Accounting Information Systems & ERP

Chapter 11
ERP Selection, Implementation and Change Management

Bachelors Program in Accounting and Finance
Accounting Information Systems & ERP   •   Bachelor

ERP Selection, Implementation and Change Management

Introduction

Enterprise resource planning (ERP) systems integrate accounting, procurement, sales, inventory, production, human resources and other organizational processes through shared data and standardized workflows. For accounting and finance professionals, ERP implementation is not merely an information technology project. It reshapes transaction processing, internal controls, financial reporting, job responsibilities and managerial information.

ERP projects are difficult because they combine technical configuration with organizational change. An apparently successful installation can still fail if requirements are unclear, data are unreliable, controls are weakened, users are unprepared or expected benefits are not realized. A disciplined systems development life cycle (SDLC) provides the structure needed to manage these risks.

This chapter applies the SDLC to ERP requirements analysis, vendor selection, business-case evaluation, process redesign, fit-gap analysis, data migration, testing, deployment, training and post-implementation review.

Learning Objectives

After studying this chapter, students should be able to:

  1. Explain how the SDLC applies to ERP acquisition and implementation.
  2. Translate business needs into functional, non-functional and control requirements.
  3. Evaluate ERP vendors using structured and evidence-based methods.
  4. prepare a financial and strategic ERP business case.
  5. Conduct process redesign and fit-gap analysis.
  6. Plan data migration, testing and deployment.
  7. Apply change-management principles to communication and training.
  8. Evaluate governance, ethical and control issues throughout implementation.
  9. Design a post-implementation review and benefits-realization process.

1. ERP Implementation Through the Systems Development Life Cycle

The SDLC is a structured approach for defining, developing, acquiring, testing, deploying and reviewing an information system. ERP projects usually involve package acquisition and configuration rather than development entirely from source code, but the SDLC remains applicable.

SDLC phasePrincipal ERP activitiesTypical outputs
InitiationDefine problem, scope and sponsorshipProject charter, preliminary case
AnalysisExamine processes and requirementsRequirements catalogue, process maps
Selection and designEvaluate vendors and design future processesVendor decision, target design
Build and configureConfigure modules, integrations and controlsConfigured solution
TestingVerify functionality, controls and performanceTest evidence, defect register
DeploymentMigrate data and move into productionLive system, cutover report
Operation and reviewStabilize, measure benefits and improvePost-implementation review

ERP implementation is iterative. Testing may reveal a misunderstood requirement, while data cleansing may expose weaknesses in existing processes. Formal control over changes is therefore necessary even when an agile or hybrid delivery method is used.

ERP implementation life cycle Initiate andgovern Analyzerequirements Select anddesign Configureand migrate Test anddeploy Stabilize, reviewand improve Feedback, corrective action and continuous improvement
ERP implementation life cycle from initiation to post-implementation review
Figure: ERP implementation life cycle from initiation to post-implementation review

Figure: ERP implementation life cycle with feedback from operational review to renewed analysis.

2. Project Initiation and Governance

2.1 Defining the problem and scope

A project should begin with a business problem or opportunity, not with a preferred product. Relevant questions include:

  • Which reporting, control or operational weaknesses must be addressed?
  • Which legal entities, sites, processes and modules are in scope?
  • What outcomes will define success?
  • Which constraints apply to budget, time, regulation and technology?

Scope should specify both inclusions and exclusions. A project described only as “implement a new ERP” invites uncontrolled expansion. A stronger scope might cover general ledger, accounts payable, procurement and inventory for three domestic entities, while excluding payroll and overseas subsidiaries from the first release.

2.2 Governance structure

The governing body, usually a steering committee, approves scope, funding, major design decisions and risk responses. It should include executive sponsorship, finance, operations, technology, internal control and affected business units.

Key roles include:

  • Executive sponsor: owns the business outcome and removes organizational barriers.
  • Project manager: coordinates scope, schedule, resources, risks and dependencies.
  • Process owner: accepts the future process and its performance.
  • Finance and control lead: safeguards accounting integrity and internal controls.
  • Data owner: approves definitions, quality standards and migration results.
  • Change lead: coordinates stakeholder engagement, communication and training.
  • Independent assurance function: evaluates whether project governance and controls are effective.

Decision rights should be explicit. A responsibility assignment matrix can distinguish who is responsible, accountable, consulted and informed for each deliverable.

3. Requirements Analysis

Requirements analysis converts organizational needs into verifiable statements. Requirements should be clear, feasible, prioritized, traceable and testable.

