (0.25 × 800) = 0.925 min

Suppose setup time is 45 min for a batch of 30 parts, loading and unloading require 0.40 min per part, inspection requires 0.15 min, and tool-related time is 0.10 min. Ignoring delays:

top = 45 ÷ 30 + 0.40 + 0.925 + 0.10 + 0.15 = 3.075 min/part

A nominal 8-hour shift contains 480 min. If the required production time is fully available and no additional allowance is applied, the theoretical capacity is:

Capacity = 480 ÷ 3.075 ≈ 156 parts/shift

This is not guaranteed output. Availability losses, quality losses, breaks, maintenance and material shortages reduce practical capacity.

3.3 Capacity and bottlenecks

For a resource with available production time Tavail and workload Tload, utilization is:

U = Tload ÷ Tavail

A value above 1 indicates that the required load exceeds available capacity. In a multi-operation route, the operation with the greatest capacity burden or least effective capacity often becomes the bottleneck. Bottleneck analysis should include setup patterns, batch sizes, changeovers, downtime and yield, not only nominal cycle time.

A simple effective-capacity model is:

Teff = Tscheduled A P Y

where A is availability, P is performance efficiency and Y is yield, all expressed as fractions. This structure is closely related to overall equipment effectiveness. It is useful only if the three factors are defined without double counting losses.

4. Energy, Power and Environmental Modelling

Cutting power is related to material-removal rate and specific cutting energy. A simplified model is:

Pcut = u Q

where Pcut is cutting power, u is specific cutting energy and Q is material-removal rate. If u is in J/mm³ and Q is in mm³/s, Pcut is in watts. Actual spindle power is higher because of transmission and motor losses:

Pin = Pcut ÷ η

where η is overall efficiency between 0 and 1.

Energy per part can be estimated by integrating power over time:

Epart = ∫ P(t) dt

For constant average power, this reduces to Epart = Pavg top. Units must be reconciled; for example, watts multiplied by seconds gives joules, while kilowatts multiplied by hours gives kilowatt-hours.

Energy analysis should include machine standby, coolant pumps, compressed air, chip handling, heating, inspection and rework where material. A process with higher cutting power may still consume less energy per part if it substantially reduces cycle time and scrap.

Life-cycle assessment broadens the boundary to raw-material production, transport, manufacturing, use and end-of-life. The appropriate boundary must be stated because conclusions can change when embodied material energy or recycling is included.

5. Manufacturing Cost Models

Manufacturing cost should be structured rather than treated as a single hourly rate. Common categories include:

  • direct material and consumables;
  • direct labor;
  • machine and facility time;
  • tooling and fixture cost;
  • programming and setup;
  • inspection and quality assurance;
  • maintenance, utilities and waste treatment;
  • scrap, rework, warranty and failure costs; and
  • allocated overhead.

For a batch, a useful total-cost model is:

Ctotal = Cfixed + N Cvariable

where Cfixed includes costs incurred for the batch or decision, Cvariable is variable cost per acceptable part, and N is quantity. If scrap probability is s, the expected production quantity required for Ngood good parts, under an independent constant-yield assumption, is:

Nproduced = Ngood ÷ (1 − s)

This simple relationship does not model rework loops or changing quality with production volume.

A machine-hour cost may be written as:

Cmachine = rm tm

where rm is the applicable machine rate per hour and tm is machine occupation time in hours. The rate should be constructed carefully. It may include depreciation, maintenance, energy, space and support, but fixed costs should not be counted again as separate avoidable costs in a decision analysis.

5.1 Break-even analysis

For two alternatives with fixed costs F1, F2 and variable costs v1, v2, the quantity at which their costs are equal is:

NBE = (F2 − F1) ÷ (v1 − v2)

This formula applies when v1 ≠ v2, costs are linear over the relevant range, quality and output are comparable, and the resulting quantity is meaningful and nonnegative. If the denominator is zero, there is no finite break-even quantity unless fixed costs are also equal.

Worked Example 2: Comparing two process routes

Route A requires a fixture and programming investment of $18,000 and costs $42 per acceptable part. Route B has no special investment but costs $58 per acceptable part. The break-even quantity is:

NBE = (18,000 − 0) ÷ (58 − 42) = 1,125 parts

Above 1,125 parts, Route A has the lower direct cost, assuming equal quality, capacity and delivery performance. Below that quantity, Route B is less expensive. The decision should still consider fixture life, flexibility, risk, lead time, cash flow and future demand.

