Advanced Cost & Management Accounting

Chapter 8
Relevant Costing and Short-Term Managerial Decisions

Bachelors Program in Accounting and Finance
Advanced Cost & Management Accounting   •   Bachelor

Relevant Costing and Short-Term Managerial Decisions

Introduction

Managers frequently choose among alternatives whose financial consequences differ from those reported in conventional product-cost statements. Decisions such as making or buying a component, accepting a special order, closing an operation, processing a joint product further, replacing equipment, or selecting a product mix require relevant costing: the identification of future revenues and costs that change because one alternative is selected instead of another.

The term short-term does not imply that strategic consequences are unimportant. A decision may affect only the next month’s profit yet also influence quality, employees, supply-chain resilience, customer expectations, intellectual property, and long-term competitive position. Relevant-cost analysis therefore provides disciplined financial evidence, not an automatic decision rule.

Learning Objectives

After studying this chapter, students should be able to:

  1. Distinguish relevant costs and revenues from sunk, unavoidable, and allocated amounts.
  2. Apply incremental analysis to make-or-buy, outsourcing, special-order, shutdown, further-processing, and replacement decisions.
  3. rank products when one resource limits output and formulate multi-constraint product-mix problems.
  4. Apply theory-of-constraints concepts to bottleneck decisions.
  5. Incorporate opportunity cost, risk, quality, ethics, and strategic consequences into recommendations.

1. Foundations of Relevant Costing

1.1 The relevance test

A revenue or cost is relevant when it satisfies both conditions:

  1. It relates to the future; and
  2. It differs between feasible alternatives.

A future cost that is identical under every alternative is irrelevant. A past cost cannot be changed and is therefore irrelevant, even if it appears prominently in the accounting records.

The financial effect of choosing an alternative can be expressed as:

Δπ = ΔR − ΔC − OC

where:

  • Δπ = change in operating profit, in currency;
  • ΔR = incremental revenue;
  • ΔC = incremental explicit cost; and
  • OC = opportunity cost of resources diverted from their best alternative use.

The expression applies when all terms cover the same decision horizon and are measured on a consistent basis. Opportunity cost should not be subtracted again if it has already been included within incremental costs.

1.2 Cost classifications for decisions

ClassificationMeaningTypical treatment
Incremental costAdditional cost caused by an alternativeRelevant
Differential costDifference in cost between alternativesRelevant
Avoidable costCost eliminated by rejecting or discontinuing an activityRelevant
Sunk costCost already incurred and irreversibleIrrelevant
Opportunity costBenefit sacrificed by using a resource in one way rather than its best alternativeRelevant
Unavoidable costFuture cost that remains under all alternativesIrrelevant to the choice
Allocated common costShare of a common cost assigned by an accounting ruleRelevant only if total cash flow changes
Committed costCost arising from an existing obligationRelevant only to the extent it can still be changed

Book value is normally a sunk accounting amount. It may nevertheless affect cash flow if taxation rules make a disposal gain, loss, or capital allowance tax-relevant.

1.3 A disciplined decision process

A sound analysis proceeds through five stages:

  1. Define feasible alternatives and the decision horizon.
  2. Identify revenues, cash costs, capacity requirements, and constraints that differ.
  3. Remove sunk costs and unavoidable common costs.
  4. quantify opportunity costs, timing, risk, and tax effects where material.
  5. Evaluate qualitative and strategic consequences before authorization.

This approach prevents two common errors: treating all variable costs as relevant and treating all fixed costs as irrelevant. A variable cost is irrelevant if it does not change; a fixed cost is relevant if it can be avoided.

2. Make-or-Buy and Outsourcing Decisions

A make-or-buy decision determines whether an input should be produced internally or purchased externally. Outsourcing is broader and may transfer an entire process, service, workforce, technology platform, or business function to a third party.

For a specified quantity, the relevant economic costs are:

Relevant cost of making = Avoidable production costs + Opportunity cost of internal capacity
Relevant cost of buying = Purchase price + Incremental procurement, transport, inspection and transition costs

Unavoidable factory rent or allocated head-office costs are excluded because they remain under both alternatives.

Worked Example 1: Component sourcing

A manufacturer needs 10,000 components. Internal costs per component are:

Cost itemAmount per unit
Direct materials$5.00
Direct labour$3.00
Variable overhead$2.00
Avoidable supervision$1.00
Unavoidable allocated fixed overhead$3.00

A supplier quotes $12.20 per component, plus delivery of $0.30.