3.1 Categories of requirements

Functional requirements specify what the system must do. Examples include calculating sales tax, generating consolidation journals and matching purchase orders, goods receipts and supplier invoices.

Non-functional requirements specify qualities or constraints such as availability, response time, scalability, usability and recovery time. For example, “The system shall return an approved trial-balance query within five seconds for 95% of normal-period requests.”

Control requirements specify safeguards supporting authorization, completeness, accuracy, validity, confidentiality and auditability. Examples include segregation-of-duties rules, approval limits, immutable posting logs and automated duplicate-invoice checks.

Data requirements define master and transactional data, ownership, validation, retention and reporting dimensions.

Interface requirements identify exchanges with banks, tax platforms, customer portals, payroll applications and data warehouses.

Compliance requirements arise from financial reporting, taxation, privacy, record-retention and sector-specific obligations.

A requirement may support more than one concern. For example, auditability is a non-functional quality, but an immutable audit trail may be documented specifically as a control requirement. The project should classify each requirement consistently and assign a clear owner rather than assume that categories are always mutually exclusive.

3.2 Requirements elicitation

Common techniques include interviews, workshops, observation, document analysis, questionnaires, transaction sampling and system-log analysis. Workshops are useful for cross-functional processes because participants can expose conflicting assumptions. Observation is important where actual work differs from documented procedures.

Requirements should describe business outcomes rather than reproduce every feature of the legacy system. Copying obsolete practices into a new ERP preserves complexity rather than creating value.

3.3 Prioritization and traceability

The MoSCoW method classifies requirements as must have, should have, could have or will not have in the current release. “Must have” should be reserved for genuinely essential legal, operational or control needs.

A requirements traceability matrix links each requirement to its source, process, design decision, configuration item, test case and acceptance result. Traceability reduces the risk that essential controls disappear between analysis and deployment.

4. Vendor and Solution Selection

ERP selection should be transparent and based on evidence. The process commonly includes market scanning, a request for information, a shortlist, a request for proposal, scripted demonstrations, reference checks, technical due diligence and contract negotiation.

4.1 Weighted scoring

A weighted score can summarize evaluations:

Sj = ∑i=1n wi rij

where Sj is the total score for vendor j, wi is the weight assigned to criterion i, and rij is vendor j’s rating on criterion i. Weights should sum to 1, and all ratings must use the same scale.

Suppose functionality, total cost, implementation capability and security receive weights of 0.40, 0.25, 0.20 and 0.15. A vendor rated 8, 6, 9 and 7 out of 10 receives:

S = (0.40 × 8) + (0.25 × 6) + (0.20 × 9) + (0.15 × 7) = 7.55

The score supports rather than replaces judgment. A high aggregate score must not compensate for failure against a mandatory legal or security requirement. Mandatory thresholds should therefore be evaluated before weighted scoring.

4.2 Demonstrations and due diligence

Vendor demonstrations should follow customer-defined scenarios and use representative data. Unscripted demonstrations often emphasize attractive features while avoiding difficult requirements.

Due diligence should examine:

  • product roadmap and financial viability;
  • implementation partner competence;
  • integration architecture and data portability;
  • security certifications and incident procedures;
  • service availability and disaster recovery;
  • upgrade policies and customization constraints;
  • references from comparable organizations;
  • contractual rights, service levels and exit arrangements.

For cloud ERP, the organization remains accountable for its information even when infrastructure is outsourced. Contracts should address data location, privacy, breach notification, subcontractors, availability, backup, audit rights and secure data return or destruction.

5. Business-Case Evaluation

The business case integrates strategic, operational, financial and risk considerations. Costs may include licenses or subscriptions, implementation services, internal labor, interfaces, data cleansing, training, temporary productivity losses, support and future upgrades. Benefits may include lower processing cost, shorter closing cycles, improved working-capital management, avoided legacy costs and better decision information.

5.1 Net present value

For a project with an initial investment followed by annual net cash flows, net present value (NPV) is:

NPV = -I0 + ∑t=1T CFt/(1+r)t

where I0 is the initial cash outflow in currency units, CFt is net cash flow in period t, r is the discount rate per period, and T is the number of periods. Cash flows and the discount rate must use consistent periods and nominal or real assumptions. Under the NPV rule, a financially independent project is acceptable if NPV is positive, subject to strategic, risk and capital constraints.