5.2 Relevant cost and sunk cost

A cost is relevant to a decision if it differs between alternatives and occurs in the future. A sunk cost has already been incurred and cannot be changed by the decision; it should not influence a purely forward-looking comparison. Opportunity cost is the benefit lost when a resource is assigned to one use instead of its best alternative. These distinctions are essential in make-or-buy decisions and when evaluating an underutilized machine.

6. Decision Methods for Alternative Process Plans

No single metric captures manufacturing performance. A useful comparison begins with feasibility screening. An alternative that cannot achieve tolerance, material integrity, safety or delivery requirements should normally be rejected before detailed economic ranking.

For feasible alternatives, evaluation may include:

CriterionExample measure
CostCost per acceptable part, total cost of ownership
ProductivityParts per hour, throughput, setup time
QualityYield, capability, defects per unit
FlexibilityProduct range, changeover time, scalability
RiskSupply, technology, safety and process uncertainty
SustainabilityEnergy, waste, emissions and recyclability
DeliveryLead time, queue exposure and capacity margin
Strategic valueSkills, intellectual property and future capability

6.1 Weighted-scoring method

A weighted decision matrix assigns normalized scores sij to alternative i on criterion j, with weights wj satisfying:

∑ wj = 1

The total score is:

Si = ∑ wj sij

Scores must be defined so that higher always means better. Cost, defect rate and risk therefore need to be transformed or scored inversely. The method is transparent but depends on judgment, scale selection and weight sensitivity. A sensitivity analysis should test whether a small change in weights changes the preferred alternative.

6.2 Risk and uncertainty

Expected cost can be represented as:

E[C] = ∑ pk Ck

where pk is the probability of scenario k, Ck is its cost, and the probabilities sum to one. Expected value alone is insufficient when consequences are severe or probabilities are uncertain. A low-probability safety failure may be unacceptable even if its expected monetary cost is small.

Useful risk responses include prevention, detection, containment, supplier qualification, spare capacity, standardization and contingency planning. Failure Mode and Effects Analysis can rank failure modes using severity, occurrence and detectability ratings, but numerical rankings should not replace engineering judgment or legal safety obligations.

7. Make-or-Buy and Technology Investment

A make-or-buy decision compares the avoidable internal cost and strategic consequences of producing an item with the supplier alternative. Internal production may offer control of quality, intellectual property, responsiveness and learning. Purchasing may offer lower cost, specialist capability, reduced capital commitment and access to scale.

The comparison should include:

  • supplier price, freight, inspection and incoming quality costs;
  • internal material, labor, energy, tooling and maintenance;
  • avoidable overhead and opportunity cost of capacity;
  • supplier qualification and switching cost;
  • lead-time and supply-disruption risk;
  • confidentiality, intellectual property and regulatory requirements; and
  • long-term demand and technology development.

An existing internal fixed cost is not automatically avoidable. If the machine remains regardless of the decision, its depreciation may be irrelevant in the short-term comparison. In the long term, replacement and capacity-investment decisions may make it relevant.

A technology-investment proposal should state the baseline, incremental cash flows, useful life, residual value, taxes where applicable, capacity effect and risk. Simple payback is:

Payback period = Initial investment ÷ Annual net cash benefit

This is easy to understand but ignores benefits after payback and the time value of money. For a discount rate r, net present value is:

NPV = −I0 + ∑[CFt ÷ (1 + r)t] + RV ÷ (1 + r)T

where I0 is initial investment, CFt is net cash flow in period t, RV is residual value at the end of period T, and T is project life. The formula assumes cash flows occur at specified period ends and that the discount rate is appropriate to their risk. A positive NPV indicates value creation relative to the chosen discount rate, subject to reliable forecasts.

8. Digital Process Planning, Simulation and AI

Computer-aided process planning systems can retrieve standard operations, generate feature-based routes and connect planning with enterprise-resource-planning systems. Digital twins and discrete-event simulation can estimate queueing, bottlenecks, utilization and delivery performance before physical implementation.

AI and machine learning can support parameter recommendation, tool-wear prediction, anomaly detection, visual inspection and demand forecasting. Their use requires representative data, validated models, traceability and human oversight. A model trained on one alloy, machine or tool geometry may fail when conditions change. Automated recommendations should therefore be bounded by verified process windows and approved by competent engineers.

Data governance includes version control, access rights, cybersecurity, intellectual-property protection and audit trails. A digitally optimized process that exposes production systems to cyberattack or produces untraceable quality decisions is not professionally adequate.

9. Illustrative Case: Choosing a Process for an Aerospace Bracket

Background

This illustrative case concerns a small aluminum aerospace bracket produced in batches of 2,000 units per year. The design requires several precision holes, a pocket, a controlled surface finish and traceable inspection. Two feasible alternatives are considered.