If internal capacity has no alternative use:

  • Relevant make cost = 10,000 × ($5 + $3 + $2 + $1) = $110,000.
  • Relevant buy cost = 10,000 × ($12.20 + $0.30) = $125,000.

Making saves $15,000. The $30,000 unavoidable allocation is excluded.

Suppose outsourcing would release capacity that could earn $20,000 contribution margin. The economic cost of making becomes $110,000 + $20,000 = $130,000. Buying for $125,000 would then improve profit by $5,000.

Strategic considerations

A financially attractive supplier may still expose the organization to defective inputs, delivery disruption, currency movements, cyber risk, labour-practice violations, or loss of proprietary knowledge. Conversely, internal production can conceal poor efficiency because allocated costs or organizational preferences protect it from external comparison.

Supplier evaluation should address total cost of ownership, service-level agreements, audit rights, business continuity, data security, environmental standards, dependency, and reversibility. Outsourcing a core capability solely for a short-term saving may weaken long-term competitiveness.

3. Special-Order Decisions

A special order is a non-routine request, often involving a different customer, quantity, specification, or price. The order should be accepted financially when its incremental revenue exceeds incremental costs and opportunity costs.

Incremental profit from order = Special-order revenue − Incremental order costs − Opportunity cost

With genuinely idle capacity, existing fixed manufacturing overhead is usually irrelevant unless the order changes it. Relevant costs may include direct materials, labour, variable overhead, special packaging, design, inspection, setup, freight, commissions, and incremental administration.

If capacity is fully used, accepting the order displaces regular sales or another activity. The lost contribution margin is an opportunity cost.

Worked Example 2: Idle versus constrained capacity

A company receives an order for 1,000 units at $42 each. Incremental manufacturing cost is $34 per unit and a one-time setup costs $3,000.

With idle capacity:

  • Revenue = $42,000.
  • Variable cost = $34,000.
  • Setup cost = $3,000.
  • Incremental profit = $5,000.

If the order instead displaces regular business contributing $7,500, its economic effect is $5,000 − $7,500 = $(2,500). It should normally be rejected.

Managers must also consider whether discounted sales will leak into the regular market, establish an unsustainable reference price, violate competition law, or weaken distributor relationships.

4. Temporary Shutdown and Closure

A temporary shutdown decision compares operating for a limited period with suspending activity. Depreciation, allocated head-office costs, and other unavoidable costs should not be used to justify closure.

The advantage of continuing rather than shutting down is:

Advantage of continuing = Revenue − Costs incurred only if operating + Costs incurred only if shut down − Opportunity cost

Continue when this amount is positive. The formula assumes the compared amounts relate to the same period and excludes costs common to both alternatives.

Worked Example 3: Seasonal operation

During an off-season, a hotel expects revenue of $180,000 and variable operating costs of $90,000. Of $120,000 in fixed costs, $70,000 can be avoided by closing; the remaining $50,000 continues either way. Closure would also require $15,000 for security and preservation.

The advantage of remaining open is:

$180,000 − $90,000 − $70,000 + $15,000 = $35,000

The hotel should remain open on financial grounds. The unavoidable $50,000 is excluded from the comparison.

Longer-term closure analysis must also include restart costs, asset deterioration, employee redundancy obligations, customer loss, licence conditions, and the possibility that suspended capacity cannot be restored promptly.

5. Sell at Split-Off or Process Further

Joint products share a common production process until the split-off point. Joint costs incurred before split-off are sunk with respect to a further-processing decision because they do not change between selling now and processing further.

Gain from further processing = Incremental sales value − Incremental processing cost − Opportunity cost

Processing is financially worthwhile when the gain is positive. Calculations must recognize processing losses, altered output quantities, additional by-products, and disposal costs.

Worked Example 4: Processing loss

At split-off, 5,000 units can be sold for $12 each, giving revenue of $60,000. Further processing costs $18,000 but yields only 4,800 saleable units, each worth $17.

  • Revenue after processing = 4,800 × $17 = $81,600.
  • Incremental revenue = $81,600 − $60,000 = $21,600.
  • Incremental gain = $21,600 − $18,000 = $3,600.

Further processing is preferred. Any joint cost incurred before split-off is irrelevant to this decision, although it remains relevant to inventory valuation and external reporting.