Worked example: ERP investment appraisal

An organization expects an ERP implementation to require an immediate investment of $400,000. Expected net cash benefits are $150,000, $166,800 and $190,000 at the end of years 1, 2 and 3. At a 10% annual discount rate:

NPV = -400,000 + 150,000/1.10 + 166,800/1.102 + 190,000/1.103

The present values are:

  • Year 1: $150,000 ÷ 1.10 = $136,363.64
  • Year 2: $166,800 ÷ 1.21 = $137,851.24
  • Year 3: $190,000 ÷ 1.331 ≈ $142,749.81

Therefore:

NPV ≈ -400,000 + 136,363.64 + 137,851.24 + 142,749.81 = 16,964.69

The positive NPV indicates expected financial value of approximately $16,965. However, the result depends on uncertain estimates. Sensitivity analysis should test changes in benefits, implementation cost, delay and discount rate.

5.2 Limits of financial appraisal

Some benefits, such as regulatory resilience and better information, are difficult to quantify. Conversely, projected labor savings may not become cash savings unless positions, overtime or external spending actually decrease. Benefits should therefore have named owners, baseline measures, target dates and measurement methods.

6. Business Process Redesign and Fit-Gap Analysis

ERP implementation creates an opportunity to redesign end-to-end processes. A process should be analyzed across departmental boundaries, because local optimization can harm overall performance.

An “as-is” process map records current activities, decisions, handoffs, delays, controls and systems. The “to-be” design should simplify work, remove unnecessary approvals, automate valid controls and clarify ownership.

6.1 Fit-gap analysis

Fit-gap analysis compares requirements and target processes with standard ERP capability. Each item may be classified as:

  • Fit: standard configuration satisfies the requirement.
  • Partial fit: configuration satisfies only part of it.
  • Gap: standard capability does not satisfy it.
  • Process adaptation: the organization changes its process to use standard functionality.
  • Extension or integration: an approved addition addresses a justified need.

Possible gap responses include changing the process, configuring the package, using a controlled workaround, integrating another application, developing an extension or rejecting the solution.

Customization should be governed carefully. It may protect a genuinely distinctive process or legal requirement, but it also increases testing, maintenance and upgrade costs. The burden of proof should usually rest on the proposal to customize rather than on adoption of the standard process.

7. Configuration, Controls and Data Migration

7.1 Configuration and internal control

Important configuration areas include the chart of accounts, fiscal calendars, tax rules, approval workflows, posting periods, organizational structures and role permissions. Configuration decisions should be documented and approved.

Segregation of duties prevents one individual from controlling incompatible stages of a transaction. Examples of conflicts include creating a supplier and releasing its payment, or creating a customer credit note and approving it. Role design should apply least privilege and be tested before access is granted.

Automated controls should not be assumed effective merely because they exist in the software. Their configuration, access restrictions, exception handling and evidence must also be assessed.

7.2 Data migration process

Data migration normally follows these steps:

  1. Discover: identify source systems, data owners and dependencies.
  2. Profile: measure missing, invalid, duplicate and inconsistent values.
  3. Cleanse: correct errors and resolve duplicates.
  4. Map: define source-to-target fields and transformation rules.
  5. Extract and transform: produce controlled migration files.
  6. Load: import data into the target environment.
  7. Validate and reconcile: compare migrated results with approved sources.
  8. Approve: obtain business and data-owner sign-off.

A simple completeness reconciliation is:

∆N = Ntarget - Napproved\ source

where Ntarget is the number of accepted target records and Napproved\ source is the number expected from the approved source population. A zero difference supports record-count completeness but does not prove accuracy.

Financial migration should also reconcile monetary totals. For example, the sum of migrated open supplier balances should equal the approved legacy control total after documented exclusions and transformations. Hash totals, control totals and sample-based field checks provide additional evidence.

Data cleansing decisions have ethical consequences. Records must not be altered merely to make migration metrics appear favorable. Personal data should be minimized, protected and retained only as authorized.

8. Testing and Quality Assurance

Testing provides evidence that the configured ERP system is suitable for intended use. A risk-based test strategy should give greater attention to high-value transactions, regulatory processes, complex integrations and key controls.

Test typePrincipal purpose
Unit/configuration testingVerify individual rules and configurations
System integration testingVerify end-to-end flows across modules and interfaces
Data migration testingVerify transformed data and reconciliation
Security and control testingVerify permissions, workflows and audit evidence
Performance testingAssess response times, throughput and capacity
User acceptance testingConfirm that authorized users can perform agreed business scenarios
Regression testingConfirm that changes have not damaged previously working functions
Disaster-recovery testingVerify recovery procedures and recovery objectives

A test case should state its requirement reference, preconditions, input data, procedure, expected result, actual result and evidence. Defects should be classified by severity and managed to closure or formally accepted risk.