Problem

Route A uses a three-axis machining centre with two setups and a dedicated fixture. Route B uses a five-axis machining centre with one setup but a higher machine rate. The company must select a route that meets quality and annual demand while considering cost, delivery and risk.

Analysis

Suppose the estimated data are:

ItemRoute ARoute B
Annual fixed or special cost$24,000$8,000
Variable cost per acceptable part$31$39
Yield96%99%
Average operation time per produced part18 min11 min
Special setup count21

For 2,000 acceptable parts, expected production quantities under the constant-yield approximation are:

NA = 2,000 ÷ 0.96 ≈ 2,083 parts
NB = 2,000 ÷ 0.99 ≈ 2,020 parts

The approximate annual variable costs are therefore:

CA = 24,000 + 2,083 × 31 ≈ $88,573
CB = 8,000 + 2,020 × 39 ≈ $86,780

Route B has the lower estimated annual cost by approximately $1,793 and also has shorter processing time and fewer setups. However, the five-axis machine is shared with other high-priority work. If its capacity margin is inadequate, the apparent advantage may disappear through delays or overtime. The team should verify available hours, fixture lead time, programming capability, maintenance support and the effect of demand variability.

A weighted assessment might give Route B a higher score for quality, setup reduction and throughput, while Route A scores higher for equipment availability and operator familiarity. Sensitivity analysis should vary the yield, demand and machine opportunity cost. A pilot batch can validate dimensional capability and actual cycle time before full adoption.

Outcome and learning points

The appropriate decision is not simply “choose the cheaper cycle.” Route B is provisionally preferred because its estimated annual total cost, yield and setup performance are favorable, but approval should depend on demonstrated capacity and process capability. The case illustrates four principles: include quality losses, compare total rather than isolated costs, account for capacity opportunity cost, and validate assumptions with production evidence.

10. Challenges, Limitations and Professional Practice

Process models contain uncertainty. Cutting conditions may vary with tool wear, material batch, coolant condition and operator practice. Cost models may be distorted by arbitrary overhead allocation, optimistic yield assumptions or omitted inspection and rework. Forecast demand may not justify a dedicated fixture or machine. For these reasons, planners should document assumptions, use ranges where appropriate and update estimates with actual data.

Quality must be engineered into the process rather than inspected only at the end. Capability studies, control plans, measurement-system evaluation and first-article approval are appropriate when risk warrants them. A process capable of meeting tolerance consistently is preferable to one that merely produces occasional conforming parts.

Ethical and regulatory responsibilities include protecting workers from hazardous energy, cutting fluids, noise and airborne contaminants; preventing unsafe automation; managing waste; ensuring truthful cost and capability reporting; and maintaining traceability for safety-critical products. Cost reduction never justifies bypassing mandatory safeguards or concealing defects.

Best practice is to use cross-functional reviews involving design, manufacturing, quality, maintenance, supply chain, finance and operators. The final plan should be technically feasible, economically defensible, auditable and understandable to those who execute it.

Chapter Summary

Process planning converts product requirements into an ordered, controlled and economically viable manufacturing route. Effective planning depends on feature interpretation, datum selection, roughing and finishing logic, workholding, machine capability, inspection and capacity.

Material-removal and time models provide useful first estimates. Milling and turning relationships can estimate removal rate and cutting time, but real production requires allowances for setup, loading, tooling, inspection, delays, yield and machine efficiency. Energy models should include both cutting and non-cutting loads, while life-cycle analysis defines a broader environmental boundary.

Manufacturing economics distinguishes fixed, variable, relevant, sunk and opportunity costs. Break-even, expected-cost, weighted-scoring, risk and NPV methods support different decisions and should not be applied mechanically. Make-or-buy and technology-investment decisions must include capacity, quality, resilience, learning, safety and strategic considerations.

Digital planning, simulation and AI improve prediction and responsiveness when supported by valid data, traceability, cybersecurity and human engineering judgment. The best process is not necessarily the one with the lowest nominal unit cost; it is the one that reliably meets requirements while creating acceptable total value over its life cycle.

Key Terms

Process planning: The systematic definition of operations, resources, parameters and controls needed to manufacture a product.

Routing: The ordered list of manufacturing operations and work centres.

Datum: A reference feature or plane used to locate, measure or manufacture a part.

Setup: The preparation and location of a workpiece for a group of operations.

Roughing: High-productivity removal of excess material before final accuracy is required.

Finishing: Processing intended to achieve final dimensions, tolerance and surface condition.

Material-removal rate: Volume of material removed per unit time.

Cycle time: Time required to complete a defined operation or part cycle.

Capacity: The maximum feasible output of a resource in a stated period.

Bottleneck: A constrained resource that limits system throughput.