6. Equipment Replacement

Replacement decisions are sometimes distorted by the old asset’s book value. The original purchase price and accumulated depreciation are sunk. Relevant amounts include the new asset’s acquisition and installation cost, the old asset’s current disposal proceeds, differences in revenues and operating costs, working-capital effects, tax consequences, and the terminal values of both alternatives.

For a replacement project with a common evaluation horizon of n periods, a general pre-tax incremental model is:

NPVreplace = −I0 + Dold,0 − ΔWC0 + ∑t=1n [(Rnew,t − Rold,t) + (OCold,t − OCnew,t)]/(1+r)t + [(TVnew,n − TVold,n) + ΔWCn]/(1+r)n

where:

  • I0 = purchase, installation, and initial transition cost of the new asset at time 0;
  • Dold,0 = net proceeds from disposing of the old asset immediately;
  • ΔWC0 = additional working capital invested initially;
  • Rnew,t and Rold,t = revenues under the new and old alternatives in period t;
  • OCnew,t and OCold,t = cash operating costs of the new and old assets in period t;
  • TVnew,n and TVold,n = net terminal values at the end of period n;
  • ΔWCn = incremental working capital recovered at the end of the horizon;
  • r = discount rate per period; and
  • t = 1, …, n.

All cash flows must use the same currency, price basis, tax basis, and period. If revenues are unchanged, the annual operating benefit is the net operating-cost saving, OCold,t − OCnew,t, not the old machine’s avoided cost alone. Where lives differ, equivalent annual cost, repeat-chain analysis, or an appropriate common horizon may be required.

Worked Example 5: Replacement NPV

A new machine costs $120,000. The old machine can be sold now for $15,000. For four years, the new machine will reduce annual cash operating costs from $70,000 to $38,000. At year 4, the new machine will be worth $10,000 and the old machine would have been worth $2,000. Revenues and working capital are unchanged. The discount rate is 10%.

The annual net operating-cost saving is $70,000 − $38,000 = $32,000. Using the four-year annuity factor of 3.169865 and year-4 discount factor of 0.683013:

NPVreplace = −$120,000 + $15,000 + ($32,000 × 3.169865) + [($10,000 − $2,000) × 0.683013]
NPVreplace = −$105,000 + $101,435.68 + $5,464.10 = $1,899.78

Replacement is financially acceptable by approximately $1,900 before tax. Given the small margin, sensitivity to maintenance, downtime, useful life, and discount-rate assumptions is important.

7. Product Mix Under a Limiting Factor

When demand exceeds available capacity, total contribution margin—not contribution per unit—must be optimized. With one binding resource and divisible products, products are ranked by contribution margin per unit of the scarce resource:

Contribution per unit of limiting factor = Contribution margin per unit ÷ Scarce-resource units required per product unit

This ranking rule assumes one binding constraint, linear revenues and variable costs, known resource usage, independent products, and no indivisibilities, setup interactions, minimum batches, or mandatory product commitments.

Worked Example 6: One scarce resource

ProductContribution per unitMachine hours per unitContribution per machine hourMaximum demand
A$303$10400 units
B$241$24700 units

With 1,300 machine hours, produce B first: 700 units use 700 hours and earn $16,800. The remaining 600 hours produce 200 units of A, earning $6,000. Total contribution is $22,800.

Ranking by contribution per unit would incorrectly prioritize A.

Multiple constraints and linear programming

When several resources may bind, a simple ranking is generally invalid. A product-mix model can be formulated as:

Maximize Z = ∑i=1m ci xi

subject to:

∑i=1m akixi ≤ bk, k = 1, …, K
0 ≤ xi ≤ di

where:

  • xi = units of product i;
  • ci = contribution margin per unit;
  • aki = units of resource k required per unit of product i;
  • bk = available quantity of resource k;
  • di = maximum demand; and
  • Z = total contribution margin.

Integer restrictions are necessary when products cannot be divided. A constraint’s shadow price measures the improvement in the objective from one additional unit of that resource, but only within the allowable range over which the current solution basis remains valid.

8. Theory of Constraints

The theory of constraints (TOC) views system performance as governed by its most restrictive constraint. Its recurring improvement process is:

  1. Identify the system constraint.
  2. Exploit the constraint using existing resources effectively.
  3. Subordinate non-constraint activities to the constraint.
  4. Elevate the constraint by adding or redesigning capacity.
  5. Repeat after the constraint moves.