User acceptance testing (UAT) is not casual exploration. Business representatives should execute realistic scenarios, including exceptions such as rejected invoices, currency differences, closed accounting periods and unauthorized access attempts. Acceptance criteria must be defined before testing begins.

9. Deployment and Cutover

Deployment strategies include:

  • Direct cutover: the old system is replaced at a specified time. It is fast but creates concentrated risk.
  • Parallel operation: both systems operate temporarily. It provides comparison but is costly and may produce inconsistent processing.
  • Phased deployment: modules, sites or entities move in stages. This limits exposure but requires temporary interfaces and coordination.
  • Pilot deployment: one business unit adopts the system before wider rollout. Learning is valuable, although the pilot may not represent every context.

The cutover plan should identify tasks, owners, timing, dependencies and decision checkpoints. Typical activities include transaction freezes, final extraction, data loading, reconciliation, access activation, interface scheduling, communication and contingency preparation.

A formal go/no-go decision should consider critical defects, reconciliation status, user readiness, support staffing, system performance, security approval and rollback feasibility. Schedule pressure must not override material control deficiencies.

After go-live, a temporary stabilization or “hypercare” period provides increased support, rapid issue triage and daily monitoring. Hypercare should have an exit criterion so that the project does not conceal unresolved structural problems indefinitely.

10. Change Management, Communication and Training

ERP projects alter routines, authority, performance measures and professional identities. Resistance may reflect rational concerns about workload, job security, control or system usability. Treating all resistance as irrational can prevent management from discovering genuine design flaws.

10.1 Change-management models

Lewin’s model describes change as unfreezing established behavior, moving to a new state and refreezing new practices. It is useful conceptually but may understate the continuing change experienced in cloud ERP environments.

The ADKAR model focuses on individual change through awareness, desire, knowledge, ability and reinforcement. It helps diagnose why a stakeholder group is not adopting the new process. For example, training addresses knowledge but will not resolve a lack of awareness or incentives.

10.2 Stakeholder analysis and communication

Stakeholders can be assessed by influence, impact and attitude. Communication should be tailored rather than limited to general announcements. Employees need to know why the change is occurring, how roles will change, when action is required and where support is available.

Change champions can provide local feedback and demonstrate new practices. However, they do not replace accountable managers or formal support channels.

10.3 Training design

Effective training is role-based, process-oriented and timed near actual use. It should combine explanation, demonstration, guided practice, independent practice and assessment. Training environments should contain realistic but protected data.

Competence should be measured rather than inferred from attendance. Assessment might require an accounts-payable employee to create an invoice, resolve a match exception, obtain approval and interpret the resulting accounting entry.

Training also supports internal control. Users should understand not only which buttons to select but why approval limits, supporting documents and access restrictions exist.

11. Post-Implementation Review and Benefits Realization

A post-implementation review (PIR) evaluates whether the project delivered an effective system and expected outcomes. It is distinct from daily stabilization and should normally occur after sufficient operational experience has accumulated.

A PIR should examine:

  • achievement of scope, schedule and cost targets;
  • reliability, performance and user adoption;
  • control effectiveness and unresolved security risks;
  • data quality and reconciliation;
  • realized benefits compared with the business case;
  • vendor and implementation-partner performance;
  • lessons for future projects.

Benefits realization continues after project closure. Each benefit should have an owner, baseline, target, data source and review frequency. For example, if the target is to reduce the monthly close from ten working days to six, the organization should define when the close begins and ends and measure the result consistently.

The PIR should encourage organizational learning rather than blame. Nevertheless, material unresolved risks require named actions, deadlines and escalation.

12. Governance, Ethics and Contemporary Developments

ERP governance must address privacy, cybersecurity, reliable financial reporting, accountability and vendor dependence. Management should prevent privileged administrators from making unreviewed production changes, maintain audit logs and periodically recertify access.

Ethical concerns arise when implementations enable intrusive employee monitoring, embed biased automated decisions or use customer data beyond its authorized purpose. Transparency, necessity, proportionality and human oversight are important safeguards.

Contemporary ERP systems increasingly use artificial intelligence for invoice capture, anomaly detection, forecasting and user assistance. AI outputs require validation. An anomaly alert is not proof of fraud, while a generated accounting recommendation is not a substitute for professional judgment. Governance should cover model access, data quality, explainability, monitoring and responsibility for decisions.