Yield: Fraction of produced units accepted without the defined quality disposition.

Fixed cost: Cost that does not vary directly with short-term production quantity.

Variable cost: Cost that changes with production quantity or activity.

Relevant cost: Future cost that differs between alternatives.

Opportunity cost: Value of the best alternative use of a constrained resource.

Break-even quantity: Output at which two cost alternatives have equal total cost.

Life-cycle assessment: Evaluation of environmental impacts across defined product-life stages.

Net present value: Present value of future project cash flows less initial investment.

Weighted decision matrix: Multi-criteria method combining criterion scores with assigned weights.

Digital twin: A data-connected digital representation used to analyze or control a physical system.

Review Questions

Short Answer Questions

  1. What information should be extracted from a part drawing before selecting a process route?
  2. Distinguish roughing, semi-finishing and finishing operations.
  3. Define bottleneck and explain its effect on capacity.
  4. Why is a sunk cost normally excluded from a short-term make-or-buy decision?
  5. State two limitations of a weighted-scoring decision matrix.

Long Answer Questions

  1. Explain a systematic procedure for developing a process plan for a precision machined component.
  2. Derive and discuss the turning-time relationship, including its assumptions and limitations.
  3. Explain how quality yield, setup time and machine capacity influence manufacturing cost.
  4. Compare break-even analysis, expected-cost analysis and net present value as decision tools.
  5. Discuss how digital process planning and AI can improve manufacturing decisions while creating new governance risks.

Analytical / Application Questions

  1. A turning operation has a cutting length of 240 mm, an approach allowance of 10 mm, feed of 0.20 mm/rev and spindle speed of 1,000 rev/min. Calculate the cutting time and identify two practical factors that could make actual time higher.
  2. A supplier offers a component for $46 each. Internal production has an avoidable fixed cost of $12,000 and an avoidable variable cost of $38 each. Determine the break-even quantity and explain what additional nonfinancial factors should be evaluated.
  3. Two process alternatives have different costs, yields, energy use and delivery risks. Design a weighted decision matrix, state suitable criteria and explain how you would test whether the recommendation is sensitive to the assigned weights.

Multiple Choice Questions with Answers

Question 1

Which activity normally occurs first when developing a process plan?

A. Selecting cutting speed

B. Interpreting the drawing, material and requirements

C. Allocating overhead cost

D. Ordering replacement tools

Correct Answer: B. Interpreting the drawing, material and requirements

Question 2

For milling, the ideal material-removal relationship is Q = w ap vf. What does vf represent?

A. Cutter diameter

B. Axial depth of cut

C. Table feed

D. Specific cutting energy

Correct Answer: C. Table feed

Question 3

A batch has a setup time of 60 minutes and contains 20 parts. The setup time allocated per part is:

A. 0.33 min

B. 3 min

C. 20 min

D. 80 min

Correct Answer: B. 3 min

Question 4

Which cost is generally irrelevant to a short-term decision if it has already been incurred and cannot be changed?

A. Opportunity cost

B. Avoidable future cost

C. Sunk cost

D. Incremental material cost

Correct Answer: C. Sunk cost

Question 5

If a process has availability 0.90, performance efficiency 0.80 and yield 0.95, the combined effective factor is:

A. 0.684

B. 0.720

C. 0.855

D. 2.650

Correct Answer: A. 0.684

Question 6

Two alternatives have fixed costs of $10,000 and $4,000, and variable costs of $25 and $31 per part, respectively. The break-even quantity is:

A. 500 parts

B. 1,000 parts

C. 2,000 parts

D. 6,000 parts

Correct Answer: C. 2,000 parts

Question 7

In a weighted decision matrix, the criterion weights should normally:

A. All equal zero

B. Sum to one

C. Be expressed only in dollars

D. Be larger for every low-scoring alternative

Correct Answer: B. Sum to one

Question 8

In the simplified cutting-power model Pcut = uQ, u denotes:

A. Machine utilization

B. Specific cutting energy

C. Tool diameter

D. Material yield

Correct Answer: B. Specific cutting energy

Question 9

Why should a feasible-process screening step precede economic ranking?

A. To eliminate all alternatives with setup time

B. To reject options that cannot meet essential technical or safety requirements

C. To ensure the most expensive process is selected

D. To avoid considering quality

Correct Answer: B. To reject options that cannot meet essential technical or safety requirements

Question 10

A positive NPV generally indicates that a project:

A. Has zero initial investment

B. Creates value relative to the selected discount rate and assumptions

C. Has the shortest physical cycle time

D. Has no operational risk

Correct Answer: B. Creates value relative to the selected discount rate and assumptions