TOC commonly defines throughput as sales revenue less totally variable cost, often direct materials in a very short-run manufacturing setting:

Throughput per bottleneck minute = (Selling price − Totally variable cost) ÷ Bottleneck minutes per unit

TOC throughput should not automatically be equated with conventional contribution margin. Whether labour and overhead are treated as fixed operating expense or variable cost depends on whether they genuinely change over the decision horizon.

TOC also warns against maximizing local machine utilization. Producing excess output at a non-bottleneck may merely create inventory, delay flow, and conceal quality problems. The relevant objective is improvement in whole-system throughput, inventory, and operating expense.

9. Integrated Illustrative Case: Atlas Medical Components

Background

Atlas Medical Components is a fictional manufacturer with 3,000 machine hours available next month. It produces products P and Q. The variable-cost data deliberately distinguish manufacturing costs from selling costs.

Item per unitProduct PProduct Q
Selling price$80$68
Direct material$20$14
Direct labour$12$10
Variable manufacturing overhead$8$6
Variable selling commission on regular sales$4$3
Total variable cost of regular sales$44$33
Regular contribution margin$36$35
Machine hours21
Maximum regular demand900 units1,800 units

A hospital offers to buy 400 specially labelled units of Q for $55 each. No selling commission applies, but special packaging costs $2 per unit and a batch setup costs $1,000. The order uses the same one machine hour per Q unit.

Problem

Management initially argues that the order can be accepted because its price exceeds Q’s $30 variable manufacturing cost. This reasoning overlooks both special-order costs and the fact that the regular product plan already uses all machine capacity.

Analysis of the regular mix

  • P contributes $36 ÷ 2 = $18 per machine hour.
  • Q contributes $35 ÷ 1 = $35 per machine hour.

Q is produced first to its maximum demand: 1,800 units use 1,800 hours and contribute $63,000. The remaining 1,200 hours produce 600 units of P, contributing $21,600. Total regular contribution is $84,600, and all 3,000 hours are used.

Analysis of the hospital order

Each special Q unit generates contribution before capacity displacement of:

$55 − $30 manufacturing cost − $2 packaging = $23

For 400 units, this equals $9,200. The order consumes 400 machine hours. Because regular Q is already prioritized and sold to maximum demand, the displaced product is P. Four hundred hours would have produced 200 P units, sacrificing 200 × $36 = $7,200 contribution.

After including setup cost:

Incremental profit = $9,200 − $7,200 − $1,000 = $1,000

The revised mix is 1,800 regular Q units, 400 special Q units, and 400 P units. Its total contribution after the setup cost is:

$63,000 + $9,200 + $14,400 − $1,000 = $85,600

This is $1,000 above the regular-only plan.

Recommendation and outcome

Atlas should accept the order on the stated financial assumptions. However, the $1,000 advantage is small. Management should confirm packaging specifications, credit risk, delivery reliability, regulatory compliance, and whether the hospital price could affect future negotiations.

Learning points

  • Variable manufacturing cost and total regular variable cost are not interchangeable; Q’s $30 manufacturing cost excludes its $3 regular-sales commission.
  • Fully used capacity creates an opportunity cost even when an order covers its direct costs.
  • Special-order and product-mix decisions must be analyzed simultaneously when they use the same constrained resource.
  • A narrow financial advantage should be tested for risk and strategic consequences.

10. Risk, Uncertainty, and Sensitivity

Relevant-cost estimates are rarely certain. Demand, defect rates, supplier performance, exchange rates, processing yields, downtime, and resale values may vary.

For discrete scenarios, expected incremental profit is:

E(Δπ) = ∑s=1S psΔπs

where ps is the probability of scenario s, Δπs is its incremental profit, and the probabilities sum to 1. Expected value is useful for repeated or risk-neutral decisions but does not describe downside severity or managerial risk tolerance.

Sensitivity analysis changes one assumption at a time. Scenario analysis changes coherent groups of assumptions. Break-even analysis identifies the value at which alternatives are financially equivalent. For example, the minimum special-order price under constrained capacity is:

Minimum price = Incremental unit cost + Unit opportunity cost + Required incremental profit per unit

Simulation can model interacting uncertainties, but its output is only as credible as its assumptions and data.