Cloud platforms also encourage continuous updates rather than infrequent major upgrades. Organizations therefore need permanent regression testing, release assessment and change communication capabilities. Composable ERP architectures can improve flexibility through modular services and application programming interfaces, but may increase integration, data-governance and vendor-management complexity.

13. Illustrative Case: Northstar Manufacturing

Background

Northstar Manufacturing is a fictional mid-sized producer operating three plants. It uses separate accounting, procurement and inventory applications. Monthly consolidation requires spreadsheets, supplier records are duplicated and inventory reports disagree with general-ledger balances.

Problem

Management initially proposed purchasing the least expensive ERP within six months. The finance director objected because requirements, controls and data quality had not been assessed. A diagnostic review found inconsistent item codes, excessive user privileges and 17 different purchase-approval practices.

Analysis

The steering committee defined the objectives as reducing the monthly close from 12 to 7 working days, establishing one supplier master, improving inventory reconciliation and standardizing purchase-to-pay controls. Requirements workshops identified mandatory tax, approval, traceability and plant-availability requirements.

Three shortlisted vendors completed scripted demonstrations. One vendor had the highest functionality score but failed the mandatory recovery-time requirement. It was therefore excluded before weighted scoring. The selected solution met mandatory conditions and offered the strongest standard manufacturing integration.

Fit-gap analysis found 84% of prioritized requirements could be met through standard configuration. Northstar changed several local approval practices to use a common workflow. Two extensions were approved: a legally required environmental report and an interface to specialized plant equipment.

Approach and solution

Data owners cleansed supplier and inventory masters. Duplicate suppliers were merged only after tax identifiers, bank details and outstanding balances were reviewed. Three trial migrations were reconciled by record count and monetary control totals.

Testing covered procure-to-pay, order-to-cash, production, period-end close, role conflicts and recovery procedures. During UAT, employees discovered that urgent maintenance purchases could not be approved outside normal hours. The workflow was corrected with controlled delegation rather than bypass access.

Northstar adopted a plant pilot followed by phased rollout. Role-based training required users to pass practical exercises. A go-live readiness review delayed the second plant by two weeks because inventory reconciliation remained outside tolerance.

Outcome

Six months after full deployment, the monthly close averaged seven working days, duplicate supplier creation had fallen substantially and inventory differences were reported through a common dashboard. Some forecast benefits were delayed because managers continued exporting data to personal spreadsheets. The post-implementation review assigned process owners to eliminate unnecessary shadow systems and improve analytics training.

Learning points

The case demonstrates that disciplined delay may protect value better than schedule compliance, mandatory requirements should precede aggregate vendor scores, data quality requires business ownership, and benefits depend on sustained process adoption rather than technical go-live alone.

Chapter Summary

ERP implementation is a business transformation governed through the systems development life cycle. Effective projects begin with defined outcomes, scope, governance and testable requirements. Vendor selection should combine mandatory thresholds, weighted evaluation, scripted demonstrations and due diligence. The business case must include total costs, risk and measurable benefits, supported where appropriate by NPV and sensitivity analysis.

Process redesign and fit-gap analysis determine whether the organization should adopt standard ERP practices, configure the system or approve justified extensions. Data migration requires profiling, cleansing, mapping, controlled loading and reconciliation. Testing must cover functionality, integration, data, controls, performance and user acceptance. Deployment choices should reflect organizational risk and readiness.

Change management, communication and role-based training are essential because ERP success depends on altered behavior as well as technology. Post-implementation review and benefits realization extend accountability beyond go-live. Governance must also address internal control, privacy, cybersecurity, ethical data use, cloud dependence and the responsible use of AI.

Key Terms

Business case: A documented justification integrating costs, benefits, risks and strategic considerations.

Business process redesign: Systematic analysis and improvement of end-to-end organizational processes.

Configuration: Setting ERP parameters and rules without changing the core source code.

Cutover: The controlled transition from a legacy system to the production ERP system.

Data migration: Extraction, cleansing, transformation, loading and validation of data in a new system.

ERP: Integrated software supporting multiple organizational functions through shared processes and data.

Fit-gap analysis: Comparison of business requirements with standard system capabilities.

Functional requirement: A statement describing what a system must do.

Hypercare: A temporary period of intensified support immediately after deployment.

Non-functional requirement: A statement describing a system quality or operating constraint.

Post-implementation review: A formal evaluation of project delivery, system performance and realized benefits.

Regression testing: Testing that determines whether a change has damaged previously functioning capabilities.