11. Quality, Ethics, Governance, and Technology

Relevant costing can be manipulated through optimistic forecasts, selective exclusion of transition costs, or arbitrary descriptions of capacity as idle. Good governance requires documented assumptions, independent review, clear accountability, and post-decision comparison of actual outcomes with forecasts.

Ethical and regulatory considerations include:

  • truthful communication of quality and delivery capability;
  • compliance with labour, environmental, procurement, and competition laws;
  • fair treatment of employees affected by outsourcing or shutdown;
  • protection of customer and supplier data;
  • avoidance of bribery and undisclosed conflicts in supplier selection; and
  • consideration of safety and product reliability, even when failures appear financially unlikely.

Modern enterprise systems can integrate capacity, cost, demand, and supplier data. Optimization software can solve large product-mix models, while AI can identify cost drivers, forecast disruptions, and generate scenarios. These tools should support rather than replace managerial judgment. Data lineage, explainability, model validation, access controls, and human authorization remain essential.

12. Common Pitfalls and Best Practices

Common errors include using absorption cost per unit as a decision cost, ignoring opportunity cost, assuming all fixed costs disappear, accepting low-price orders despite constrained capacity, allocating joint costs to further-processing decisions, and comparing replacement alternatives without the new asset’s operating costs or relevant terminal values.

Best practice is to prepare an incremental schedule showing only differences between alternatives, reconcile it to operational capacity, state the time horizon, disclose excluded common costs, test sensitivity, and record important qualitative considerations. When decisions interact, they should be modelled jointly rather than assessed in isolation.

Chapter Summary

Relevant costing focuses on future revenues and costs that differ between alternatives. Sunk costs and unavoidable allocations are excluded, while avoidable costs and opportunity costs are included. Make-or-buy analysis compares avoidable internal cost plus capacity opportunity cost with the total incremental cost of external supply. Special orders require attention to incremental order costs and displaced contribution when capacity is constrained.

Shutdown decisions compare operating-specific and shutdown-specific cash flows. Joint costs incurred before split-off do not affect further-processing decisions. Replacement analysis requires the new investment, disposal proceeds, net revenue and operating-cost differences, working capital, discounting from t = 1 to n, and relevant terminal values.

Under one limiting factor, products are ranked by contribution per unit of scarce resource. Multiple constraints generally require linear or integer programming. Theory of constraints emphasizes throughput at the bottleneck and whole-system flow. Financial calculations must ultimately be combined with risk, quality, ethics, resilience, and strategic analysis.

Key Terms

Relevant cost: A future cost that differs between alternatives.

Relevant revenue: Future revenue that changes because of the decision.

Incremental cost: Additional cost resulting from an alternative.

Differential cost: Difference in cost between two alternatives.

Avoidable cost: Cost eliminated when an activity is discontinued.

Sunk cost: Past, irreversible cost that is irrelevant to the current choice.

Opportunity cost: Benefit sacrificed by selecting one use of a resource over another.

Unavoidable cost: Cost that remains under all considered alternatives.

Special order: Non-routine customer order evaluated using incremental analysis.

Split-off point: Stage at which joint products become separately identifiable.

Joint cost: Common processing cost incurred before split-off.

Limiting factor: Resource whose restricted availability constrains output.

Contribution margin: Sales revenue less costs that vary with the relevant activity.

Shadow price: Marginal objective improvement from one more unit of a constrained resource within an allowable range.

Throughput: Under TOC, sales revenue less totally variable cost.

Bottleneck: Resource that limits the system’s output rate.

Terminal value: Net cash flow associated with an asset at the end of the evaluation horizon.

Sensitivity analysis: Assessment of how results change when an assumption changes.

Review Questions

Short Answer Questions

  1. State the two conditions that make a cost relevant.
  2. Why is allocated fixed overhead not automatically relevant to a make-or-buy decision?
  3. Define opportunity cost in the context of constrained capacity.
  4. Why are joint costs excluded from a further-processing decision?
  5. Distinguish conventional contribution margin from TOC throughput.

Long Answer Questions

  1. Explain how financial and strategic considerations should be integrated in an outsourcing decision.
  2. Discuss the analysis of a special order under idle and fully utilized capacity.
  3. Explain the cash flows required in an equipment-replacement NPV model.
  4. Evaluate the assumptions underlying contribution per limiting-factor analysis.
  5. Discuss governance, ethical, and data-quality risks in technology-assisted relevant-cost analysis.

Analytical / Application Questions

  1. A component has avoidable internal costs of $18 per unit. A supplier charges $19, and outsourcing 8,000 units would free capacity earning $24,000 contribution. Determine the preferred alternative and annual financial advantage.
  2. A product can be sold at split-off for $90,000 or processed into output worth $126,000. Further processing costs $31,000 and requires capacity with an opportunity cost of $7,000. Recommend an alternative and quantify its effect.
  3. Products X and Y contribute $48 and $30 per unit and require four and two bottleneck hours respectively. Maximum demand is 300 X and 500 Y, and 1,400 hours are available. Determine the optimal mix and total contribution under the single-constraint assumptions.

Multiple Choice Questions with Answers

Question 1

Which condition is necessary for a cost to be relevant to a managerial decision?

A. It must be recorded in the general ledger.

B. It must be a future amount that differs between alternatives.

C. It must be classified as variable under absorption costing.

D. It must have been allocated to a product.

Correct Answer: B. It must be a future amount that differs between alternatives.

Question 2

A component has avoidable manufacturing costs of $11 per unit. A supplier charges $12.50 per unit. Buying would release capacity earning contribution of $2 per component. Which alternative is financially preferable?

A. Make, because its accounting cost is lower by $1.50.

B. Make, because opportunity cost is irrelevant.

C. Buy, because making has an economic cost of $13 per component.

D. The alternatives are financially equivalent.

Correct Answer: C. Buy, because making has an economic cost of $13 per component.

Question 3

A special order for 500 units offers $30 per unit. Incremental production and delivery cost is $24 per unit, and idle capacity is available. No other costs change. What is the order's incremental profit?

A. $3,000

B. $12,000

C. $15,000

D. $27,000

Correct Answer: A. $3,000

Question 4

Product A contributes $40 per unit and requires four bottleneck hours. Product B contributes $30 per unit and requires two bottleneck hours. Under a single binding constraint, which product should receive priority?

A. A, because it has the higher unit contribution.

B. A, because it uses more bottleneck hours.

C. B, because it contributes $15 per bottleneck hour compared with A's $10.

D. Neither, because unit contribution cannot be used in product-mix decisions.

Correct Answer: C. B, because it contributes $15 per bottleneck hour compared with A's $10.

Question 5

A joint product can be sold at split-off for $50,000 or after further processing for $71,000. Further processing costs $18,000. What is the financial effect of processing further?

A. A $3,000 increase in profit

B. An $18,000 decrease in profit

C. A $21,000 increase in profit

D. A $53,000 increase in profit

Correct Answer: A. A $3,000 increase in profit

Question 6

Operating for one month would generate revenue of $100,000, variable costs of $55,000, and fixed costs avoidable on shutdown of $38,000. Shutdown itself would cost $4,000. What is the advantage of continuing rather than shutting down?

A. $3,000

B. $7,000

C. $11,000

D. $49,000

Correct Answer: C. $11,000

Question 7

A replacement machine costs $80,000, and the old machine can be sold now for $10,000. Annual net operating-cost savings are $30,000 for three years. The three-year annuity factor is 2.4869. The new machine's terminal value exceeds the old machine's by $5,000, with a year-3 discount factor of 0.7513. What is the replacement NPV, before tax?

A. $3,756

B. $4,607

C. $8,364

D. $78,364

Correct Answer: C. $8,364

Question 8

In the Atlas case, why does the hospital order have an opportunity cost?

A. The hospital does not pay the regular selling commission.

B. The order displaces product P because all machine hours are already used.

C. Product Q has allocated fixed overhead.

D. The order's price is below the regular price of Q.

Correct Answer: B. The order displaces product P because all machine hours are already used.

Question 9

Under the theory of constraints, throughput per bottleneck minute is generally calculated as:

A. Sales revenue divided by total factory hours.

B. Absorption profit divided by units produced.

C. Selling price less totally variable cost, divided by bottleneck minutes.

D. Contribution per unit divided by non-bottleneck minutes.

Correct Answer: C. Selling price less totally variable cost, divided by bottleneck minutes.

Question 10

What does a linear-programming shadow price represent?

A. The historical purchase price of a constrained asset

B. The unavoidable fixed cost allocated to a product

C. The objective improvement from one additional resource unit within the allowable range

D. The maximum selling price that customers will accept

Correct Answer: C. The objective improvement from one additional resource unit within the allowable range

Advanced Cost & Management Accounting
Chapter 8 of 15