Requirements traceability matrix: A record linking requirements to design, configuration, tests and acceptance.

Segregation of duties: Separation of incompatible responsibilities to reduce error and fraud risk.

System development life cycle: A structured process for initiating, analyzing, acquiring, implementing and reviewing systems.

Total cost of ownership: The full cost of acquiring, operating, supporting and eventually retiring a system.

User acceptance testing: Business-user testing that confirms the system supports agreed processes and requirements.

Weighted scoring model: A method that combines criterion weights and vendor ratings into comparable scores.

Review Questions

Short Answer Questions

  1. Distinguish functional, non-functional and control requirements.
  2. What is the purpose of a requirements traceability matrix?
  3. Why should mandatory criteria be assessed before weighted vendor scoring?
  4. Identify four activities included in data migration.
  5. What is the purpose of a post-implementation review?

Long Answer Questions

  1. Explain how the SDLC can be applied to ERP selection and implementation.
  2. Discuss the financial and non-financial components of an ERP business case.
  3. Evaluate the advantages and risks of ERP customization.
  4. Compare direct, parallel, phased and pilot deployment strategies.
  5. Explain how change management and training contribute to control effectiveness and benefits realization.

Analytical / Application Questions

  1. An organization has selected an ERP that satisfies most functional requirements but fails a mandatory privacy requirement. Analyze the appropriate decision and possible responses.
  2. Design a migration reconciliation plan for open customer balances, including completeness and accuracy checks.
  3. A company has gone live on schedule, but employees continue using legacy spreadsheets and closing time has not improved. Diagnose the likely causes and recommend corrective actions.

Multiple Choice Questions with Answers

Question 1

Which document most directly links an ERP requirement to its configuration, test case and acceptance result?

A. Requirements traceability matrix

B. Vendor marketing brochure

C. Organization chart

D. General ledger

Correct Answer: A. Requirements traceability matrix

Question 2

Which is the clearest example of a non-functional ERP requirement?

A. The system must calculate value-added tax on taxable invoices

B. The system must require two approvals for payments above $50,000

C. The system must return 95% of standard account queries within five seconds

D. The system must generate a supplier payment journal

Correct Answer: C. The system must return 95% of standard account queries within five seconds

Question 3

Why should a vendor that fails a mandatory regulatory requirement normally be excluded before weighted scoring?

A. Weighted scores are used only for hardware purchases

B. A high score elsewhere cannot compensate for regulatory non-compliance

C. Regulatory requirements do not require testing

D. All vendors should receive identical scores

Correct Answer: B. A high score elsewhere cannot compensate for regulatory non-compliance

Question 4

An ERP project costs $100,000 immediately and generates $55,000 at the end of each of the next two years. At a 10% annual discount rate, what is its NPV?

A. $4,545.45

B. −$10,000.00

C. −$4,545.45

D. $10,000.00

Correct Answer: C. −$4,545.45

Question 5

A vendor is rated 8, 6 and 9 on criteria weighted 0.50, 0.30 and 0.20, respectively. What is its weighted score?

A. 7.20

B. 7.60

C. 7.80

D. 8.10

Correct Answer: B. 7.60

Question 6

Which test most directly confirms that transactions flow correctly across procurement, inventory and general-ledger modules?

A. System integration testing

B. Employee aptitude testing

C. Vendor reference checking

D. Benefits-realization testing

Correct Answer: A. System integration testing

Question 7

Which deployment strategy introduces the ERP first in one selected business unit before wider rollout?

A. Direct cutover

B. Parallel operation

C. Pilot deployment

D. Full simultaneous deployment

Correct Answer: C. Pilot deployment

Question 8

Which data migration result provides evidence of completeness but does not by itself prove accuracy?

A. The target record count equals the approved source record count

B. Every user attended training

C. The vendor signed the implementation contract

D. The project remained within its travel budget

Correct Answer: A. The target record count equals the approved source record count

Question 9

Which role combination creates the clearest segregation-of-duties conflict?

A. Reviewing financial reports and preparing a budget

B. Creating a supplier and releasing payments to that supplier

C. Entering a purchase requisition and viewing inventory

D. Approving annual leave and attending ERP training

Correct Answer: B. Creating a supplier and releasing payments to that supplier

Question 10

What is the primary purpose of a post-implementation review?

A. To repeat vendor selection after every reporting period

B. To replace all operational support activities

C. To assess project outcomes, controls, performance and realized benefits

D. To eliminate the need for future system changes

Correct Answer: C. To assess project outcomes, controls, performance and realized benefits